The Yanchep line (known as the Joondalup line prior to 14 July 2024) is a suburban railway line and service in Perth, Western Australia, linking the city's central business district (CBD) with its northern suburbs. Operated by the Public Transport Authority as part of the Transperth system, the Yanchep line is 54.5 kilometres (33.9 mi) long and has sixteen stations. It commences in a tunnel under the Perth CBD as a through service with the Mandurah line. North from there, the line enters the median strip of the Mitchell Freeway, where nine of the line's stations are. The Yanchep line diverges from the freeway to serve the centre of Joondalup and permanently leaves the freeway north of Butler for the northernmost four stations to Yanchep.

Yanchep line
A freeway with a railway in the median strip
Overview
Other name(s)Northern Suburbs Railway
Joondalup line (former name)
OwnerPublic Transport Authority (2003–present)
LocalePerth, Western Australia
Termini
Continues asMandurah line
Stations16
Service
TypeSuburban rail
SystemTransperth
Operator(s)
Depot(s)
Rolling stock
Ridership16,135,201 (year to June 2024)
History
CommencedNovember 1989 (November 1989)
Opened
  • 20 December 1992 (20 December 1992) (partial)
  • 21 March 1993 (21 March 1993) (full opening)
Last extension14 July 2024 (14 July 2024)
Technical
Line length54.5 km (33.9 mi)
Number of tracks2
CharacterAt-grade and underground
Track gauge1,067 mm (3 ft 6 in) narrow gauge
Electrification25 kV 50 Hz AC from overhead catenary
Operating speed130 km/h (81 mph)
SignallingFixed block signalling
Train protection systemAutomatic train protection
Route map

54.5
Yanchep Bus transfer
46.7
Eglinton Bus transfer
43.0
Alkimos Bus transfer
40.7
Butler Bus transfer
Nowergup depot
33.2
Clarkson Bus transfer
29.2
Currambine
26.2
Joondalup Bus transfer
22.9
Edgewater
19.8
Whitfords Bus transfer
17.7
Greenwood
14.5
Warwick Bus transfer
8.8
Stirling Bus transfer
5.6
Glendalough Bus transfer
2.4
Leederville Bus transfer
Perth Transperth Transwa
0.0
Perth Underground Bus transfer
0.6
Elizabeth Quay Bus transfer

Planning for a rapid transit service to the northern suburbs began in 1987. After several transport modes were considered, including bus rapid transit, an electric railway was chosen. Known during planning and construction as the Northern Suburbs Railway, the project was approved by state cabinet in late 1989 and construction began in November 1989. The line was built under several different contracts, with the total cost of the original project being A$277 million. It used widely-spaced stations with bus interchanges and large park-and-rides, distinguishing the line from Perth's three existing rail lines. The line opened on 20 December 1992 as the Joondalup line to limited service and with three stations: Leederville, Edgewater and Joondalup. Four more stations opened in February 1993, and on 21 March 1993, peak service and feeder bus routes commenced. The final station, Currambine, opened on 8 August 1993.

An extension north to Clarkson station and rebuild of Currambine station opened on 4 October 2004, which coincided with the introduction of B-series trains. On 29 January 2005, Greenwood opened as an infill station. The Joondalup line originally through-ran with the Armadale line via Perth station, but in 2005, the line started terminating at Perth station, and on 15 October 2007 the line was rerouted through a new tunnel under the CBD, with two new stations: Perth Underground and Elizabeth Quay. The Mandurah line opened on 23 December 2007 to connect with the southern end of that tunnel. An extension north to Butler station opened on 21 September 2014 and a three station extension north to Yanchep station was opened on 14 July 2024, upon which the line became the Yanchep line.

B-series and C-series trains are the main rolling stock used on the Yanchep line. End-to-end services run at a fifteen minute headway, reducing to a ten minute headway in peak. Additional peak services run between Perth and Whitfords or Clarkson stations, making for a five minute headway on inner sections of the line. The travel time from Yanchep to Perth Underground is 49 minutes. The Yanchep line received 16,135,201 boardings in the 2023–24 financial year, making it the second busiest line in the Transperth system, after the Mandurah line.

History

edit

Planning

edit

The 1955 Plan for the Metropolitan Region, Perth and Fremantle, also known as the StephensonHepburn Report, proposed a 12-mile (19 km) railway line branching off the Eastern Railway (Fremantle line) at Daglish, then heading west to Reabold Hill and then north to Whitfords Beach via City Beach, Scarborough, and North Beach. The branch was planned to have about eight or nine stations and projected to have about 20,000 daily passenger journeys. The report also proposed a highway to Yanchep, now known as the Mitchell Freeway.[1][2] When the Metropolitan Region Scheme was adopted in 1963 though, the land for the proposed highway was reserved but the not the land for the proposed railway.[3][4]

The Northern Suburbs Rapid Transit Study was commissioned in 1987 by Transperth and the Department of Transport at the request of the Government of Western Australia. The study, published in September 1988 and written by a team of consultants, considered possible modes of transport and the route to take.[5] Routes considered were along West Coast Highway, Marmion Avenue, the western side of the Mitchell Freeway, the median strip of the Mitchell Freeway, the eastern side of the Mitchell Freeway, Wanneroo Road, and Alexander Drive. The median strip of the Mitchell Freeway was determined to have the lowest cost and least environmental impact out of each of the routes.[6] Transport modes considered by the study were buses on a separate roadway, buses on a guided busway (like the O-Bahn Busway in Adelaide), light rail, heavy rail, automated rubber-tyred trains, high-capacity monorail, and an automated people mover system. A monorail or automated people mover were ruled out due to the cost and unproven nature of those technologies. Light rail was also ruled out due to having a lower operating speed than other modes and the desire to not introduce another mode to Perth's transport system.[6] A bus expressway, guided busway and electric railway along the Mitchell Freeway were all shortlisted for further consideration.[6][7]

Public consultation found that 41.0 percent of people preferred an electric railway, 34.4 percent preferred a bus expressway, 19.3 percent preferred a guided busway, 3.2 percent did not want any rapid transit, and 2.2 percent preferred some other option. The people who preferred rail chose it because of its greater comfort, lower pollution and less crowding. The people who preferred the bus options chose them because there would be no transfer for trips into the Perth central business district (CBD) and the bus options would cost less than a railway.[8] The study suggested that the bus options could be built in multiple stages and the rail option could first be built between Perth and Warwick and later be extended to Joondalup.[9] The two bus options were projected to increase northern suburbs public transport patronage by fourteen percent and the rail option was projected to increase patronage by nine to twelve percent, less than the bus options due to the time taken to transfer from bus to train.[10] The net cost of the railway was estimated to be A$145 million, compared to $87 million for the guided busway and $79 million for the bus expressway.[11] The study concluded that either of the bus options were preferred over the electrified railway, and that further studies should determine whether to build a bus expressway or a guided busway.[12]

In response to the Northern Suburbs Rapid Transit Study, the state minister for transport, Bob Pearce, set up an expert panel consisting of Murdoch University Associate Professor Peter Newman, Tyne and Wear Transport Director General David F. Howard, and University of Pennsylvania Professor Vukan Vuchic.[13] The expert panel concluded that an electrified railway would be the best option instead of a bus rapid transit system.[14] They costed an electric railway at $124 million and gave a lower operating cost for the railway compared to the bus options, making up the difference in cost within 12 to 15 years.[15] The expert panel criticised the Northern Suburbs Rapid Transit Study for concentrating on commuters travelling to the CBD and said that the bus system the study recommended would not serve people doing short or local trips well.[16] The panel said that other cities show that a rail trunk line with feeder buses would attract more passengers.[17] State cabinet officially chose the railway option in December 1988.[18][19] The Liberal Party supported plans for a bus lane within the Mitchell Freeway, which prompted Pearce to claim that the Liberals did not want the railway.[20][21]

