Frankfurt (Main) Hauptbahnhof, also called Frankfurt Central Station and Frankfurt Main Station, is the busiest train station in the German state of Hesse.[2] Due to its location near the middle of Germany and usage as a transport hub for long and short distance travelling, Deutsche Bahn refers to it as the most important station in Germany.
Name
editThe affix "Main" comes from the city's full name, Frankfurt am Main ("Frankfurt on the River Main") and is needed to distinguish it from Frankfurt (Oder) station on the River Oder in Brandenburg. In German, the name is often abbreviated as Frankfurt (Main) Hbf.
History
editInitial situation
editBefore the current Hauptbahnhof was built on the Galgenfeld (gallows field), the three western stations, the termini of the Taunus Railway (Taunusbahn), the Main–Weser Railway (Main-Weser-Bahn) and the Main-Neckar Railway (Main-Neckar-Bahn) were located on the outskirts of the city, the Gallusanlage, the area of today's Bahnhofsviertel ("station district").
Plans
editDue to the increased volume of travellers at the end of the 19th century, the capacity of the three western railway stations became increasingly inadequate, but changes were made more difficult by the territorial affiliations of the states surrounding the Free City of Frankfurt. After the annexation of Frankfurt, Nassau and Hesse-Kassel by Prussia in 1866, these obstacles were largely removed, so that planning for a central station was taken seriously. The inadequacy of the situation became apparent particularly during the Franco-Prussian War of 1870/71, when troop movements were noticeably hampered by the scattered stations. Like the three western stations before it, the new station was to be built as a terminal station. First, a large station with 34 platform tracks was planned. Because of the huge dimensions, however, a variant with "only" 18 platform tracks was used. Mail and goods handling was to take place under the station hall, local traffic was to be handled outside, which was realised by the main freight yard built later. The town council, which only got a say in 1875, also wanted the railway facilities relocated from the Anlagenring (the ring of roads and parklands on the demolished walls surrounding the inner city) to the former gallows field. A new district with Kaiserstraße as the main axis was to be created on the area of the track fields of the Western stations that would be released from railway operations. This option also had the great advantage that operations could be carried out largely undisturbed during the construction phase, since the new station hardly affected the old lines.
From 1880, the Bauakademie (Prussian Building Academy) held a competition involving all the major architects to design a "monument that challenged the highest artistic standards". In 1881, the winner of this architectural competition was that of the agricultural inspector and university master builder Hermann Eggert from Strasbourg in Alsace, from among the 55 designs submitted. He was commissioned with the planning and construction of the entrance building. The Berlin architect Johann Wilhelm Schwedler, who specialised in steel construction, scored second place. He became the designer of the three new station halls made of iron with a 28-metre (91 ft 10 in)-high barrel vault, each of which had three platforms with six tracks.[3]
Realisation
editOn 18 August 1888, after only five years of construction, the Centralbahnhof Frankfurt (Frankfurt Central Station) was inaugurated. In the next few years, the station district developed to the east of the entrance building and was fully developed by around 1900. Frankfurt Hauptbahnhof was the largest station in Europe until Leipzig Hauptbahnhof was built in 1915.
Railway operations
editThe station was designed for regular services. The entry and exit tracks of each line lay next to each other.[4]
On the evening of the opening day, a train was unable to stop in time and ran over the buffer stop. The locomotive and the pavement of the transverse platform were damaged. This was the beginning of a whole series of such incidents, which caused some ridicule in the press.[5] The "highlight" was the "sweeping" crossing of the locomotive of the Ostend-Wien-Express on 6 December 1901. The locomotive and tender only came to a stop near the first and second class waiting room.
Many engine drivers therefore drove very carefully into the station and came to a stop some distance from the buffer stops. This in turn meant that the last carriages of the trains came to a stop away from the platforms, which the management did not like either. The engine drivers were warned to "drive as close as possible to the buffer stops".[6]
Extensions and conversions
editIn 1924 the building was extended with two outer halls in Neoclassical style. The number of tracks increased to 25 (tracks 1 to 24 and 1a). Reliefs with motifs of the Wandervogel movement were installed at the southern entrance.
During the Second World War, the station was the target of Allied air raids, for instance on 11 December 1944, when almost 1000 tons of multi-purpose bombs were dropped on the station.[7] However, it had already been damaged by air raids on Frankfurt am Main. Above all, the glazing of the platform halls was destroyed.[8] In order to protect the passengers from rain, the former glass surfaces were partly closed with wood, a temporary solution that remained in place for almost 60 years. Offices that did not necessarily have to be on site for operational purposes were outsourced, the lost and found office for example to the Frankfurt-Höchst station.[9]
The station was fully electrified in 1956.
