Line 14 of the Shanghai Metro is an east-west metro line opened on 30 December 2021.[1] The line, consisting of 31 stations, starts from Fengbang town in Jiading District, and terminate in Jinqiao town in Pudong New Area via Zhenru, Jing'an Temple, Dashijie, and Lujiazui. Its total length is 39.1 kilometres (24.3 mi),[2] and passengers are able to transfer to 13 existing and planned metro lines.[3] Due to Line 14 cutting across some of the densest areas of Shanghai and being a relief line for line 2, high ridership is expected for the line. As such the line uses high capacity 8 car A size trains similar to lines 1 and 2.[4] The line uses an automatic train control system jointly developed by Thales and Shanghai Electric.[5] Line 14 is fully driverless.[6] The line is colored olive on system maps.
Line 14 | |
---|---|
Overview | |
Other name(s) | M6 (planned name) |
Native name | 上海地铁14号线 |
Status | Operational |
Owner | Shanghai Rail Transit Line 14 Development Co., Ltd. |
Locale | Pudong, Huangpu, Jing'an, Putuo, and Jiading districts, Shanghai, China |
Termini | |
Connecting lines | 1 2 3 4 6 7 8 9 10 11 13 15 18 |
Stations | 30 (30 open and 1 under construction) |
Website | www |
Service | |
Type | Rapid transit |
System | Shanghai Metro |
Services | Mainline: Fengbang ↔ Guiqiao Road Partial mainline: Zhenxin Xincun ↔ Lantian Road |
Operator(s) | Shanghai No. 4 Metro Operation Co. Ltd. |
Depot(s) | Fengbang Depot Jinqiao Parking Lot |
Rolling stock | 49 Class A 8 car trains |
History | |
Commenced | 29 November 2014 |
Opened | 30 December 2021 |
Technical | |
Track length | 38.18 km (24 mi) |
Number of tracks | 2 |
Character | underground |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) |
Electrification | Overhead lines (1500 volts) |
Operating speed | 80 km/h (50 mph) Average speed: 34.2 km/h (21 mph) |
Signalling | Thales SEC Transport |
History
editEnvironmental evaluations began on January 2, 2014.[2] On November 29, 2014, construction began on a section in Pudong New Area.[7]
The line was originally scheduled to open in 2020,[8] but its opening was delayed to 30 December 2021. Longju Road station has not been opened yet, due to problems with land acquisition process.
Shanghai Metro Line 14 opening history | ||||||
---|---|---|---|---|---|---|
Segment | Commenced | Opened | Length | Station(s) | Name | Investment |
Fengbang - Guiqiao Road | 29 Nov 2014 | 30 Dec 2021 | 38.2 km (23.7 mi) | 30 | Phase 1 | ¥57.686 billion |
Longju Road | u/c | Infill station | 1 | |||
Stations
editService routes
editShanghai Metro Line 14 service routes | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||
Routes | Station name | Connections | Distance | Location | Open- ing | |||||
M | P | English | Chinese | km | min | |||||
● | Fengbang | 封浜 | 0.0 | 0.0 | 0 | Jiading | 30 Dec 2021 | |||
● | Lexiu Road | 乐秀路 | 1.61 | 1.61 | 2 | |||||
● | Lintao Road | 临洮路 | 1.65 | 3.26 | 4 | |||||
● | Jiayi Road | 嘉怡路 | 1.55 | 4.81 | 7 | |||||
● | Dingbian Road | 定边路 | 1.41 | 6.22 | 9 | |||||
● | ● | Zhenxin Xincun | 真新新村 | 1.24 | 7.46 | 11 | ||||
● | ● | Zhenguang Road | 真光路 | 1.00 | 8.46 | 13 | Putuo | |||
● | ● | Tongchuan Road | 铜川路 | 15 | 1.31 | 9.77 | 15 | |||
● | ● | Zhenru | 真如 | 11 | 0.92 | 10.69 | 17 | |||
● | ● | Zhongning Road | 中宁路 | 0.90 | 11.59 | 20 | ||||