State cabinet officially approved the Northern Suburbs Transit System Master Plan in the second half of 1989. The planned opening dates were the end of 1992 for Perth to Joondalup and the end of 1993 for Joondalup to Currambine.[22] The master plan was released in November 1989. It laid out the route of the Northern Suburbs Railway and works proposed to occur. The railway was to be 29 kilometres (18 mi) long and have seven new stations: Glendalough, Warwick, Whitfords, Edgewater, Joondalup, and Burns (later renamed Currambine). It also gave the option of building stations at Oxford Street in Leederville, Wishhart Street between Stirling and Warwick, or Hepburn Avenue between Warwick and Whitfords.[23] Perth station, the centre of the rail network and southern terminus of the Northern Suburbs Railway, was planned to be expanded.[24] The railway's planned route was mostly along the median strip of the Mitchell Freeway, deviating in the Perth CBD to reach Perth station and in Joondalup to serve the future city centre of Joondalup. A section between Joondalup and Burns was to be west of the future freeway, which at the time only reached as far north as Ocean Reef Road. The section through Joondalup was to be in a trench below surface level to allow for roads to bridge across.[25] The railway was to be fully grade separated with no level crossings, unlike Perth's existing rail network.[26]

The Northern Suburbs Railway's route was placed in the Mitchell Freeway's median strip to reduce costs as the freeway was already grade separated from other roads and had its own right of way. The disadvantage of freeway-running railways is that access to the stations is more difficult, with walking distance in earlier plans from a bus interchange to the platform being between 70 metres (230 ft) and 180 metres (590 ft), and even longer for park and ride passengers. Earlier plans also had limited shelter and facilities at each station.[27] This was deemed bad for patronage, so the master plan instead located bus interchanges closer to the station platform. In the cases of Stirling, Warwick and Whitfords stations, the bus interchanges are on a bridge directly above the train platforms.[28] The feeder buses were planned to run between pairs of adjoining stations at a 10 to 15 minute headway in peak, covering the area between Wanneroo Road and the coastline. According to forecasts, two thirds of Northern Suburbs Railway passengers would use the feeder buses and 120 buses would be required. The opening of the railway would allow for express buses along the Mitchell Freeway to be phased out.[24]

Much of the Mitchell Freeway was designed with provisions for a public transport corridor in its median strip. However, a 5-kilometre (3 mi) section between Loftus Street in Leederville and Hutton Street in Osborne Park was not. This section was built as just a single carriageway with a dividing barrier. On that section, a second carriageway, which now carries the freeway's northbound lanes, was planned to be constructed. Additional bridges would be built across Vincent Street, Powis Street, and Scarborough Beach Road for the new carriageway and the railway. Twelve other road bridges and nine pedestrian bridges needed minor modifications so that there was enough clearance for the overhead wires, and four bridges over the railway in Joondalup needed to be constructed.[29][30] The master plan said that alterations to Perth station were required. This included a new platform at the station's northern side, a new concourse west of the Horseshoe Bridge, and an extra span on the Barrack Street bridge.[31] New stowage tracks at Claisebrook depot would be required, and trains would also be stored at Whitfords station temporarily and at Currambine station.[26]

The total cost of the Northern Suburbs Railway was estimated to be $222.8 million (equivalent to $530 million in 2022), of which $133.17 million was for the railway's construction and $89.63 million was for the acquisition of 22 two-car electric multiple unit trains. An additional $27 million for the works to widen the Mitchell Freeway between Leederville and Osborne Park was funded separately[32] and managed by the Main Roads Department.[30] The rest of the construction works were managed by Westrail. The $222.2 million was higher than the $150 million estimated in 1988 due to an underestimation in the cost of some parts of the project, increased facilities at stations, more bridges, the extension to Currambine which was not accounted for, additional railcars due to higher forecasted demand, and inflation.[33] The railway was planned to opened between Perth and Joondalup by the end of 1992 and from Joondalup to Currambine by the end of 1993.[34]

Construction

edit

In November 1989, the Fremantle line was realigned north between Perth station and the Mitchell Freeway to make way for the Roe Street tunnel. Premier of Western Australia Peter Dowding hammered in the first spike on 14 November 1989, marking the start of construction.[22][35] That year, the Parliament of Western Australia passed an enabling act authorising the construction of the railway, and on 15 January 1990, the act received royal assent.[36][37]

 
The Yanchep line north of the Roe Street tunnel, October 2024

By the end of 1990, earthworks at Joondalup and the Mitchell Freeway roadworks between Loftus Street and Hutton Street were underway. The project's first contract was awarded in December 1990 to Remm Constructions.[38] It was a $4.3 million contract for the construction of the walls of the tunnel under Roe Street.[38][39][40] The tunnel is 130 metres (430 ft) long, with 250-metre-long (820 ft) ramps at each end. The tunnel and ramp's route partially followed a bus on ramp from Roe Street to the freeway, allowing the reuse of a bridge carrying the Mitchell Freeway's westbound carriageway above the bus lane. A temporary bus on ramp was used until the railway was opened.[40] The tunnel walls were constructed using secant piles. The close proximity of the tunnel to the Mitchell Freeway's bridge footings complicated the construction process and necessitated preventing any ground movement.[38][41] The tunnel's second contract, for the excavation and construction of the floor and roof, was awarded to Leighton Contractors. Construction on that phase was planned to take place in the second half of 1991.[40] The tunnel's total cost was about $8–9 million.[38][40]

 
Lake Monger in October 2021
 
Leeder Street footbridge, which connects to Glendalough station

The second Mitchell Freeway carriageway between Loftus Street and Hutton Street passed in close proximity to the environmentally sensitive Lake Monger.[30] After criticism over the encroachment on the lake,[42][43] Premier Carmen Lawrence announced in July 1990 that a review of the plans would be undertaken by Peter Newman in cooperation with Main Roads engineers.[44] In response to Newman's report, the new carriageway was scaled back from five lanes to four.[45][46][47] About 650,000 tonnes (640,000 long tons; 720,000 short tons) of sand from the Joondalup area was used to compact the marshy soil next to the lake.[30] Most of the Mitchell Freeway roadworks were done in-house by Main Roads Department staff,[30] but the road and rail bridges across Vincent Street, Powis Street, and Scarborough Beach Road were built by Leighton Contractors for $8.8 million. Work started on those bridges in April 1991. The bridges were incrementally launched to avoid disruption to road traffic.[48] Three cable-stayed footbridges across the freeway were also constructed by Leighton Contractors under a separate $5.3 million contract. The Britannia Road footbridge was new, while the Oxford Street and Leeder Street bridges were replacing old footbridges that were not long enough for the widened freeway. The latter two footbridges provide access to Leederville and Glendalough stations respectively.[49][50] The new northbound Mitchell Freeway carriageway opened on 21 June 1992, after eighteen months of construction, allowing railway work along that section to begin.[51]

The Fitzgerald Street level crossing, used by buses to access the Wellington Street bus station, was relocated 250 metres (820 ft) west to avoid intersecting with the Northern Suburbs Railway.[52][53] The master plan said the level crossing should be replaced by a bridge,[54] but parliament passed legislation in November 1991 to prevent the bridge from being built without the government consulting the Perth City Council, residents and businesses.[55][56] The legislation was introduced to parliament by the independent member for Perth, Ian Alexander, who wanted the railway tunnelled and a ground-level bus road built instead, calling the bridge a "cheap and nasty solution". Transport Minister Pam Beggs said that tunnelling the railway would cost an additional $11 million and that she would rather spend money on the outer suburbs.[57] Beggs submitted a report to the Legislative Assembly detailing consultation with the stakeholders, but a resolution to build the bridge failed to pass, leading to the bridge's cancellation.[58] The new level crossing opened in March 1993.[59] A nearby bridge next to the Mitchell Freeway ended opening in 2010 as part of the construction of Perth Arena.[60][61]

External images
  A train carrying ballast via Rail Heritage WA
  A train carrying rails during tracklaying via Rail Heritage WA
  An ADK diesel multiple unit during testing via Rail Heritage WA