A 22 meter high signal box tower was built between 1955 and 1957.[10] In 1957, what was then the largest and most modern track signal box in Europe (with a train number signalling system) was put into operation. 16 operators controlled the 15,000 relay system. The building erected near tracks 9 and 10 is now a listed building.[11]
Also in 1957, nine steam shunting locomotives were replaced by seven diesel shunting locomotives. In the early 1960s, Germany's largest express freight handling facility was set up under the station. 15 million pieces of luggage and express goods alone were handled annually in these years. The facilities also included a supply centre for the station and the dining cars, with its own confectionery, large bakery and butcher's shop. Two railway post offices were also part of the extensive facilities, as were 70 freight lifts.
As a result of growing inner-city traffic congestion, the idea of an inner-city connecting railway was taken up again in the 1960s, despite the fact that it was not economically justifiable.[12]
The construction of the underground railway systems began in 1971 with the B-Tunnel of the Frankfurt U-Bahn in the central city. A large shopping arcade (B level) was created as a distribution level, from which two four-track stations each—an underground station (C level) and an S-Bahn station (D level)—and a three-storey underground car park (part of which can also be used as a fallout shelter), is accessed through numerous corridors and stairs. These were the first public escalators in the city at the time. The tram stop on the square in front of the station, Am Hauptbahnhof, could formerly only be reached from the escalator opened in 1978[13] on the B level. There is now a pedestrian crossing at street level.
The underground stations were built using "cut and cover" construction: for the construction of the S-Bahn station below the long-distance train hall, the north wing of the entrance building was removed from 12 January 1972[14] and later rebuilt using the original facade cladding. The underground stations began operating in 1978.
At the same time, a two-storey air raid shelter was built to offer railway employees protection in an emergency. All telephone operations could be handled from this bunker. It was also possible to operate the loudspeaker system. Even though stocks such as canned food are no longer stored today, the technical systems (air filter systems, power generators) are still fully operational.
In the early 1970s, the platform ticket requirement was abolished and the platform barriers were dismantled.
The two platforms on tracks 6 to 9 were widened, raised and lengthened for the introduction of ICE operations in June 1991. The space for the widening was gained by demolishing the baggage platforms, which were no longer used.
From 2002 to 2006, the listed[11] roofs of the five platform halls were completely renewed during operation, taking into account heritage preservation issues.[15][16] A total of around 60,000 square metres (650,000 sq ft) of roof and wall cladding, including around 30,000 square metres (320,000 sq ft) of glass, were renewed and 5,000 tons of steel replaced. A special routine was developed as an assembly concept for this basic repair. At a height of ten meters, an assembly and transport platform was drawn in over the length of the roof for the duration of the construction work. Tower cranes were installed in the central area of this platform. Some loads of up to 150 tons per support were lowered to the basement and foundations were built there. All work steps were integrated in the routine in such a way that the platforms were moved by one field (9.3-metre (30 ft 6 in)) per hall every two weeks. Since then, screw connections instead of rivets have served as the means of fastening, although a specially developed rivet head screw was approved in individual cases by the Federal Railway Authority. The refurbishment of the station roof has allowed significantly more daylight to enter. The trusses that support the roof were painted light gray as in the original condition and therefore appear lighter. The decorative rosettes in the gussets are now painted dark blue and are more easily seen. The entire construction process took place almost unnoticed ten metres above the heads of the travellers.
An incident occurred shortly after work began. During welding work, part of the roof of the northern part of the station building caught fire. The "North Ventilation Centre" was almost completely destroyed and had to be replaced. Since air continued to be sucked in during the fire, dirt and damage also occurred inside the building, especially on level B.
A total of €117m was invested in the roof renovation.[17] 80 percent of the costs were borne by the federal government.[18] The facade was renovated in 2013.[16]
Other parts of the interior design of the station and entrance halls as well as the underground station were also modernised. In the meantime, liquid-crystal displays have replaced the old split-flap displays on the platforms. As in Wiesbaden Hauptbahnhof, seven cubic glass and steel pavilions have replaced the previous buildings on the transverse platform. In mid-2006, cubic and transparent lifts were also installed to connect the S-Bahn platforms to the U-Bahn and to the side platform of the train shed.
Due to the frequent theft of luggage trolleys, which caused annual damage of up to €30,000, a security system was installed in the station to prevent the luggage trolleys from being removed from the railway premises. When crossing a red mark, the front wheel locked. This system was originally developed for shopping carts and adapted accordingly. The rental of luggage trolleys was later discontinued, and in view of the increased number of passengers, there was no longer any room for safe operation.
Planning began in 1998, and implementation at the end of 2001, of a computer-based interlocking of the SIMIS C type, the four-stage commissioning of which was completed on 27 November 2005.[19][20] It replaces the track control signal box from 1957, which handled a total of around 20 million trains and 100 million shunting trips.[20] The "Fpf" signal box located between tracks 9 and 10 was considered the largest and most modern signal box in Europe at the time it was commissioned. Since 27 March 1986, circuit changes at the signal box had been prohibited due to age-related signs of wear, the stress on the system and the insulation of the interior wiring.[19] The new signal box is divided into two sub-centres (north and south) and was the largest two-storey signal box building in Germany when it was commissioned.[19]
The entry and exit speeds were increased from 30 km/h (18.6 mph) to 40 to 60 km/h (24.9 to 37.3 mph)[20] and new running options were created with additional points. A platform changeover was introduced on all access routes, and 13 platform tracks of the main station were also divided into two sections (with train detection signals). The system comprises a total of 845 control units, including 340 switches and track closures as well as 67 main signals. The interlocking is now remotely operated from the operations centre in Frankfurt by six dispatchers and a node dispatcher.[11] €132m[20] was spent on the signal box.
