The LAX Automated People Mover is an under construction automated people mover (APM) system that will serve the area around Los Angeles International Airport (LAX).
LAX Automated People Mover | |||
---|---|---|---|
Overview | |||
Status | Under construction | ||
Owner | Los Angeles World Airports (LAWA) | ||
Locale | Los Angeles International Airport (LAX) | ||
Stations | 6 | ||
Website | lalinxs | ||
Service | |||
Type | Automated people mover | ||
Operator(s) | LAX Integrated Express Solutions (LINXS) | ||
Rolling stock | Alstom Innovia APM 300 | ||
History | |||
Planned opening | January 2026[1] | ||
Technical | |||
Line length | 2.25 mi (3.62 km) | ||
Number of tracks | 2 | ||
Character | Fully elevated | ||
Operating speed |
| ||
|
The system will be owned by Los Angeles World Airports (LAWA) and operated by LAX Integrated Express Solutions (LINXS). The line will run for 2.25 miles (3.62 km) and have six stations that connect the LAX Consolidated Rent-A-Car Facility (ConRAC), the Los Angeles Metro Rail system, and the LAX West Intermodal Transportation Facility (West ITF) with the airport's central terminal area (CTA).
The line was initially planned to open in 2023, but as of July 2024, it is scheduled to open in January 2026. An arbitrator found that LAWA was responsible for nearly two years of delays by failing to take steps to integrate the APM with its communications network and the delayed construction of the Metro Rail's LAX/Metro Transit Center station. As a result, the airport and city agreed to pay an additional $600 million in change orders to the contractors.
Service description
editRoute description
editThe LAX Automated People Mover (APM) will run 2.25 miles (3.62 km) along a line of six stations,[2] with parallel tracks forming a pinched loop.
The APM will serve three stations in the central terminal area (CTA) each with footbridges with moving walkways to nearby terminals. The west station will serve terminals 3, 4, and B (the Tom Bradley International Terminal), the center station will serve terminals 1, 2, 5 and 6, and the east station will serve terminals 7 and 8 with a future connection to terminal 1. Continuing to the east, the line will travel over Sepulveda Boulevard and skirt along the airfield where Terminal 9 is planned.[3]
At that point, the line turns to the north, crossing Century Boulevard to reach the LAX West Intermodal Transportation Facility (ITF), a large parking structure with a kiss and ride area and access to the LAX City Bus Center and nearby hotels.
From there, the route continues east along 96th Street, passing the line's maintenance yard and crossing over the Metro Rail tracks as it arrives at the East ITF station atop the LAX/Metro Transit Center station.
Trains then travel a short distance to the east and enter the LAX Consolidated Rent-A-Car Facility (ConRAC), a massive parking structure that will house all of the major rental car companies that operate at LAX.[4]
Hours and frequency
editThe APM is expected to operate 24 hours a day. During peak hours (9 a.m. to 11 p.m.) trains will arrive every two minutes. The line will have a ten-minute end-to-end travel time.[5]
Rolling stock
editThe LAX Automated People Mover's fleet will consist of 44 Innovia APM 300 vehicles manufactured by Alstom (initially Bombardier Transportation). Each vehicle can accommodate up to 50 passengers and their luggage, with 12 seated and the rest standing.[6] During peak periods, nine four-car trains will operate simultaneously. Trains will operate with a top speed of 47 miles per hour (76 km/h) and an average speed, including stops, of 13.5 miles per hour (21.7 km/h).[7]
Each four-car train can accommodate up to 200 passengers. During peak hours, with a headway of every 2 minutes, up to 30 trains per hour are expected to enter LAX, carrying up to 6,000 passengers per hour (p/h/d) and up to 84,000 daily peak hour passengers, or up to 30.7 million annual peak hour passengers. The opposite direction capacity will be the same, enabling the system to theoretically transport up to 85 million passengers annually in both directions, including up to 23.7 million non-peak passengers.[8]
Station listing
editThe following is the complete list of stations, from west to east.
Station Name | Connections and notes[9] | |
---|---|---|
A | West CTA | Terminals: 3, 4, B, Parking Garages: P3, P4 |
B | Center CTA | Terminals: 1, 2, 5, 6, Parking Garages: P2a, P2b, P5, P6 |
C | East CTA | Terminals: 7, 8, Parking Garages: P1, P7, Theme Building, Bob Hope USO, Future connection to Terminal 1[10] |
D | Terminal 9 | Future infill station |
E | West ITF | Economy parking garage, hotel shuttles, access to Airport Blvd |
F | East ITF | LAX/Metro Transit Center station, access to Aviation Blvd, future economy parking garage |
G | ConRAC | Consolidated rental car facility |
Traffic reduction
editThe ConRAC facility is projected to eliminate over 3,200 daily car-rental shuttle trips.[11] The East and West ITFs are projected to reduce parking and hotel shuttle trips and car trips into the CTA. The LAX/Metro Transit Center is projected to displace car trips by increasing transit ridership. Riders will include many of the over 57,000 airport and airline badge holders, in addition to airline passengers.