The overhead line equipment was built by Barclay Mowlem as an extension to their contract for the electrification of the existing rail network.[62] Installation of the masts for the overhead line equipment was underway by April 1992. The masts were manufactured by Delta Corporation.[63][64] Unusually, the masts were installed before the tracks were laid, as track laying was delayed by the Mitchell Freeway works.[65] Track laying by Westrail started in July 1992, starting at the southern end and heading north.[66][67] This was paused by a week-long strike by Westrail locomotive drivers in October 1992.[68][69] In November 1992, a $1.2 million contract was awarded to TG Industries to supply a galvanised steel barrier between the railway and the Mitchell Freeway.[70] The master plan only called for crash barriers at stations, where the tracks are below freeway level, and a few other circumstances.[71] A $2.8 million contract for the construction of Currambine station was awarded to Doubikin Constructions in November 1992 as well.[70] The Edgewater substation was turned on for the first time on 31 October 1992, and the overhead line equipment was energised on 1 November 1992.[72][73][74] On 20 November 1992, the first A-series train ran on the railway,[75] and on 14 December 1992, driver training commenced, a week later than planned due to strikes by Westrail locomotive drivers in November 1992.[76]

Opening

edit
 
Plaque commemorating the opening of the Joondalup line on 20 December 1992 at Perth station

The first stage of the Joondalup line was officially opened on 20 December 1992 by Premier Carmen Lawrence and Transport Minister Pam Beggs. This involved the opening of Leederville, Edgewater and Joondalup stations. The West Australian newspaper reported that hundreds of people attended the opening of Leederville and Edgewater stations, and thousands of people attended the opening of Joondalup station, but that the state opposition criticised the opening ceremonies by saying that they were an "expensive political extravaganza". From 21 December, train services ran under a limited service "discoveride" brand, meaning that train services had a limited frequency of every half-an-hour and only operated between 9:30 am and 2:30 pm.[77][78][79][80]

The remaining four stations opened throughout February 1993: Whitfords on 14 February,[81] Glendalough and Stirling on 21 February,[82] and Warwick on 28 February.[83] Full service on the line between Perth and Joondalup was originally scheduled to commence on 7 March 1993,[84] but was delayed by two weeks as driver training took longer than expected.[85] Full service commenced on 21 March 1993. This included trains in peak hour for the first time and feeder buses servicing the Joondalup line's bus interchanges.[86][87][88] Bus routes along the Mitchell Freeway were withdrawn, which included some of Perth's busiest bus routes, such as the 396 to Warwick.[89][90] The bus changes encountered resistance, particularly for their impact on schoolchildren,[91][92] which led to the retention of two of the school bus services that were planned to be cancelled.[88] Services to and from Joondalup through ran with the Armadale line, while services to and from Whitfords terminated at Perth.[93] Recently-appointed Coalition Transport Minister Eric Charlton held a small opening ceremony at Joondalup station, in contrast to the large opening ceremony conducted by the Labor government in December 1992.[86][88] He also highlighted the increased operating costs that the new line would have and the debt resulting from the line's construction, which was used as a justification for a fare increase.[88][94][95] The final part of the Northern Suburbs Railway, the 3 kilometres (1.9 mi) from Joondalup to Currambine station, opened on 8 August 1993. The final cost was $277 million.[96][97]

Expansion under New MetroRail

edit

In 1995, the government began planning an extension north of Currambine.[98] During the 1996 state election campaign, Liberal Premier Richard Court committed to constructing an extension from Currambine to Clarkson by 2000 for $28 million, plus $12 million for additional rolling stock.[99][100] In December 1997, the state government also committed to building Greenwood station at Hepburn Avenue,[101] which was one of the sites given for an optional station by the 1989 master plan.[23] Parliament passed an enabling act for the extension to Clarkson and the construction of the Mandurah line in November 1999.[102]

In June 2000, it was announced that the completion of the Clarkson extension had been delayed until 2003.[100] Later that month, the Currambine to Butler Extension Master Plan was released. It detailed the plans for the extension north to Clarkson, the construction of Greenwood station, and a later extension to Butler.[103][104] The extension to Clarkson was planned to be within the freeway's median, for consistency with the rest of the Joondalup line and the planned Mandurah line,[105] and for "environmental and social benefits".[106] This meant that Currambine station would have to be rebuilt, as the original station was on the western side of the future Mitchell Freeway rather than the median.[103][105] Other works proposed in the master plan were for the construction of a railcar depot in Nowergup north of Clarkson station to allow for more trains and replace the stowage facility at Currambine, and extensions to all the platforms along the line to allow for six-car trains.[107] The estimated cost of the whole project was $58 million for the infrastructure, and $23 million for the additional rolling stock, for a total of $81 million.[104][108] By October, the cost had risen to $99 million.[109]

 
Clarkson station, which opened on 4 October 2004

The first contract for the Clarkson extension was awarded in March 2001, when Brierty Contractors signed a $14 million earthworks contract.[110] Work began in May 2001[111][112] and was completed in November 2002.[113] In July 2001, the contract for the construction of the rail bridge over Burns Beach Road was awarded to Transfield Pty Ltd for $1.7 million.[110][114] The bridge was completed in May 2003.[115] In April 2002, Barclay Mowlem and Alstom were awarded a contract worth $17 million for the rail infrastructure for the extension.[110] This contract included the design and construction of the track, traction power, signalling and communications systems, as well as track relocation at Greenwood station.[116] The $3.2 million contract for the construction of Currambine station was awarded to John Holland Group in March 2002,[110] and in November 2002, an $8.7 million contract was awarded to Transfield for the construction of Clarkson station.[117] In February 2004, a $6.8 million contract to build Greenwood station was awarded to John Holland Group.[118][119] Construction of Greenwood station began in March 2004.[120][121]

The contract for the platform extensions was awarded to Lakis Constructions in 2003 for $4.8 million.[122] By April 2004, the extensions at Leederville and Edgewater stations were complete.[123] The extensions at Warwick and Whitfords stations were complete by July 2004, and the extensions at Glendalough, Stirling and Joondalup stations were complete soon after that, ready for the extension to Clarkson to open.[124]

 
Greenwood station, which opened on 29 January 2005

Nowergup depot, which cost $36 million, officially opened in June 2004.[125] The extension to Clarkson and new Currambine station opened on 4 October 2004, the same day on which the first five Transperth B-series trains entered service on the Joondalup line.[126][127][128] The railway line south of Currambine station was largely left as is, and was not relocated until the Mitchell Freeway was extended to Burns Beach Road in 2007 and 2008 by Macmahon Contractors. This extension also involved the construction of a tunnel to carry the railway line under the freeway.[129][130][131] On 29 January 2005, Greenwood station was opened by Premier Geoff Gallop and Minister for Planning and Infrastructure Alannah MacTiernan.[132]

Mandurah line

edit

In March 1999, the South West Metropolitan Railway Master Plan was approved by the state government. It was to branch off the Armadale line at Kenwick to head to Mandurah, south of Perth.[133] It was chosen that the Joondalup line would through-run with the Mandurah line upon its opening, instead of the Armadale line. This was because both lines had similar levels of demand, with six-car trains required to meet demand on both lines.[134] Following the election of a Labor government, in July 2001, the state government announced that the proposed South West Metropolitan Railway would be rerouted via the Kwinana Freeway, with a tunnel under the Perth CBD to connect the Mandurah line to the Joondalup line.[135][136] A new master plan was released in August 2002.[137][138] The master plan divided the Mandurah line's construction into several packages, with Package F being for the construction of the tunnel under the Perth CBD and connection with the Joondalup line, also known as the City Project.[139][140]

 
The Joondalup line (left) on 6 October 2007, one day before the line was shut down to connect to the William Street tunnel tracks (middle). The Fremantle line is on the right.

