Hale Dam is a hydroelectric dam in Tanzania, located in the town of Hale in Mnyuzi ward of Korogwe District of Tanga Region. Its installed capacity is 21 megawatts (28,000 hp). Thousands of people were displaced to build the dam.

Hale Dam
Hale Dam is located in Tanzania
Hale Dam
Map of Tanzania showing the location of Hale Dam
Official nameHale Power Station
LocationHale, Mnyuzi, Korogwe District, Tanga, Tanzania
Coordinates05°17′53.3″S 38°36′14.8″E / 5.298139°S 38.604111°E / -5.298139; 38.604111
Construction began1961
Opening date1964
Construction cost£5,000,000 (1964)
Owner(s)TANESCO
Dam and spillways
ImpoundsPangani River
Spillway typeEarth and Rock Fill
Spillway capacity1,190 m3 (0.96 acre⋅ft)
Power Station
Operator(s)Tanesco
Commission date1964
Turbines2x10.5
Installed capacity21 MW (28,000 hp)
Website
Tanesco website

History

edit

The Hale Dam is the oldest operation dam currently in the country. The Pangani river basin had been a source of power since the early colonial times for Tanganiyka. The lower Pangani power plant was established at Pangani Falls by a German company as early as 1936. With the growing Tanga region and the close proximity to Mombasa, the government decided to construct a new Hydro electric power plant in Hale.[1]

The plant began construction in 1961 and cost around £5,000,000, which was the single largest investment into the country since the failed groundnut scheme.[1] The power-plant became operational in November 1964.[2]

Overview

edit

The Hale hydro electric Power Plant utilizes a natural fall of 70 meters. It is sited at Hale Township on the Segera–Tanga highway, 6 km from the Tanga – Moshi junction at Segera.[2]

Water from the neighboring rivers is channeled and dropped 70 meters below the ground surface. The power-plant its self is based 76 meters below the surface. The underground power station generates power by two vertical units comprising Francis turbines and salient pole generators and has an installed capacity of 21 MW (28,000 hp).[2]

The plant has undergone heavy rehabilitation twice since its inauguration, in 1987 and 2009.[2]

The construction of the dam in the 1960s led to the displacement of about 12,000 people. However, after the establishment of the dam, with a big supply of water and fish, it attracted a large proportion of migrants from fishing communities. This has also led to the establishment of big urban settlements called Nyumba ya Mungu, with an estimated population of about 20,000 people in 2002. The growing population led to a lot of water conflicts.[3]

See also

edit

References

edit
  1. ^ a b Datoo, B.A. (April 1965). "The generation of hydro-electric power on the lower Pangani river" (PDF). East African Geographical Review. 3: 47–49. Archived from the original (PDF) on 4 March 2016. Retrieved 29 July 2015.
  2. ^ a b c d "Pangani Hydro Systems". TANESCO. Archived from the original on 24 September 2015. Retrieved 29 July 2015.
  3. ^ Mbonile, Milline J. (March 2005). "Migration and intensification of water conflicts in the Pangani Basin, Tanzania". Habitat International. 29 (1): 41–67. doi:10.1016/s0197-3975(03)00061-4.
edit