Upcoming Airfield & Terminal Modernization Project (ATMP)
editThe upcoming Airfield & Terminal Modernization Project (ATMP), scheduled for 2028, includes roadway improvements in the vicinity of the West ITF, with an elevated roadway system to separate airport traffic from local traffic.[12][13] Upon completion of these planned improvements, access from the north on Sepulveda Boulevard will be convenient to West ITF; access from Interstate 405 will be convenient to East ITF; and access from the south on Interstate 105 and the Sepulveda tunnel will be convenient to the planned APM station at Terminal 9.
Architecture
editThe six APM stations each feature a line of 20-foot diameter circular skylights, with an additional one in the mezzanine of the LAX/Metro Transit Center. The West ITF parking garage also features similar circular lighting fixtures.[14] The new pedestrian walkways employ a Vierendeel truss, featuring rectangular rather than triangular bracing.[15] The old-style pedestrian walkways with triangular bracing still service parking lots P1, P4, P5, and P7. The APM concrete guideway features "gentle sweeping curves and clean uniform look".[16][17] Each station features a single island platform, with level boarding, which serves trains in both directions. The proposed Terminal 9 infill station is the exception, with a pair of separate side platforms serving both directions.[18]
The East CTA station features a viewing platform for the Theme Building (see Gallery); the West CTA station features a viewing platform for the Tom Bradley International Terminal; and the pedestrian "bridge to nowhere" gives the appearance of a viewing platform for Terminal 1.[19]
History
editBackground
editThe Los Angeles International Airport has long struggled with gridlocked traffic on World Way, the main road that circles through the airport's central terminal area, that can often back up onto Century Boulevard or the Airport Tunnel, which connect the airport to Interstate 405 and Interstate 105 respectively.[6]
Ahead of the 1984 Summer Olympics in Los Angeles, a second level was added to World Way, sending vehicles dropping off departing passengers to the upper level and those picking up arriving passengers to the lower.[20] The relief was short-lived, and by the 2000s, the airport had ranked as one of the nation's most congested and hardest to navigate.[6] That led airport managers to spend over US$15 billion to modernize the airport, with an automated people mover (APM) being one of the major improvements. The project was given added urgency in 2017 when Los Angeles was awarded its bid to host the 2028 Summer Olympics.
Planning
editAfter receiving three bids, Los Angeles World Airports announced it had chosen LAX Integrated Express Solutions (LINXS) to design, build, finance, operate and maintain the APM for a period of 25 years.[21][22] LINXS is a joint venture, public–private partnership of ACS, Alstom, Balfour Beatty, Fluor and Hochtief, with assistance from HDR and Flatiron West.[23] The Los Angeles City Council approved the US$4.9 billion project on April 11, 2018.[22]
Beyond the construction of the APM guideway and stations, LAX has also planned several projects that will enable or connect to the APM. New vertical cores will be built near each terminal, enabling vertical movement of passengers with elevators and escalators, as well as pedestrian bridges over World Way with moving walkways to connect terminals to the APM stations and to existing airport parking structures. LAX is building cores between terminals 5 and 6, at terminals 7 and at terminal B (the Tom Bradley International Terminal) at the cost of $490 million. New cores were also included in larger renovation projects at terminals 1, 2, 3 and 4.[24]
The APM will also connect to the LAX West Intermodal Transportation Facility (West ITF), a US$294.1 million, 4,300 space parking structure with a lot to pick up and drop off passengers and areas for shuttle buses, the new LAX Consolidated Rent-A-Car Facility (ConRAC), a massive parking structure that will house all of the major rental car companies that operate at LAX in one location located adjacent to Interstate 405, and to the LAX/Metro Transit Center station (East ITF), connecting passengers to the Los Angeles Metro Rail C and K Lines and other transit services.[25]
Altogether, these projects are called the Landside Access Modernization Program and are expected to cost a total of US$5.5 billion.[26]
Construction
editIn 2018, 2,100 parking spaces in lot C were removed to reconfigure the area for the West ITF.[26] Utility relocation started in the second quarter of 2018.[5] Construction on the West ITF officially began in the summer of 2019[27] and ConRAC broke ground in September 2019.[28] The first large concrete pour for the APM occurred in September 2020 at the West ITF station.[29]