The contract for the City Project was awarded to Leighton–Kumagai Gumi in February 2004 for $324.5 million.[141] With the opening of the Thornlie line, through services to the Armadale line ceased on 8 August 2005 and Joondalup line trains began terminating at Perth station, in preparation for through running with the Mandurah line.[142][143] The City Project reached practical completion in September 2007.[144] From 7 October to 14 October 2007, the Joondalup line was shut down between Leederville and Perth stations and the Fremantle line was fully shut down to connect the tunnel tracks to the Joondalup line.[145][146] The Joondalup line reopened on 15 October 2007 with its new southern terminus at Esplanade station.[147][148] The Mandurah line opened on 23 December 2007.[145][149]

Extension to Butler

edit

The first contract for the Butler extension, for earthworks north of Nowergup depot to Landbeach Boulevard, a distance of 4 kilometres (2 mi), was awarded to RJ Vincent & Co for $6 million in December 2010.[150][151] A second contract was awarded in May 2011, to Bocol Constructions and RJ Vincent & Co for $9.8 million. This was for the construction of three bridges to cross over the Butler extension and associated works.[152][153] By June 2012, Cooper and Oxley had been awarded the contract for Butler station's construction, worth $22 million.[154][155] Construction on the station began on 16 July 2012.[156] By October 2012, earthworks and bridge construction was complete, allowing track laying to commence. The $24 million track laying contract had been awarded to John Holland Group.[157] In November 2012, the contract for signalling was awarded to Ansaldo STS Australia for $19.7 million.[158][159] By October 2013, track laying was eighty percent complete,[160] and by April 2014, Butler station was complete.[161]

 
Butler station, which opened on 21 September 2014

The first train ran on the Butler extension on 25 August 2014,[156] with train driver familiarisation beginning after that.[162] The extension was opened on 21 September 2014 by Premier Colin Barnett and Minister for Transport Dean Nalder, three months early and $20 million under budget.[163][164][165] Following the opening of the extension to Butler, some nearby residents experienced excessive vibrations when trains passed by, with a petition complaining about the problem gaining 178 signatures. Acoustic matting was used for parts of extension, but not the area closest to Butler station, which was where the complaints were coming from.[166][167][168] The results of noise monitoring were released in December 2014. The results concluded that noise and vibration levels near Butler station were within acceptable limits, but another section of the extension was above acceptable limits, so a larger noise wall was built there.[169]

Extension to Yanchep

edit

Labor promised ahead of the 2017 state election that it would build the Yanchep Rail Extension as part of its revised Metronet plans. It was promised that the extension would open in 2021 and cost $386 million.[170] The September 2017 state budget gave the Yanchep Rail Extension a cost of $520.2 million.[171][172][173] The business case for the Yanchep Rail Extension was submitted to Infrastructure Australia in August 2017.[174] In November 2018, Infrastructure Australia released its assessment of the project, adding the project to the Infrastructure Priority List as a "High Priority Project" and giving it a projected economic benefit of $2.549 billion and a benefit–cost ratio of 2.6. Infrastructure Australia recommended that the contract for the Thornlie–Cockburn Link be combined with the contract for the Yanchep Rail Extension to save costs during procurement.[175][176][177] The Infrastructure Australia assessment allowed $700 million in federal funding to be spent on the Yanchep Rail Extension and the Thornlie–Cockburn Link, of which $350 million was for the Yanchep Rail Extension.[178][179]

Enabling legislation was introduced to the Parliament of Western Australia in May 2018[180][181] and passed in November 2018.[182] The project definition plan, detailing the scope of the project, for the Yanchep Rail Extension was approved by state cabinet in July 2018.[183] A request for proposal was released in September 2018 for the design and construct contract for the Yanchep Rail Extension and the Thornlie–Cockburn Link.[184][185] Two consortia were shortlisted in April 2019: METROconnex, a joint venture between Coleman Rail, Clough Group, and Georgiou Group; and NEWest Alliance, a joint venture between CPB Contractors and Downer.[186][187][188] In November 2019, NEWest Alliance was announced as the preferred proponent,[189][190][191] and the contract was awarded in the following month.[192][193][194] The cost of the Yanchep Rail Extension at the time was $531.7 million.[195]

 
Alkimos station under construction in February 2023
 
Howden Road bridge under construction in August 2023

Early works began in November 2019 and a sod turning ceremony took place on 24 November, making the Yanchep Rail Extension the second Metronet project to begin construction, after the Forrestfield–Airport Link.[195] Major works on the Yanchep Rail Extension began in mid-2020.[196] Construction at Alkimos station had begun by March 2021, with the first major concrete pour taking place that month.[197]

In June 2021, PerthNow reported that work on the Yanchep Rail Extension had stalled, but the PTA was still saying the extension would open in late 2022.[198] The government first raised the potential for a delay in July 2021,[199] and after the September 2021 state budget, it was revealed that the Yanchep Rail Extension's opening date would be delayed by a year to late 2023 due to a skills shortage and to ease pressure on Western Australia's construction industry.[200][201][202] To cut costs, the construction of a shared path along the extension was cancelled, with the decision being justified by there also being a shared path along Marmion Avenue and a proposed one to be constructed as part of the extension of the Mitchell Freeway. The decision to cancel the shared path was criticised by cycling groups and the City of Wanneroo.[203][204][205] By the end of 2021, work on all three stations was underway. At Eglinton and Yanchep stations, the foundations were being poured, and at Alkimos station, retaining walls had been put up.[206][207]

The March 2022 federal budget revealed the federal government would provide $90 million of additional funding for the project, bringing its share of the project to $440 million.[208][209] The May 2022 state budget revealed a $175.3 million cost increase,[210] the May 2023 state budget revealed a $375.3 million cost increase,[211][212][213] and the May 2024 state budget revealed a $288 million cost increase,[214][215] bringing the extension's total cost to $1.27 billion.[216] The Liberal Party has readily criticised the cost increases, saying the money should instead be spent on healthcare among other things, but Transport Minister Rita Saffioti blamed the cost increases on increases in the cost of steel, diesel, and concrete, and the COVID-19 pandemic.[217][218][219]

After the May 2023 budget, the government said that the Yanchep extension "is due for completion at the end of 2023, with services commencing in the new year"[220] That month, the first 2.7 kilometres (1.7 mi) of track had been laid.[221][222] The first train ran on the Yanchep Rail Extension on 22 December 2023.[223][224] The opening date was revealed in April 2024.[225][226] The extension was officially opened by Premier Roger Cook and Transport Minister Saffioti on 14 July 2024,[217][218][219] with celebrations occurring at Yanchep station.[227] Regular train and bus services commenced the following day. Upon the extension's opening, the Joondalup line was renamed the Yanchep line.[225][228]

Future

edit

There are provisions for a special events station to serve Arena Joondalup.[229][230]

The proposed East Wanneroo line is planned to link the Morley–Ellenbrook line to the Yanchep line near Clarkson station.[231]

Description

edit
 
The Yanchep line viewed from the Glendalough station footbridge

The Yanchep line was built with 1,067 mm (3 ft 6 in) narrow gauge track.[26] Trains are powered by 25 kV 50 Hz AC overhead line equipment[232] powered by three substations at Sutherland Street in West Perth, Edgewater, and Nowergup.[233]: 121–122  The maximum speed is 110 kilometres per hour (68 mph) south of Currambine[26] and 130 kilometres per hour (81 mph) north of Currambine.[233] The line has used automatic train protection since it opened and is signalled to allow for headways as low as three minutes using fixed block signalling.[26] As part of the High Capacity Signalling Project, the signalling system will be replaced by a moving block system using communications-based train control (CBTC), allowing for higher frequencies.[234][235] As of 2021, the CBTC system is planned to be implemented on the Joondalup and Mandurah lines by June 2029.[236]

Route

edit
 
Transperth system map, with the Yanchep line in green

The Yanchep line runs from Perth Underground station in the south to Yanchep station in the north, a distance of 54.5 kilometres (33.9 mi). South of Perth Underground station, the line continues as the Mandurah line,[233] although trains in the 0.6-kilometre (0.4 mi) tunnel south of Perth Underground station to Elizabeth Quay station are considered to be part of the Yanchep line and Mandurah line simultaneously.[237]

 
The Yanchep line south of Warwick station, February 2012

North of Perth Underground station, the tunnel curves westward,[238] passing under the Fremantle line tunnel by 1.2 metres (4 ft),[239] before surfacing parallel to the Fremantle line, 0.6 kilometres (0.4 mi) from Perth Underground station.[233] After 0.3 kilometres (0.2 mi), the Yanchep line dives down to enter a short tunnel and bend north to pass under Roe Street and enter the freeway's median strip, where the line bends west again. The Yanchep line continues along the Mitchell Freeway for 23 kilometres (14 mi) until it reaches Joondalup. There are seven stations along this section: Leederville, Glendalough, Stirling, Warwick, Greenwood, Whitfords, and Edgewater. South of Leederville and north of Whitfords stations are turnback sidings for trains to turn around.[233]

 
The Yanchep line passing under Lakeside Joondalup Shopping Centre, September 2020