The new interlocking laid the foundation for numerous extensions and conversions of the tracks of the station and the lines leading to it, in order to better utilise the station platform tracks in the future and to increase their capacity.[11]
The wayfinding system was renewed in November 2005 in preparation for the 2006 World Cup. Replacing of the partly outdated signage made a quick and easy orientation within the station possible.
Finishing in 2007, the floors and the cladding of the stairs, which had not been renewed for decades, were uniformly covered with black granite from China. Following this, a redesign of the station forecourt, the B level and the S-Bahn station is planned.
From July to September 2010, platform 12/13 was removed and rebuilt. The platform cover was separated from the substructure with concrete saws, demolished in sections and rebuilt in prefabricated concrete sections. The new platform was given the same granite flooring as the transverse platform and the main platforms. The part outside the hall will be provided with a new, 130-metre (426 ft 6 in)-long platform roof. Overall, the platform renovation cost €8.5m.
In October 2020, the conversion of the B level and the entrance hall began, which will be completely redesigned within eight years. The federal government, DB, the city and the Frankfurt public transport company (Verkehrsgesellschaft Frankfurt) are investing a total of €375m.[13] By the end of 2024, the entrance hall is to be renovated first, followed by the forecourt.[21]
Other upgrades
editThe capacity of some access routes is considered to be exhausted. Several lines (e.g. ICE 13 and RB 58) can no longer be routed via the station. For reasons of acceleration, only four platform tracks (tracks 6 to 9) are normally used for long-distance trains on the north-south axis.[4]
In order to mitigate a number of traffic disadvantages of terminal stations in general and the Frankfurt railway junction in particular, ideas and suggestions have been discussed again and again since the Frankfurt Hauptbahnhof was commissioned to mitigate the disadvantages or to relocate the station as a whole. These proposals were discarded due to technical problems and lack of economic viability.[12]
Various options for underground through stations were discussed in the 1980s and 1990s. The Frankfurt 21 concept that emerged from this provided for the conversion of the station into a twelve-track through station. The project presented in 1996 was shelved in 2001 due to a lack of funding. The RheinMain plus project was then pursued.
Deutsche Bahn is planning to separate long-distance and regional traffic from the direction of Mannheim, Mainz and the Cologne–Frankfurt high-speed rail line. Almost all long-distance traffic is to be concentrated on the south side of the station, on platforms 1 to 8, and conflicts between routes are to be reduced. Part of the regional traffic is to be relocated to the north side. Among other things, the construction of a connecting curve known as the Kraftwerkskurve ("power station curve") from Frankfurt South to platform tracks 1 to 3 and the installation of additional sets of points in the apron of the station are planned by 2030.[4] From June 2017 to November 2021, the Homburger embankment was upgraded in two ways. According to an estimate in 2017, the 800-metre-long upgrade would cost €131m, but the costs ultimately amounted to around €180m.[22][23][24] The costs were funded by the federal government.[25] Operationally, the line is to be referred to as "Ffm Hbf–Mainzer Landstraße".[26]
By 2019, access from level B and the station forecourt are to be remodelled at a cost of €175m.[27] Between the beginning of 2016 and the beginning of 2019, more than 1,000 square metres of new retail space are to be built for €134.5m. The city is contributing €27.5m. Previously unused basements are to be used for this purpose.[28] On 21 December 2015, Deutsche Bahn and the city of Frankfurt signed a contract to modernise the underground distribution level and to create additional access points. Work was scheduled to begin in the fourth quarter of 2016 and be completed in mid-2020. The city of Frankfurt is contributing €27.5m to the construction costs of €135m.[16]
The planned Frankfurt am Main long-distance railway tunnel is to run from the Offenbach city limits or from the Frankfurt East station to the Niederräd Main bridge. It is intended to relieve the Hauptbahnhof and turn it into an underground through station for many long-distance lines. The project is included as an "urgent need" of the Federal Transport Infrastructure Plan 2030.[29] The results of the feasibility study were presented to the public on 28 June 2021.[30] The construction period is estimated at 10 years after the completion of planning. Construction is expected to start in the 2030s and operations would start in the 2040s. The construction costs are estimated at €3.6b.[31] The upgrade of the node is one of 13 infrastructure projects of the proposed German clock-face timetable (Deutschlandtakt) that, according to the coalition agreement of the red-green-yellow federal government presented in November 2021, are to be "accelerated" and implemented "with high political priority".[32]
Architecture
editAbove ground part
editThe above-ground part of Frankfurt Haupptbahnhof is divided into the entrance building and the train shed. The entrance building faces on to the street side to the east and thus opens up the terminal station towards the Bahnhofsviertel (station district). The façade of the older building, in front of the three central train sheds, was designed in a Renaissance Revival style, the extensions of the entrance building from 1924, in front of the two outer halls, is in the neoclassical style. The building is 270 metres (885 ft 10 in) wide. The centre of the entrance building is the main reception hall, the street-side entrance of which consists of three doorways divided by two large pillars. Above the centre there is a decorated clock with allegories of day and night and the Deutsche Bahn logo with the word "Hauptbahnhof". The division into three bays is also continued in the roof area, where large glass surfaces let in daylight. The division of the train shed into three parts corresponded to the original use by three railway companies: the Taunus-Eisenbahn, the Prussian state railways and the Hessian Ludwigsbahn. There is a tower on each side of the facade. In the middle of the roof there is a 6.3-metre (20 ft 8 in)-high bronze group of figures by the Braunschweig sculptor Gustav Herold: Atlas, who carries the globe on his shoulders, accompanied by symbolic figures for steam and electricity. There are also figures representing trade and agriculture and the iron industry and shipping.