Construction on the 2.25 miles (3.62 km) of two-track elevated guideway began in the spring of 2019 with the first underground support columns being placed. The first concrete for the columns was poured in January 2020. The pouring of the concrete for the guideway began in September 2020 and it was completed in May 2022. A total of 69,700 cubic yards (53,300 m3) of concrete was poured and one million work hours were completed to complete this project.[30][31][5]
Connecting Los Angeles's Metro Rail system to the airport, which was studied by transit planners since the 1980s,[32] started when Metro commenced construction on the LAX/Metro Transit Center station on June 21, 2021. The new station will connect Metro and other transit services to the East ITF station. The new station will link the LAX Automated People Mover to the C and K rail lines, Metro Bus, and other municipal bus operator lines. Additionally, a customer service center and Metro Bike Hub will be constructed.[25]
After two years of construction, West ITF's economy parking structure opened on October 19, 2021. Until the APM opens, temporary shuttle buses transport passengers between the airport and the facility.[33]
The line was initially planned to open in 2023, but as of July 2024 is slated to open in January 2026.[1] Schedule delays have coincided with top management changes. John Ackerman became the new LAWA CEO in February 2024.[34] In March 2024 Terri Mestas, Chief Development Officer, accepted a new position,[35] and three new appointments were made to the executive leadership team: Marla Bleavins as Chief Airport Administrative Officer, Robert Lowe as Chief People and Culture Officer, and Becca Doten as Chief of Staff.[36]
An additional $200 million was authorized by the Board of Airport Commissioners on May 2, 2024 to fund change orders in an attempt to firm up the schedule.[37][38] An additional $400 million was approved on August 16, 2024 by the City Council,[39][40][41] following a June 7, 2024 decision by an arbitrator (the "Project Neutral") that LAWA was responsible for delays of 526 calendar days, having failed to act in good faith and comply with the contract documents.[42]
As of May 2024[update], overall construction progress is 97.3% complete.[43] On April 29, 2024, the project test drove the one-car Maintenance Service Vehicle on the guideway between the Maintenance and Storage Facility (MSF), West ITF, and ConRAC.[44]
Gallery
edit-
Rendering of the Center CTA station
-
Rendering of the East CTA station and its viewing platform for the Theme Building
-
Rendering of West CTA station as seen from the Tom Bradley International Terminal
References
edit- ^ a b "Automated People Mover Project - Monthly Report for March 2024" (PDF). Electronic Municipal Market Access. LAX Integrated Express Solutions. Retrieved April 26, 2024.
- ^ Cain, Josh (March 14, 2019). "Officials touted 2.25-mile LAX Automated People Mover at groundbreaking". Daily Breeze. Archived from the original on March 9, 2023. Retrieved March 16, 2019.
- ^ "Airfield & Terminal Modernization Project Elements". LAWA. Los Angeles World Airports. Retrieved March 10, 2024.
- ^ "LAX is bringing all rental car companies to one location near 405 with People Mover train to airport". Daily Breeze. September 12, 2019. Archived from the original on March 9, 2023. Retrieved September 12, 2019 – via City News Service.
- ^ a b c Sharp, Steven (February 16, 2018). "Renderings Galore for the LAX Automated People Mover". Urbanize LA. Archived from the original on February 23, 2018. Retrieved March 16, 2018.
- ^ a b c Uranga, Rachel (August 3, 2022). "LAX's traffic nightmare could end with new people mover, but you'll have to wait". Los Angeles Times. Archived from the original on August 4, 2022. Retrieved August 5, 2022.
- ^ "Automated People Mover (APM) Train System". Los Angeles World Airports. Archived from the original on August 29, 2022. Retrieved August 5, 2022.
- ^ "APM Train Car Fact Sheet". Los Angeles World Airports. Retrieved July 22, 2024.
- ^ LAX Unveils Automated People Mover Train (Video). Los Angeles World Airports. August 2, 2022. Event occurs at 0:38. Archived from the original on August 5, 2022. Retrieved August 5, 2022 – via YouTube.
- ^ "East CTA Station Fact Sheet" (PDF). LAX Integrated Express Solutions. 2020. Retrieved March 31, 2023.
- ^ "LAX Integrated Express Solutions (LINXS)".
- ^ "LAWA Official Site | Transforming LAX".
- ^ https://www.lawa.org/-/media/lawa-web/cip-microsite/rendering/atmp/202202-atmp-map.ashx [bare URL]
- ^ https://www.lawa.org/connectinglax/construction-photos/2021-february (photo #13)
- ^ "LAX commences automated people mover pedestrian walkway construction". June 15, 2021.
- ^ "An Inside Look at the Innovative Guideway Design for LAX's Automated People Mover Project | HDR". October 11, 2023.
- ^ "Aspire Magazine Fall 2023 Page 18".
- ^ "LAX's Terminal 9 Industry Showcase, April 14, 2023". YouTube. April 17, 2023.