At Joondalup, the Yanchep line enters a short tunnel to pass under the southbound Mitchell Freeway carriageway for a 3.3-kilometre (2.1 mi) deviation from the freeway through Joondalup.[233] For this section, the line is in a cutting below ground level, passing under several local roads.[25] North of Joondalup station, the Yanchep line passes under the Lakeside Joondalup Shopping Centre[240][241] and bends west, passing under more roads. The line then bends north and enters a tunnel to pass under the southbound Mitchell Freeway carriageway to reach the freeway's median again.[233]

North of Joondalup, the Yanchep line has two stations in the freeway median: Currambine and Clarkson. North of Clarkson station is the Nowergup depot, which is between the two main lines. After 11 kilometres (6.8 mi), the Yanchep line exits the Mitchell Freeway median for the last time by passing under the northbound carriageway, to enter the residential suburb of Butler. The remaining 16 kilometres (9.9 mi)[233] of the Yanchep line is largely within a cutting below ground level, passing through developing residential areas and bushland.[242] There are four stations: Butler, Alkimos, Eglinton, and Yanchep, where the line terminates. North of Yanchep station are tracks to stow trains.[233]

Stations

edit
 
Perth Underground station
 
Glendalough station
 
Whitfords station
 
Joondalup station

The Yanchep line spans six fare zones.[243] All stations on the Yanchep line are fully accessible except for Leederville, Stirling, and Edgewater stations, which have platform gaps that are too large. Leederville station also has a ramp that is too steep.[244] All platforms are approximately 150 metres (490 ft) long, allowing six-car trains to stop at all stations.

List of stations
Station Distance from Perth[233] Fare zone[237] Location Opened Connections[237][243]
km mi
Elizabeth Quay -0.6 -0.4 1/FTZ Perth 15 October 2007[148] Bus at Elizabeth Quay Bus Station
Services continue on the Mandurah line
Perth Underground 0.0 0.0 1/FTZ Perth 15 October 2007[148] Bus at Perth Busport
Australind, Airport, Armadale, Fremantle, Midland and Thornlie lines
Leederville 2.4 1.5 1 Leederville, West Leederville 20 December 1992[77] Bus
Glendalough 5.6 3.5 1 Glendalough, Osborne Park, Mount Hawthorn 21 February 1993[82] Bus
Stirling 8.8 5.5 2 Innaloo, Osborne Park, Stirling 21 February 1993[82] Bus
Warwick 14.5 9.0 2 Carine, Duncraig, Hamersley, Warwick 28 February 1993[83] Bus
Greenwood 17.7 11.0 2 Duncraig, Greenwood, Kingsley, Padbury 29 January 2005[132]
Whitfords 19.8 12.3 3 Craigie, Kingsley, Padbury, Woodvale 14 February 1993[81] Bus
Edgewater 22.9 14.2 3 Edgewater, Heathridge 20 December 1992[77]
Joondalup 26.2 16.3 3 Joondalup 20 December 1992[77] Bus
Currambine 29.2 18.1 4 Currambine, Joondalup 8 August 1993[97]
Clarkson 33.2 20.6 4 Clarkson 4 October 2004[128] Bus
Butler 40.7 25.3 5 Butler 21 September 2014[163] Bus
Alkimos 43.0 26.7 5 Alkimos 14 July 2024[217] Bus
Eglinton 46.7 29.0 5 Eglinton 14 July 2024[217] Bus
Yanchep 54.5 33.9 6 Yanchep 14 July 2024[217] Bus

Service

edit

Transperth train services are operated by the Public Transport Authority's Transperth Train Operations division.[245] Yanchep line train headways reach as low as five minutes during peak, increasing to fifteen minutes outside peak and on weekends, and half-an-hour to an hour at night. During peak, some services terminate or commence at Whitfords or Clarkson stations. The travel time from Yanchep station to Perth Underground station is 49 minutes. On weeknights, the last train arrives at Yanchep station at 1:06 am and the first train departs at 4:38 am. On Saturday and Sunday nights, the last train arrives at Yanchep station at 3:04 am and the first train departs at 5:05 am on Saturdays and 6:28 am on Sundays.[243]

Before January 2016, express services operated on the Yanchep line during peak periods to manage overcrowding. The introduction of more B-series sets allowed for most trains during peak to be six cars long, which increased capacity and allowed for all services to stop at all stations from 31 January 2016 onwards.[246][247] Before then, some peak trains from Perth to Butler or Clarkson skipped Leederville and Glendalough, and trains from Perth to Whitfords skipped Greenwood.[248] Before June 2009, services terminating at Whitfords operated off-peak as well, making for 7½-minute headways between Perth and Whitfords during the day.[249][250] These services were withdrawn to save money.[251][252][253]

Rolling stock

edit
 
Transperth B-series train south of Butler station
 
Transperth C-series train south of Joondalup station

Transperth B-series trains and C-series trains run on the Yanchep line. The B-series trains are three cars long each, and are typically coupled together to form six car sets. These trains have a maximum speed of 130 kilometres per hour (81 mph), and have two doors on each side per car.[254] The C-series trains are six cars long, have a maximum speed of 130 kilometres per hour (81 mph), and have three doors on each side per car, which help reduce dwell times at stations compared to the B-series, making 18 trains per hour possible.[255] Previously, there were Transperth A-series trains operating on the line. These trains are two cars long, typically coupled together to form four car sets, have a maximum speed of 110 kilometres per hour (68 mph), and have two doors on each side per car. As more B-series trains were delivered, A-series trains were moved from the Joondalup and Mandurah lines to the other lines on the network.[256] The C-series trains entered service on 8 April 2024.[257][258] The B-series trains will be gradually transferred onto the other lines to replace A-series trains.[255][259] By about 2031, all trains on the Yanchep line will be C-series trains.[236]: 79 

In May 2002, the government signed a contract with EDI RailBombardier Transportation for the delivery and maintenance of 31 three car B-series trains, and the construction of the Nowergup depot.[254] In December 2006, the government signed another contract for 15 more three car B-series trains.[260][261] The first of these additional railcars were delivered in 2009, allowing several A-series trains to be moved from the Joondalup and Mandurah lines to other lines on the network, and for frequencies to increase on most lines, including the Joondalup line.[256] In July 2011,[262] the government ordered 15 more three car B-series trains.[263][264] In August 2012, this order was increased by two, to cater for the opening of Aubin Grove station on the Mandurah line. In November 2012, this order was increased by five, bringing the total order to 22 three car trains.[262][265] By the final delivery from that order, all trains operating on the Joondalup and Mandurah lines were B-series trains.[265] In December 2019, the government signed a contract with Alstom for the construction of 41 six car C-series trains.[266] These trains are expected to enter service on 8 April 2024.[257][258]

Most trains on the Yanchep line are stored and cleaned at Nowergup depot. There is also Mandurah depot on the southern end of the Mandurah line, which can store and clean a smaller number of trains. Maintenance occurs at Nowergup depot.[citation needed]

Patronage

edit

In the 1993–94 financial year,[a] the first full year since the Joondalup line opened, the line received 8,221,000 passengers, significantly more than predicted. Patronage on the whole system almost doubled from 13.6 million in the previous financial year to 22.9 million.[267] The Clarkson extension's opening in 2004 resulted in a significant increase in patronage.[268] Upon the Mandurah line's opening in 2007, the Joondalup line was relegated to being Perth's second-most-used line.[269][270] Another significant increase in patronage followed the Mandurah line's opening, reaching a peak of 17,449,891 boardings in 2012–13.[271] Following years of growth, the Joondalup line's patronage decreased in 2013–14, due to shutdowns relating to the Perth City Link and economic factors.[272] The line recorded a small increase in patronage the following financial year with the opening of the extension to Butler,[273] but patronage declined over the following three years due to economic conditions.[274][275][276] In the 2018–19 financial year, patronage was increasing again,[277] but the COVID-19 pandemic's onset in 2020 resulted in a massive decrease,[278] reaching a low of 11,752,572 boardings in 2021–22.[271] By the line's 30th anniversary on 20 December 2022, over 381 million trips had been made on the line.[279] In the latest financial year, 2023–24, there were 16,135,201 boardings on the Yanchep line.[271]

The busiest stations on the Yanchep line as of 2018, excluding Perth Underground and Elizabeth Quay, are Warwick, Joondalup, Stirling, and Whitfords. The least-busiest are Currambine, Edgewater, and Greenwood.[280] Warwick and Joondalup were the fourth and fifth busiest stations in Perth in October 2017, with 5,125 and 4,791 boardings per day respectively.[281]

Yanchep line annual patronage[271]
Year Patronage ±%
2010–11 15,611,836
2011–12 16,700,234 +6.97%
2012–13 17,449,891 +4.49%
2013–14 16,897,361 −3.17%
2014–15 17,105,797 +1.23%
2015–16 16,917,029 −1.10%
2016–17 16,658,559 −1.53%
2017–18 16,477,387 −1.09%
2018–19 16,531,788 +0.33%
2019–20 13,374,710 −19.10%
2020–21 11,885,779 −11.13%
2021–22 11,752,572 −1.12%
2022–23 14,045,991 +19.51%
2023–24 16,135,201 +14.87%

Notes

edit
  1. ^ An Australian financial year is from 1 July to 30 June the following year.