West of the entrance building is the train shed. It consists of five steel and glass halls that cover the platforms over a length of 186 metres (610 ft 3 in). The three larger halls are 56 metres (183 ft 9 in) wide and 28 metres (91 ft 10 in) high, the two outer small halls are 31 metres (101 ft 8 in) wide and 20 metres (65 ft 7 in) high.[18] The transverse platform, which allows access to the 24 above-ground mainline tracks in the train shed, extends across the entire width of the halls, only the outer track 1a can only be reached indirectly via the platform on track 1. The platforms, which are at right angles to the transverse platform, are also connected by an underpass (transverse tunnel) connected to the west. Outside the platform halls, the platforms continue with canopies from different eras.
Operational usage
editThe station's terminal layout has posed some unique problems ever since the late 20th century, since all trains have to change directions and reverse out of the station to continue on to their destination. This causes long turn-around times and places the passengers in the opposite direction of where they had been sitting. There have been several attempts to change this. The last project, called Frankfurt 21, was to put the whole station underground, connect it with tunnels also to the east, and so avoid the disadvantages of the terminal layout. This would be financed by selling the air rights over the area now used for tracks as building ground for a skyscraper, but this soon proved unrealistic, and the project was abandoned.
Frankfurt is the third-busiest railway station outside Japan and the second-busiest in Germany after Hamburg Hauptbahnhof.[citation needed]
Long distance services
editAs for long-distance traffic, the station profits greatly from its location in the heart of Europe; 13 of the 24 ICE lines call at the station, as well as 2 of the 3 ICE Sprinter lines. To ease the strain on the Hauptbahnhof, some ICE lines now call at Frankfurt Airport station and at Frankfurt (Main) Süd instead of Hauptbahnhof.
Line | Route | Interval |
---|---|---|
ICE 4 ICE-Sprinter |
Hamburg-Altona – Hamburg Dammtor – Hamburg – Hannover – Frankfurt – Darmstadt | One train pair |
ICE 11 | Hamburg-Altona – Berlin – Leipzig – Erfurt – Frankfurt – Mannheim – Stuttgart – Augsburg – Munich | Every two hours |
ICE 12 | Berlin Ost – Wolfsburg – Braunschweig – Kassel-Wilhelmshöhe – Frankfurt – Mannheim – Karlsruhe – Freiburg – Basel (– Interlaken Ost) | |
ICE 13 | Berlin Ost – Braunschweig – Kassel-Wilhelmshöhe – Frankfurt | Some services |
ICE 15 ICE-Sprinter |
Berlin – Halle – Erfurt – Frankfurt | Every two hours |
ICE 20 | (Kiel –) Hamburg – Hannover – Kassel-Wilhelmshöhe – Frankfurt – Mannheim – Karlsruhe – Freiburg – Basel – Zürich (– Chur) | |
ICE 22 | (Kiel –) Hamburg – Hannover – Kassel-Wilhelmshöhe – Frankfurt – Frankfurt Airport – Mannheim – Stuttgart | |
ICE 22 | (Munich East – Nuremberg – Würzburg – Hanau –) Frankfurt – Fulda – Kassel-Wilhelmshöhe – Göttingen – Hannover – Bremen – Oldenburg (Oldb) | One train Sun – Fri |
ICE 26 | (Stralsund –) Hamburg – Kassel-Wilhelmshöhe – Gießen – Frankfurt – Heidelberg – Karlsruhe | Every two hours together with IC 26 |
IC 26 | Westerland – Hamburg – Kassel-Wilhelmshöhe – Gießen – Frankfurt – Heidelberg – Karlsruhe | One train pair |