- ^ "Evacuation lifted at LAX terminal after suspicious package investigation". January 8, 2024.
- ^ Levin, Jay (April 22, 1984). "LAX being molded into an easy airport". Daily Breeze. Copley News Service. p. A1 – via NewsBank.
- ^ "Three Firms Have Submitted Bids to Build a People Mover at LAX". KNBC. November 10, 2017. Archived from the original on March 17, 2018. Retrieved March 16, 2018 – via City News Service.
- ^ a b Nelson, Laura J. (April 11, 2018). "City Council approves long-awaited people mover to LAX". Los Angeles Times. Archived from the original on April 12, 2018. Retrieved November 17, 2018.
- ^ "Meet the Team". LAX Integrated Express Solutions (LINXS). Archived from the original on August 5, 2022. Retrieved August 5, 2022.
- ^ "LAWA Official Site | Transforming LAX". www.lawa.org. Retrieved January 8, 2024.
- ^ a b Jager, Rick (June 21, 2021). "Groundbreaking held for Airport Metro Connector project". The Source. Retrieved January 8, 2024.
- ^ a b Sharp, Steven (December 8, 2017). "LAX Takes First Step Toward Construction of $5.5-Billion Landside Access Modernization Project". Urbanize LA. Archived from the original on February 9, 2018. Retrieved March 16, 2018.
- ^ "LAX Breaks Ground on Intermodal Transportation Facility – West, A Key Component of the Landside Access Modernization Program". Los Angeles World Airports (Press release). Archived from the original on July 21, 2019. Retrieved July 21, 2019.
- ^ "Mayor Garcetti and Los Angeles World Airports Break Ground on Historic Consolidated Rental Car Facility". Los Angeles World Airports (Press release). September 12, 2019. Archived from the original on September 24, 2022. Retrieved October 19, 2021.
- ^ Sharp, Steven (September 15, 2020). "Construction Continues for LAX Automated People Mover". Urbanize LA. Archived from the original on September 16, 2020. Retrieved September 16, 2020.
- ^ "Fluor Joint Venture completes LAX's APM train guideway structure". Mass Transit (magazine). May 5, 2022. Archived from the original on May 6, 2022. Retrieved August 10, 2022.
- ^ "Officials Break Ground On $5.5 Billion People Mover At LAX". CBS Los Angeles. March 14, 2019. Archived from the original on March 1, 2020. Retrieved March 15, 2019.
- ^ COASTAL CORRIDOR RAIL TRANSIT PROJECT NORTH SEGMENT (PDF). Metro (Report). Bechtel. August 1988. Archived (PDF) from the original on October 24, 2020. Retrieved September 1, 2020.
- ^ "New LAX parking structure opens Tuesday with 4,300 new spots, pre-booking discounts". KTLA. October 15, 2021. Archived from the original on August 5, 2022. Retrieved August 5, 2022.
- ^ "Mayor Karen Bass Recognizes City Council's Confirmation of John Ackerman as CEO of Los Angeles World Airports". LA City. December 12, 2023. Retrieved April 3, 2024.
- ^ Lindblom, Mike (March 29, 2024). "Sound Transit will pay $600K to new megaproject leader hired from LAX". The Seattle Times. Retrieved April 3, 2024.
- ^ "Los Angeles World Airports Announces the Appointment of Chief Airport Administrative Officer, Chief People and Culture Officer, and Chief of Staff". LAWA. March 20, 2024. Retrieved April 3, 2024.
- ^ Shalby, Colleen (May 3, 2024). "LAX People Mover gets $200 million more to resolve claims between contractor and airport". Los Angeles Times. Retrieved May 31, 2024.
- ^ "Report to the Board of Airport Commissioners". Los Angeles World Airports. April 26, 2024. Retrieved July 22, 2024.
- ^ "City Council approves additional $400 million to complete LAX's Automated People Mover, settle legal claims - CBS Los Angeles". CBS News.
- ^ Shalby, Colleen (July 15, 2024). "LAX People Mover could have completion date — and $400 million in added costs". Los Angeles Times. Archived from the original on July 15, 2024. Retrieved July 17, 2024.
- ^ "Report to the Board of Airport Commissioners". Los Angeles World Airports. July 11, 2024. Retrieved July 17, 2024.
- ^ "Project Neutral Reccomendations" (PDF). LAX Integrated Express Solutions. June 7, 2024. Retrieved October 31, 2024.
- ^ "Automated People Mover Project - Monthly Report for May 2024" (PDF). LAX Integrated Express Solutions. June 14, 2024. p. 5. Retrieved July 9, 2024.
- ^ "Monthly Performance Report – April 2024" (PDF). California Public Utilities Commission. May 29, 2024. p. 19. Retrieved July 22, 2024.