References

edit
  1. ^ Stephenson, Gordon; Hepburn, Alistair (1955). "Plan for the Metropolitan Region, Perth and Fremantle". Government Printing Office. pp. 120, 132. nla.obj-745050840. Retrieved 15 July 2024 – via National Library of Australia.
  2. ^ Kennedy, Peter (21 July 2011). "Lib's public transport opportunity". Business News. Archived from the original on 8 September 2022. Retrieved 15 July 2024.
  3. ^ "Metropolitan Region Scheme Map 13" (PDF). Department of Planning, Lands and Heritage. 1963. Archived from the original (PDF) on 6 June 2021. Retrieved 6 June 2021.
  4. ^ Zimmerman, Josh (22 February 2017). "Grandson of town planner Gordon Stephenson sets record straight". PerthNow. Melville Gazette. Archived from the original on 8 September 2022. Retrieved 9 May 2024.
  5. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 2.
  6. ^ a b c Summary of the Northern Suburbs Rapid Transit Study 1988, p. 4.
  7. ^ Nicholson, Brendan (6 June 1988). "New 'super buses' plan for city link". The West Australian. p. 8.
  8. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 5.
  9. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 6.
  10. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 7.
  11. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 9.
  12. ^ Summary of the Northern Suburbs Rapid Transit Study 1988, p. 11.
  13. ^ Newman, Howard & Vuchic 1988, Front cover, p. 1.
  14. ^ Newman, Howard & Vuchic 1988, p. 1.
  15. ^ Newman, Howard & Vuchic 1988, p. 3.
  16. ^ Newman, Howard & Vuchic 1988, p. 11.
  17. ^ Newman, Howard & Vuchic 1988, p. 12.
  18. ^ Hooker, Peter (14 December 1988). "Land deals may fund line". The West Australian. p. 3.
  19. ^ Westrail (1989). Annual Report 1988–1989. p. 17.
  20. ^ Hooker, Peter (21 January 1989). "Row over Coalition rail plans". The West Australian. p. 6.
  21. ^ "Liberals 'against train'". The West Australian. 23 January 1989. p. 24.
  22. ^ a b Westrail (1990). Annual Report 1989–1990. pp. 29–30.
  23. ^ a b Northern Suburbs Transit System Master Plan 1989b, p. 4.
  24. ^ a b Northern Suburbs Transit System Master Plan 1989b, p. 7.
  25. ^ a b Northern Suburbs Transit System Master Plan 1989b, p. 2.
  26. ^ a b c d e Northern Suburbs Transit System Master Plan 1989b, p. 11.
  27. ^ Northern Suburbs Transit System Master Plan 1989b, p. 19.
  28. ^ Northern Suburbs Transit System Master Plan 1989b, p. 21.
  29. ^ Northern Suburbs Transit System Master Plan 1989b, p. 18; Northern Suburbs Transit System Progress Summary 1991, p. 6.
  30. ^ a b c d e Edmonds, Leigh (1997). The Vital Link: A History of Main Roads Western Australia 1926–1996. University of Western Australia Press. p. 395. ISBN 978-1-876268-06-0.
  31. ^ Northern Suburbs Transit System Master Plan 1989b, p. 6–7.
  32. ^ Northern Suburbs Transit System Master Plan 1989b, p. 25, 28.
  33. ^ Northern Suburbs Transit System Master Plan 1989b, p. 1, 31.
  34. ^ Northern Suburbs Transit System Master Plan 1989b, p. 26.
  35. ^ Goodrick, Russell (December 1989). Westrail News (Video) (13th ed.). Westrail – via State Library of Western Australia.
  36. ^ "Perth–Joondalup Railway Act 1989". Parliamentary Counsel's Office. Department of Justice. Retrieved 4 January 2024.
  37. ^ "Perth–Joondalup Railway Act" (PDF). Parliamentary Counsel's Office. Department of Justice. Retrieved 4 January 2024.
  38. ^ a b c d Lawrence, Carmen (17 December 1990). "Work will start soon to construct a tunnel under Roe Street as part of the $223 million program to provide an electrified rail link to Perth's northern suburbs" (Press release). Government of Western Australia. pp. 45–46 – via Curtin University Library.
  39. ^ Hooker, Peter (18 December 1990). "Work to start on rail tunnel". The West Australian. p. 9.
  40. ^ a b c d Northern Suburbs Transit System Progress Summary 1991, p. 14.
  41. ^ Vorobieff, George; Potter, Robert J (29 October – 1 November 1995). High-Performance Concrete in Rail Structures. Conference on Rail Engineering. pp. 143–144 – via Rail Knowledge Bank.
  42. ^ Hooker, Peter (12 February 1990). "Lake's future at crossroads". The West Australian. p. 8.
    Jenkins, C. F. H. (12 February 1990). "Wetlands the key to the state's survival". The West Australian. p. 63.
  43. ^ Dowding, Simon (6 July 1990). "400 at freeway meeting". The West Australian. p. 22.
  44. ^ Lawrence, Carmen (5 July 1990). "Premier today announced a review of Main Roads Department plans for the development of Mitchell Freeway between Loftus and Vincent Streets" (Press release). Government of Western Australia. pp. 1–2 – via Curtin University Library.
  45. ^ Newman, Peter (July 1990). Review of Mitchell Freeway widening at Leederville and Lake Monger (Report).
  46. ^ Lawrence, Carmen (13 August 1990). "A compromise solution to the widening of the Mitchell Freeway around Lake Monger was announced today by Premier" (Press release). Government of Western Australia. pp. 35–36 – via Curtin University Library.
  47. ^ Bevis, Stephen; Southgate, Tim (14 August 1990). "Lake to escape freeway surgery". The West Australian. p. 5.
  48. ^ Northern Suburbs Transit System Progress Summary 1991, p. 15–16.
  49. ^ Northern Suburbs Transit System Progress Summary 1991, p. 16.
  50. ^ Raykos, C.; Dundas, G. S. (1994). Three Cable-Stayed Footbridges. 2nd Austroads Bridge Conference. Retrieved 10 September 2024 – via Rail Knowledge Bank.
  51. ^ Beggs, Pam (19 June 1992). "Changes to Mitchell Freeway" (Press release). Government of Western Australia. Retrieved 16 July 2024.
  52. ^ Beggs, Pam (15 October 1992). "Fitzgerald St railway crossing to be moved" (Press release). Government of Western Australia. Retrieved 5 January 2024.
  53. ^ Barrass, Tony (16 October 1992). "New railway crossing wins council backing". The West Australian. p. 28.
    Barrass, Tony (21 October 1992). "Withers urges rail lines rethink". The West Australian. p. 19.
  54. ^ Northern Suburbs Transit System Master Plan 1989b, p. 18.
  55. ^ "Bridge Bill through". The West Australian. 8 November 1991. p. 33.
    "Public debate on bus bridge". The West Australian. 30 November 1991. p. 32.
    Hurley, Amanda (4 December 1991). "Beggs a step ahead on bus bridge". The West Australian. p. 21.
  56. ^ "Fitzgerald Street Bus Bridge Act 1991" (PDF). Parliament of Western Australia. Retrieved 17 May 2024.
  57. ^ "Bus bridge still best bet: Beggs". The West Australian. 18 October 1991. p. 28.
  58. ^ Hurley, Amanda; Callander, Diana (5 December 1991). "Bridge plan put on hold". The West Australian. p. 44.
  59. ^ "Bus drivers ban level crossing". The West Australian. 18 March 1993. p. 38.
  60. ^ "Bus bridge set to ease congestion". WAtoday. 31 July 2010. Retrieved 17 May 2024.
  61. ^ Peden, Lauren (7 December 2010). "City bus bridge to open this month". Guardian Express. Community Newspaper Group. p. 6.
  62. ^ Northern Suburbs Transit System Progress Summary 1991, p. 9.
  63. ^ Beggs, Pam (22 April 1992). "Work underway on masts for northern suburban transit system" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  64. ^ "Design sits poles apart in top looks". The Sunday Times. 21 March 1993. p. 50.
  65. ^ Hooker, Peter (19 December 1992). "Poles before the track was a master stroke". The West Australian. p. 15.
  66. ^ "Gangs get new railway on track". The West Australian. 14 July 1992. p. 7.
  67. ^ McGinty, Jim (13 July 1992). "Progress on Northern Suburbs Rapid Transit System (A/Min)" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  68. ^ Hooker, Peter (30 October 1992). "Ban puts rail work on hold". The West Australian. p. 14.
  69. ^ Hooker, Peter (31 October 1992). "Hearing sought to end rail dispute". The West Australian. p. 39.