IC 34 | Frankfurt – Wetzlar – Siegen Hbf – Dortmund/Unna – Hamm – Münster – (Emden – Norddeich Mole) | Every two hours |
ICE 41 | (Dortmund –) Essen – Duisburg – Düsseldorf – Köln Messe/Deutz – Frankfurt Airport – Frankfurt – Aschaffenburg – Würzburg – Nuremberg – Munich | Hourly |
ICE 49 | (Dortmund – Hagen – Wuppertal – Solingen –) Cologne – Siegburg/Bonn – Montabaur – Limburg Süd – Frankfurt Airport – Frankfurt | Some services |
ICE 50 | Dresden – Leipzig – Erfurt – Eisenach – Fulda – Frankfurt – Frankfurt Airport – Wiesbaden | Every two hours |
ICE 62 | Frankfurt – Darmstadt – Heidelberg – Stuttgart – Augsburg – München – Salzburg – Linz or – Graz or – Villach – Klagenfurt | Four train pairs |
ICE 78 | Amsterdam – Arnhem – Duisburg – Cologne – Frankfurt Airport – Frankfurt | Every two hours |
ICE 79 | Bruxelles-Midi/Brussel-Zuid – Liège-Guillemins – Aachen – Köln – Frankfurt Airport – Frankfurt | |
ICE/TGV 82 | Frankfurt – Mannheim – Kaiserslautern – Saarbrücken/– Karlsruhe – Strasbourg – Paris Est | |
ICE/TGV 84 | Frankfurt – Mannheim – Karlsruhe – Baden-Baden – Strasbourg – Mulhouse-Ville – Belfort-Montbéliard – Besançon Franche-Comté – Chalon-sur-Saône – Lyon-Part-Dieu – Avignon – Aix-en-Provence – Marseille-Saint-Charles | One train pair |
IC 87 | Frankfurt – Heidelberg – Stuttgart – Singen | Individual services |
ECE 85 | Frankfurt – Mannheim – Karlsruhe – Baden-Baden – Freiburg (Breisgau) Hbf – Basel Bad Bf – Basel SBB – Olten – Lucerne – Arth-Goldau – Bellinzona – Lugano – Chiasso – Como – Monza – Milan | One train pair |
ICE 91 | Dortmund (– Essen – Duisburg – Düsseldorf) or (Wuppertal) – Cologne – Bonn – Koblenz – Mainz – Frankfurt Airport – Frankfurt – Würzburg – Nuremberg – Regensburg – Passau – Linz – Vienna | Every two hours |
RJ 63 | Frankfurt – Munich – Salzburg – Linz – Vienna – Budapest | Sat and Sun |
RJ 66 | Budapest – Vienna – Linz – Salzburg – Munich – Frankfurt | Fri and Sat |
Local services
editWith regard to regional traffic, Frankfurt Hbf is the main hub in the RMV network, offering connections to Koblenz, Limburg, Kassel, Nidda, Stockheim, Siegen, Fulda, Gießen, Aschaffenburg, Würzburg, Mannheim, Heidelberg, Dieburg, Eberbach, Worms and Saarbrücken with fifteen regional lines calling at the main station.
Line | Route | Interval |
---|---|---|
RE 2 | Frankfurt – Frankfurt Airport – Rüsselsheim – Mainz – Bingen (Rhein) – Koblenz | 120 min (extra trains to the peak) |
RE 3 | Frankfurt – Frankfurt Airport – Rüsselsheim – Mainz – Bingen – Koblenz/Bad Kreuznach – Saarbrücken | |
RE 4 | Frankfurt – Frankfurt-Höchst – Mainz – Worms – Ludwigshafen – Germersheim – Karlsruhe | 120 min |
RE 5 | Frankfurt – Frankfurt (Main) Süd – Hanau – Fulda – Bebra | Some trains |
RE 9 | Frankfurt – Frankfurt-Höchst – Mainz-Kastel – Wiesbaden-Biebrich – Wiesbaden-Schierstein – Niederwalluf – Eltville | 60 min (only in peak) |
RE 13 | Frankfurt – Frankfurt Airport – Rüsselsheim – Mainz – Alzey | Some trains in peak |
RE 14 | Frankfurt – Frankfurt-Höchst – Mainz – Worms – Ludwigshafen Mitte – Mannheim | 120 min |
RE 20 | Frankfurt – Frankfurt-Höchst – Niedernhausen (Taunus) – Limburg (Lahn) | 60 min (only in peak) |
RE 30 | Frankfurt – Friedberg (Hess) – Gießen – Marburg (Lahn) – Treysa – Wabern (Bz Kassel) – Kassel | 120 min |
RE 50 | Frankfurt – Frankfurt South – Offenbach – Hanau – Fulda | 60 min (only in peak) |