● | ● | Caoyang Road | 曹杨路 | 3 4 11 [i] | 1.10 | 12.69 | 22 | |||
● | ● | Wuning Road | 武宁路 | 13 | 1.05 | 13.74 | 24 | |||
● | ● | Wuding Road | 武定路 | 0.97 | 14.71 | 26 | Jing'an | |||
● | ● | Jing'an Temple | 静安寺 | 2 7 | 1.03 | 15.74 | 28 | |||
● | ● | Site of the First CPC National Congress · South Huangpi Road | 一大会址·黄陂南路 | 1 | 3.07 | 18.81 | 32 | Huangpu | ||
● | ● | Dashijie | 大世界 | 8 | 0.71 | 19.52 | 34 | |||
● | ● | Yuyuan Garden | 豫园 | 10 | 0.74 | 20.26 | 36 | |||
● | ● | Lujiazui | 陆家嘴 | 2 | 1.60 | 21.86 | 39 | Pudong | ||
● | ● | South Pudong Road | 浦东南路 | 2 [ii] | 1.01 | 22.87 | 41 | |||
● | ● | Pudong Avenue | 浦东大道 | 4 | 0.74 | 23.61 | 43 | |||
● | ● | Yuanshen Road | 源深路 | 1.05 | 24.66 | 45 | ||||
● | ● | Changyi Road | 昌邑路 | 18 | 1.06 | 25.72 | 47 | |||
● | ● | Xiepu Road | 歇浦路 | 1.23 | 26.95 | 49 | ||||
| | | | Longju Road | 龙居路 | 1.02 | 27.97 | Later opening due to land acquisition process | ||||
● | ● | Yunshan Road | 云山路 | 6 | 2.05 | 30.02 | 53 | 30 Dec 2021 | ||
● | ● | Lantian Road | 蓝天路 | 9 | 1.16 | 31.18 | 56 | |||
● | Huangyang Road | 黄杨路 | 1.86 | 33.04 | 58 | |||||
● | Yunshun Road | 云顺路 | 0.88 | 33.92 | 60 | |||||
● | Pudong Football Stadium | 浦东足球场 | 1.49 | 35.41 | 63 | |||||
● | Jinyue Road | 金粤路 | 1.28 | 36.69 | 65 | |||||
● | Guiqiao Road | 桂桥路 | 1.49 | 38.18 | 67 | |||||
| ||||||||||
Headways
editShanghai Metro Line 14 headway[9] | ||||||
---|---|---|---|---|---|---|
Time | Fengbang - Zhenxin Xincun |
Zhenxin Xincun - Lantian Road |
Lantian Road - Guiqiao Road | |||
Monday - Friday (Working Days) | ||||||
AM peak | 7:00–9:20 | About 6 min and 40 sec | About 3 min and 20 sec | About 6 min and 40 sec | ||
Off-peak | 9:20–16:40 | About 12 min | About 6 min | About 12 min | ||
PM peak | 16:40–20:00 | About 8 min | About 4 min | About 8 min | ||
Other hours |
|
About 5-12 min | ||||
Saturday and Sunday (Weekends) | ||||||
Peak | 7:00–21:00 | About 10 min | About 5 min | About 10 min | ||
Other hours |
|
About 5-12 min | ||||
Technology
editRolling Stock
editShanghai Metro Line 14 rolling stock | ||||||||
---|---|---|---|---|---|---|---|---|
Fleet numbers | Manufacturer | Time of manufac- turing |
Class | No of car |
Assembly[i] | Rolling stock | Number | Notes |
392 | CRRC Nanjing Puzhen Co., Ltd. | 2019–2020 | A[ii] | 8 | Tc+Mp+M+Mp+M+M+Mp+Tc | 14A01 | 14001-14049 (140011-143921) |
[10] |
References
edit- ^ Ren Tianbao (9 September 2020). 终于!上海轨交14号线预计明年开通. Xinhuanet (in Chinese). Archived from the original on 21 October 2021. Retrieved 15 December 2020.
- ^ a b Line 14 Evaluation, 4 March 2016, retrieved 4 March 2016
- ^ 14号线选线规划对外公示 “大横线”将与16条线路换乘 (in Chinese). 8 February 2013. Retrieved 8 February 2013.
- ^ "上海地铁14号线拟年底开建 横贯5区设31站_民生热线_新民网". shanghai.xinmin.cn. Retrieved 17 January 2018.
- ^ Briginshaw, David. "Shanghai awards contract for first automated metro line". Retrieved 3 February 2018.
- ^ "上海轨交14号线进入新车调试阶段,开通后可换乘13条轨交_申通地铁". www.sohu.com. Retrieved 6 June 2021.
- ^ 朱敏之. "浦东大道:东西通道开建 拥堵初现建议绕行-东方视频-东方网". imedia.eastday.com. Retrieved 30 May 2017.
- ^ "上海轨交14号线与延安高架上下重合 15号线跨越5区_新闻中心_赢商网". sh.winshang.com. Retrieved 30 May 2017.
- ^ "Schedule" (in Chinese). Shanghai Metro. 7 July 2021. Retrieved 7 July 2021.
- ^ "First of 49 Bombardier MITRAC propulsion-equipped metro trains for Shanghai Metro's Line 14 rolled off the assembly line". Bombardier. Retrieved 20 March 2020.