  70. ^ a b Beggs, Pam (10 November 1992). "Guard rail barrier between freeway and northern subs railway line" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  71. ^ Northern Suburbs Transit System Master Plan 1989b, p. 17.
  72. ^ Lawrence, Carmen (31 October 1992). "Power switched on for northern suburbs railway" (Press release). Government of Western Australia. Retrieved 16 July 2024.
  73. ^ Westrail (31 October 1992). "The Power's On From November 1 (advertisement)". The West Australian. p. 41.
  74. ^ "Northern line a track star". The Sunday Times. 1 November 1992. p. 8.
  75. ^ Beggs, Pam (20 November 1992). "Trial of first northern suburbs electric train a success" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  76. ^ Russell, Mark (13 December 1992). "Glamor rail service won't be on track". The Sunday Times. p. 5.
  77. ^ a b c d Lawrence, Carmen (20 December 1992). "Opening of Perth–Joondalup rail link" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  78. ^ Lawrence, Carmen (21 December 1992). "Northern suburbs railway an instant hit" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  79. ^ Hooker, Peter (21 December 1992). "Transperth tips rail boom". The West Australian. p. 4.
  80. ^ "Back on track". The Canberra Times. 21 December 1992. p. 12. Retrieved 30 July 2024 – via National Library of Australia.
  81. ^ a b "Transperth Information (advertisement)". The West Australian. 11 February 1993. p. 4.
  82. ^ a b c "Transperth Information (advertisement)". The West Australian. 18 February 1993. p. 4.
  83. ^ a b "Transperth Information (advertisement)". The West Australian. 25 February 1993. p. 4.
  84. ^ Beggs, Pam (28 January 1993). "Bus/train interchanges on northern subs railway to open February" (Press release). Government of Western Australia. Retrieved 6 November 2024.
  85. ^ "Training delays new line". The West Australian. 25 February 1993. p. 8.
  86. ^ a b Charlton, Eric (21 March 1993). "Inspection of Joondalup train-bus interchange" (Press release). Government of Western Australia. Retrieved 4 January 2024.
  87. ^ Russell, Mark (21 March 1993). "History is right on track". The Sunday Times. p. 9.
  88. ^ a b c d Hooker, Peter (22 March 1993). "New rail line faces first big test". The West Australian. p. 22.
  89. ^ Hooker, Peter (20 March 1993). "Busiest buses axed to make way for trains". The West Australian. p. 25.
  90. ^ MetroBus (1998). Annual Report 1997–1998. p. 64.
  91. ^ Blanksby, Alison (16 March 1993). "Bus changes hit students". The West Australian. p. 40.
  92. ^ Blanksby, Alison (17 March 1993). "Perth's new trains bring bad news". The West Australian. p. 9.
  93. ^ "Feeder service set for trains". The Sunday Times. 21 March 1993. p. 51.
  94. ^ Hooker, Peter (24 March 1993). "More delays as snarls hit new railway". The West Australian. p. 13.
  95. ^ Quekett, Malcolm; Hooker, Peter; Southgate, Tim (27 March 1993). "Fare rises certain as rail debt climbs". The West Australian. p. 1.
  96. ^ Charlton, Eric (17 July 1993). "Opening of Currambine railway station next month" (Press release). Government of Western Australia. Retrieved 5 January 2024.
  97. ^ a b Charlton, Eric (8 August 1993). "New warning devices for Fastrak trains" (Press release). Government of Western Australia. Retrieved 5 January 2024.
  98. ^ Charlton, Eric (18 March 1995). "Opposition promise to 'fast track' transport systems pre-empted by Govt" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  99. ^ Court, Richard (20 November 1996). "Extension of northern suburbs transit system to Neerabup Drive, Clarkson" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  100. ^ a b Mallabone, Mark (9 June 2000). "Cabinet lacks will to expand rail: ALP". The West Australian. p. 32.
  101. ^ Charlton, Eric (5 December 1997). "Go-ahead for new railway station at Hepburn Avenue, Greenwood" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  102. ^ Criddle, Murray (26 November 1999). "Way cleared for construction of SW Metropolitan Railway to Mandurah" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  103. ^ a b Robb, Trevor (22 June 2000). "Station to move in rail extension". The West Australian. p. 9.
  104. ^ a b Criddle, Murray (21 June 2000). "Minister says the push is on for earlier Clarkson rail link" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  105. ^ a b Currambine to Butler Extension Master Plan 2000, p. 10.
  106. ^ Currambine to Butler Extension Master Plan 2000, p. 1, 9.
  107. ^ Currambine to Butler Extension Master Plan 2000, p. 74.
  108. ^ Currambine to Butler Extension Master Plan 2000, p. 89.
  109. ^ Court, Richard (18 October 2000). "Green light for rail extension to Clarkson: Premier" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  110. ^ a b c d "OnTrack: March 2003" (PDF). New MetroRail. p. 6. Archived from the original (PDF) on 29 August 2007.
  111. ^ Callaghan, Ruth (1 May 2001). "Trains Revamp – New lines, rail carriages to cost $1.5b". The West Australian. p. 1.
  112. ^ MacTiernan, Alannah (2 May 2001). "Minister to commence extension to the Northern Suburbs Transit System" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  113. ^ "Bulk Earthworks". New MetroRail. Archived from the original on 29 August 2007.
  114. ^ MacTiernan, Alannah (11 July 2001). "Contract Awarded for Burns Beach Road Rail Bridges" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  115. ^ "Bridges". New MetroRail. Archived from the original on 29 August 2007.
  116. ^ "Railway and Track Infrastructure". New MetroRail. Archived from the original on 28 August 2007.
  117. ^ MacTiernan, Alannah (13 November 2002). "$8.7million contract awarded for construction of Clarkson Station" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  118. ^ MacTiernan, Alannah (12 February 2004). "Work to start on Greenwood station" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  119. ^ "Greenwood Station Construction". New MetroRail. Archived from the original on 29 August 2007.
  120. ^ "What's going on with Greenwood Station?" (PDF). New MetroRail. April 2004. Archived from the original (PDF) on 15 June 2005.
  121. ^ "OnTrack: Issue 5" (PDF). New MetroRail. April 2004. p. 4. Archived from the original (PDF) on 29 August 2007.
  122. ^ "OnTrack: Issue 3" (PDF). New MetroRail. October 2003. p. 8. Archived from the original (PDF) on 29 August 2007.
  123. ^ "OnTrack: Issue 5" (PDF). New MetroRail. April 2004. p. 4. Archived from the original (PDF) on 29 August 2007.
  124. ^ "OnTrack: Issue 6" (PDF). New MetroRail. July 2004. p. 5. Archived from the original (PDF) on 29 August 2007.
  125. ^ MacTiernan, Alannah; Gallop, Geoff (13 June 2004). "First railcars arrive at new Nowergup train depot" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  126. ^ "Currambine". New MetroRail. Archived from the original on 8 February 2006.
  127. ^ MacTiernan, Alannah (30 September 2004). "Free rail travel to celebrate network expansion" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  128. ^ a b MacTiernan, Alannah; Gallop, Geoff (4 October 2004). "Gallop Government delivers northern rail extension on time and budget" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  129. ^ MacTiernan, Alannah (14 December 2006). "Work begins on Mitchell Freeway extension" (Press release). Government of Western Australia. Retrieved 15 September 2024.
  130. ^ "Mitchell Freeway Extension – Hodges Drive to Burns Beach Road – Concept Plan" (PDF). Main Roads Western Australia. Archived from the original (PDF) on 28 July 2008.
  131. ^ Thomas, Beatrice (24 October 2008). "Extensions to ease congestion on roads to the north". The West Australian. p. 13.