RE 54 | Frankfurt – Maintal – Hanau – Aschaffenburg – Würzburg – Bamberg | 120 min (with gaps to the peak) |
RE 55 | Frankfurt – Offenbach – Hanau – Aschaffenburg – Würzburg/– Bamberg | 120 min (Frankfurt–Würzburg; additional trains in the peak); individual trains in the peak (Würzburg–Bamberg) |
RE 60 | Frankfurt – Darmstadt – Bensheim – Weinheim (Bergstr) – Mannheim | 60/120 min |
RE 70 | Frankfurt – Groß Gerau-Dornberg – Riedstadt-Goddelau – Gernsheim – Biblis – Mannheim | 60 min |
RE 85 | Frankfurt – Offenbach – Hanau – Babenhausen – Groß-Umstadt Wiebelsbach (– Erbach (Odenw)) | 60 min (Frankfurt–Babenhausen); 120 min (Babenhausen–Erbach) |
RE 98 | Frankfurt – Friedberg – Gießen – Marburg – Treysa – Wabern – Kassel | Some trains between Frankfurt and Gießen in the peak |
RE 99 | Frankfurt – Friedberg – Gießen – Wetzlar – Dillenburg – Haiger – Siegen | |
RB 10 | Frankfurt – Frankfurt-Höchst – Wiesbaden – Rüdesheim (Rhein) – Koblenz – Neuwied | 60 min |
RB 12 | Frankfurt – Frankfurt-Höchst – Kelkheim – Königstein (Taunus) | 30 min |
RB 15 | Frankfurt – Bad Homburg – Friedrichsdorf – Wehrheim – Neu-Anspach – Usingen – Grävenwiesbach – Brandoberndorf | 60 min (only in peak) |
RB 22 | Frankfurt – Frankfurt-Höchst – Niedernhausen (Taunus) – Limburg (Lahn) | 30/60 min |
RB 34 | Frankfurt – Bad Vilbel – Niederdorfelden – Nidderau – Altenstadt (Hess) – Glauburg-Stockheim | 30/60 min |
RB 40 | Frankfurt – Friedberg (Hess) – Butzbach – Gießen – Wetzlar – Herborn (Dillkr) – Dillenburg | 40/80 min |
RB 41 | Frankfurt – Friedberg (Hess) – Butzbach – Gießen – Marburg (Lahn) – Cölbe – Kirchhain (Bz Kassel) – Stadtallendorf – Neustadt – Treysa | 60 min |
RB 48 | Frankfurt– Friedberg (Hess) – Beienheim – Reichelsheim (Wetterau) – Nidda | some trains in peak |
RB 51 | Frankfurt – Offenbach (Main) Hbf – Hanau – Langenselbold – Gelnhausen – Wächtersbach (– Bad Soden-Salmünster) | 60 min |
RB 58 | Rüsselsheim Opelwerk – Frankfurt Airport – Frankfurt – Frankfurt South – Frankfurt East – Maintal Ost – Hanau – Aschaffenburg – Laufach | 60 min in peak |
RB 61 | Frankfurt – Dreieich-Buchschlag – Rödermark-Ober Roden – Dieburg | 60 min |
RB 67 | Frankfurt – Darmstadt – Bensheim – Heppenheim (Bergstr) – Weinheim (Bergstr) – Mannheim | |
RB 68 | Frankfurt – Darmstadt – Bensheim – Heppenheim – Weinheim (Bergstr) – Heidelberg | |
RB 82 | Frankfurt – Darmstadt Nord – Reinheim (Odenw) – Groß-Umstadt Wiebelsbach – Erbach (– Eberbach) |
The subterranean S-Bahn station is the most important station in the S-Bahn Rhein-Main network, used by all Frankfurt S-Bahn lines, except line S 7, which terminates at the surface station.
Line | Route |
---|---|
Frankfurt (Main) Hbf – Walldorf (Hess) – Mörfelden – Groß Gerau-Dornberg – Riedstadt-Goddelau |
In brief | |
---|---|
Total number of tracks: | 120 |
Number of passenger tracks above ground: |
25 main tracks, 2 branch) 3 tram stops (2 tracks each) |
Below ground: | 4 S-Bahn tracks, 4 U-Bahn tracks (3 in use) |
Daily trains: (excluding Stadtbahn & tramway) |
342 long-distance 290 regional |
Passengers (daily): | 460,000 |
Other services
editTram connections are offered by TraffiQ, with tram lines 11 and 12 (station Hauptbahnhof/Münchener Straße), 14, 16, 17, 20, 21 and the Ebbelwei-Expreß. The lines U4 and U5 call at the subterranean Stadtbahn stop.
Preceding station | Frankfurt U-Bahn | Following station | ||
---|---|---|---|---|
Festhalle/Messe towards Bockenheimer Warte
|
U4 | Willy-Brandt-Platz towards Enkheim
| ||
Terminus | U5 | Willy-Brandt-Platz towards Preungesheim
|
Future expansion
editThis section needs to be updated.(March 2022) |
Construction of a railway tunnel with four platforms below the existing station was proposed in 2018 under the project name Fernbahntunnel Frankfurt am Main (Long-distance railway tunnel Frankfurt am Main).[33] As being listed as "urgent need" in the Federal Infrastructure Plan 2030, government funding for the scheme was secured. A study to determine feasibility of construction is expected to be completed by early 2021.[34]
Crime
editIn 2019, the Federal Police recorded 4,787 crimes at Frankfurt Hauptbahnhof, more than at any other German train station.[35] This included the murder of an eight-year-old boy on 29 July.[36][37]
References
edit- ^ "Tarifinformationen 2021" (PDF). Rhein-Main-Verkehrsverbund. 1 January 2021. p. 137. Archived from the original (PDF) on 15 May 2021. Retrieved 8 April 2021.
- ^ "Getting here & travelling around: Rail". Frankfurt.de. City of Frankfurt am Main.
Frankfurt central station is the most important rail transport hub in Germany.
- ^ Hager, Bernd (2013). "Atlas, die Erdkugel tragend …". Eisenbahngeschichte (in German). 58. DGEG Medien: 34–43.
- ^ a b c Mytzka, Johannes-Jakob (2014). "Betriebliche Untersuchung von Infrastrukturmaßnahmen im Umfeld von Frankfurt (Main) Hauptbahnhof". Eisenbahntechnische Rundschau (in German) (11): 15–18. ISSN 0013-2845.
- ^ Schomann 1983, p. 161.
- ^ "Notice no. 345". Amtsblatt der Königlich Preußischen und Großherzoglich Hessischen Eisenbahndirektion in Mainz (in German) (26). Eisenbahndirektion Mainz: 172. 27 May 1916.
- ^
Stahl, Hans-Günter (2015). Der Luftkrieg über dem Raum Hanau 1939–1945. Hanauer Geschichtsblätter (in German). Vol. 48. Hanau. p. 227.
{{cite book}}
: CS1 maint: location missing publisher (link) - ^
Lasky, Melvin (2014). And everything was still (German diary 1945). Berlin. p. 347. ISBN 978-3-87134-708-5.
{{cite book}}
: CS1 maint: location missing publisher (link) - ^ "notice no. 337". Amtsblatt der Reichsbahndirektion Mainz (in German) (21). Deutsche Reichsbahn: 145. 13 May 1944.
- ^ "Neue Betriebszentrale für Frankfurt/M". Eisenbahn-Revue International (in German) (1/2): 2. January 1999. ISSN 1421-2811.
- ^ a b c d "Frankfurt RheinMainplus" (PDF) (Das Projekt. Der Eisenbahnknoten. Die Schieneninfrastruktur.) (in German). Deutsche Bahn AG. June 2009. pp. 6f, 10f, 12, 28. Archived from the original (PDF; 1,63 MB) on 23 January 2013. Retrieved 9 May 2023. (32-page brochure)
- ^ a b Speck, Georg (October 1984). … und dann immer geradeaus. Ein Vorschlag für die Eisenbahn in Frankfurt am Main (in German). Fachgebiet Eisenbahnwesen, einschließlich spurgebundener Nahverkehr der Technischen Hochschule Darmstadt. pp. 2, 3, 15.
- ^ a b Harting, Mechthild (12 October 2020). ""Hier beginnt etwas Großes"". Frankfurter Allgemeine Zeitung (in German). Retrieved 16 May 2023.
- ^ Thomas, Peter (19 December 2021). "Aufbruch in die Unterwelt". Frankfurter Allgemeine Sonntagszeitung (in German). No. 50. p. 46.
- ^ Tempel, Norbert (2010). "Eine Wiedergeburt: Grundinstandsetzung der Gleishallen im Frankfurter Hauptbahnhof". Industrie-Kultur (in German) (50): 10f. (based on a manuscript by Volker Rödel)
- ^ a b c "B-Ebene des Frankfurter Hauptbahnhofs wird schöner". Frankfurter Allgemeine Zeitung (in German). No. 297. 22 December 2015. p. 29. ISSN 0174-4909.
- ^ "Vorbereitungen für die Erneuerung des Bahnsteiges 12/13 im Hauptbahnhof Frankfurt beginnen" (Press release) (in German). Deutsche Bahn AG. 26 February 2010.
- ^ a b "Sanierung des Frankfurter Hauptbahnhofs". Eisenbahn-Revue International (in German) (10): 429. October 2001. ISSN 1421-2811.
- ^ a b c Magiera, Dieter; Vorlitzky, Jürgen; Beinlich, Andreas; Bezzenberger, Wolfram; Briesen, Dieter (2006). "Elektronisches Stellwerk für den Hauptbahnhof Frankfurt am Main". Signal + Draht (in German). 98 (10): 6–9. ISSN 0037-4997.
- ^ a b c d "ESTW Frankfurt Hbf in Betrieb". Eisenbahn-Revue International (in German) (1): 4. January 2006. ISSN 1421-2811.
- ^ Leclerc, Florian (2 October 2020). "Hauptbahnhof Frankfurt wird umgebaut: So sehen die Pläne aus". Frankfurter Rundschau (in German). Retrieved 16 May 2023.
- ^ Rippegather, Jutta (19 March 2017). "Hauptbahnhof wird entflochten". Frankfurter Rundschau (in German). Retrieved 16 May 2023.
- ^ Wrede, Stephan; Gericke, Jens-Peter (July 2018). "Building Information Modeling ist die digitale Zukunft des Bauens". Der Eisenbahningenieur (in German). 68 (7): 16–18. ISSN 0013-2810.
- ^ "Deutsche Bahn beseitigt Engpass im Frankfurter Schienennetz: Zusätzliches Gleis zum Hauptbahnhof fertiggestellt" (Press release) (in German). Deutsche Bahn. 30 November 2021. Archived from the original on 30 November 2021. Retrieved 16 May 2023.
- ^ "Homburger Damm: Baubeginn der Maßnahmen im Knoten Frankfurt Hauptbahnhof" (Press release) (in German). Deutsche Bahn. 14 June 2017. Archived from the original on 10 July 2017. Retrieved 16 May 2023.
- ^ "Aus Geschäftlichen Mitteilungen". Lok-Report (in German) (11): 24–26. November 2019. ISSN 0344-7146.
- ^ "Not known". Frankfurter Rundschau (in German). 14 November 2013. p. D2.
- ^ Jaeger, Milan; Leclerc, Florian (8 October 2014). "Einkaufszentrum im Hauptbahnhof". Frankfurter Rundschau (in German). Retrieved 16 May 2023.
- ^ "Bundesverkehrsminister kündigt Fernbahntunnel für Frankfurt an". Offenbach-Post (in German). 14 November 2018. Retrieved 16 May 2023.
- ^ "Planung für Fernbahntunnel startet: Täglich 250 Züge mehr zum Hauptbahnhof Frankfurt". deutschebahn.com (Press release) (in German). 28 June 2021. Retrieved 16 May 2023.
- ^ "Die nächsten Schritte Fernbahntunnel Frankfurt". fernbahntunnel-frankfurt.de (in German). 28 June 2021. Retrieved 16 May 2023.
- ^ "Mehr Fortschritt wagen: Bündnis für Freiheit, Gerechtigkeit, und Nachhaltigkeit" (PDF) (Koalitionsvertrag 2021–2025 zwischen der Sozialdemokratischen Partei Deutschlands (SPD), BÜNDNIS 90 / DIE GRÜNEN und den Freien Demokraten (FDP)) (in German). SPD, Bündnis 90/Die Grünen, FDP. November 2021. p. 13. Retrieved 16 May 2023.
- ^ "Das Ende des Kopfbahnhofs, so wie wir ihn kennen". fnp.de. 8 November 2018. Retrieved 5 October 2020.
- ^ "Knoten Frankfurt; Fernbahntunnel inkl. Station unterhalb des Hbf Frankfurt/Main, Machbarkeitsstudie". ted.europa.eu. Retrieved 5 October 2020.
- ^ "Frankfurter Hauptbahnhof mit den meisten Straftaten". Frankfurter Allgemeine (in German). 7 March 2020. ISSN 0174-4909. Retrieved 4 February 2023.
- ^ "Germany train incident: Eritrean on trial for boy's Frankfurt death". BBC News. 19 August 2020. Retrieved 4 February 2023.
- ^ "Frankfurt rail attack: Boy's killer given life in psychiatric ward". BBC News. 28 August 2020. Retrieved 4 February 2023.
Sources
edit- Bundesbahndirektion Frankfurt am Main (1988). Abfahrt 1888, Ankunft 1988: 100 Jahre Hauptbahnhof Frankfurt am Main. Darmstadt: HESTRA-Verlag. ISBN 3-7771-0215-6.
- Groß, Lothar (2012). Made in Germany: Deutschlands Wirtschaftsgeschichte von der Industralisierung bis heute. Vol. 1: 1800 - 1945. Books on demand. ISBN 978-3-8482-1042-8.
- Rödel, Volker (2006). Der Hauptbahnhof zu Frankfurt am Main. Aufstieg, Fall und Wiedergeburt eines Großstadtbahnhofs [The main station to Frankfurt am Main. Rise, Fall and Rebirth of a City Train Station]. Arbeitshefte des Landesamtes für Denkmalpflege Hessen 8. Stuttgart.
{{cite book}}
: CS1 maint: location missing publisher (link) - Schomann, Heinz (1983). Der Frankfurter Hauptbahnhof. Ein Beitrag zur Architektur- und Eisenbahngeschichte der Gründerzeit [The Frankfurt central station. A contribution to the architectural and railway history of the Wilhelminian era]. Deutsche Verlags-Anstalt. ISBN 3-421-02801-X.
- Setzepfandt, Wolf-Christian (August 2002). Architekturführer Frankfurt am Main [Architecture Guide Frankfurt am Main]. Berlin: Dietrich Reimer Verlag. p. 33. ISBN 3-496-01236-6.