  132. ^ a b Gallop, Geoff (29 January 2005). "Services commence from Greenwood Railway Station" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  133. ^ Perth Urban Rail Development Project – Supplementary Master Plan 2002, p. 1–2.
  134. ^ Northern Suburbs Transit System Master Plan 1989b, p. 27.
  135. ^ MacTiernan, Alannah; Gallop, Geoff (16 July 2001). "Gallop Government unveils vision for faster rail link to Mandurah" (Press release). Government of Western Australia. Retrieved 19 October 2024.
  136. ^ Robb, Trevor (17 July 2001). "Rail Switch – New train link across city foreshore". The West Australian. p. 1.
  137. ^ MacTiernan, Alannah; Gallop, Geoff (13 August 2002). "Master Plan shows new line a winner" (Press release). Government of Western Australia. Retrieved 19 October 2024.
  138. ^ Robb, Trevor (14 August 2002). "ALP claims win on freeway line". The West Australian. p. 4.
  139. ^ Perth Urban Rail Development Project – Supplementary Master Plan 2002, p. 140.
  140. ^ Longhurst 2008, p. 309.
  141. ^ MacTiernan, Alannah (14 February 2004). "City section of New MetroRail Project signed" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  142. ^ "Transperth passengers will benefit from the new Thornlie Station (advertisement)". The West Australian. 6 August 2005.
  143. ^ "Table Talk" (PDF). Australian Timetable Association. September 2005. p. 5. ISSN 1038-3697.
  144. ^ MacTiernan, Alannah (8 September 2007). "City tunnel project completion announced" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  145. ^ a b Longhurst 2008, p. XVII.
  146. ^ "Your Guide to the Shutdown". Transperth. Archived from the original on 7 October 2007.
  147. ^ MacTiernan, Alannah (14 October 2007). "Perth's new underground railway stations ready for action" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  148. ^ a b c "Perth CBD's first underground train station in operation". ABC News. 15 October 2007. Retrieved 18 May 2024.
  149. ^ Carpenter, Alan; MacTiernan, Alannah (23 December 2007). "All aboard as the new Perth-to-Mandurah Railway begins" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  150. ^ Quinn, Russell (8 December 2010). "RJ Vincent wins $6m Joondalup rail contract". PerthNow. Retrieved 13 September 2024.
  151. ^ O'Brien, Simon (8 December 2010). "Government contract kicks off Joondalup rail line extension" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  152. ^ Buswell, Troy (20 May 2011). "Bridges contract awarded for Butler extension" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  153. ^ "State awards rail extension deal". Business News. 20 May 2011. Retrieved 13 September 2024.
  154. ^ Buswell, Troy (8 June 2012). "Work to start on Butler station" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  155. ^ "Butler train station works to begin". The West Australian. 8 June 2012. Retrieved 13 September 2024.
  156. ^ a b "Our history". Public Transport Authority. Retrieved 17 May 2024.
  157. ^ Buswell, Troy (19 October 2012). "Butler Station moves step closer as track laid" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  158. ^ Orr, Aleisha (13 November 2012). "Work starts on taking train line further north". WAtoday. Retrieved 13 September 2024.
  159. ^ Buswell, Troy (13 November 2012). "Another big step for Butler rail project" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  160. ^ Buswell, Troy (23 October 2013). "Butler extension full steam ahead" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  161. ^ Nalder, Dean (17 April 2014). "Butler Station construction complete" (Press release). Government of Western Australia. Retrieved 13 September 2024.
  162. ^ Nalder, Dean (30 August 2014). "Trains start using new Butler extension" (Press release). Government of Western Australia. Retrieved 18 May 2024.
  163. ^ a b "Barnett opens rail extension as first train leaves Butler station". WAtoday. 21 September 2014. Retrieved 6 January 2024.
  164. ^ "Butler train station and rail extension opens". ABC News. 21 September 2014. Retrieved 6 January 2024.
  165. ^ "Extended northern railway: Butler train station open today". PerthNow. 21 September 2014. Retrieved 6 January 2024.
  166. ^ Jarvis, Lucy (23 September 2014). "Residents rattled by rail". PerthNow. North Coast Times. Retrieved 13 September 2024.
  167. ^ Jarvis, Lucy (23 September 2014). "Government to monitor noise complaints". PerthNow. North Coast Times. Retrieved 13 September 2024.
  168. ^ Wearne, Phoebe (13 October 2014). "Train vibrations send residents loco". The West Australian. Retrieved 13 September 2024.
  169. ^ Wearne, Phoebe; Acott, Kent (13 December 2014). "No housing near station". The West Australian. p. 40.
  170. ^ Caporn, Dylan (8 February 2017). "Trains to Yanchep by 2021 with $386m Labor plan". The West Australian. Retrieved 24 March 2024.
  171. ^ McGowan, Mark; Saffioti, Rita; Wyatt, Ben (7 September 2017). "METRONET well underway with major funding injection" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  172. ^ "Western Australia budget backs rail growth". Railway Gazette International. 13 September 2017. Retrieved 24 March 2024.
  173. ^ Caporn, Dylan (8 September 2017). "Budget 2017: Metronet construction to start in 2019". The West Australian. Retrieved 24 March 2024.
  174. ^ McGowan, Mark; Saffioti, Rita (21 August 2017). "METRONET progress on track" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  175. ^ "Project Evaluation Summary METRONET: Yanchep Rail Extension" (PDF). Infrastructure Australia. 18 November 2018. Retrieved 24 March 2024.
  176. ^ Saffioti, Rita (16 November 2018). "METRONET projects get Infrastructure Australia tick of approval" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  177. ^ Wright, Shane (16 November 2018). "National infrastructure tsar gives green light to Perth Metronet plan". The West Australian. Retrieved 24 March 2024.
  178. ^ "Federal Funding Secured". Metronet. 15 November 2018. Retrieved 24 March 2024.
  179. ^ Jarvis, Lucy (16 November 2018). "Yanchep: Infrastructure Australia approves $700m federal contribution to Metronet rail projects". PerthNow. North Coast Times. Retrieved 24 March 2024.
  180. ^ Saffioti, Rita (10 May 2018). "METRONET Bill to enshrine rail commitment in legislation" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  181. ^ "Metronet legislation to pave way for construction of Yanchep rail extension". PerthNow. North Coast Times. 1 June 2018. Retrieved 24 March 2024.
  182. ^ "METRONET Rail Enabling Bill Passed". Metronet. 16 November 2018. Retrieved 10 September 2023.
  183. ^ McGowan, Mark; Saffioti, Rita (3 July 2018). "Two METRONET projects on track to begin construction next year" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  184. ^ Saffioti, Rita (9 September 2018). "Joint media statement – Wanted: Contractor to build Perth's new METRONET rail lines" (Press release). Government of Western Australia. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  185. ^ Gameng, Monica (10 September 2018). "Request for Proposal released for two major METRONET projects WA". Felix Vendor Marketplace. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  186. ^ Milne, Peter (6 April 2019). "METROconnex, NEWest Alliance consortiums vie for $1.1b Metronet's Thornlie–Cockburn and Yanchep rail work". The West Australian. Archived from the original on 6 April 2019. Retrieved 19 July 2023.
  187. ^ Beyer, Mark (8 April 2019). "Two bidders for rail projects". Business News. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  188. ^ Saffioti, Rita (6 April 2019). "METRONET's Thornlie–Cockburn Link and Yanchep Rail Extension tender reaches next phase" (Press release). Government of Western Australia. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  189. ^ Zimmerman, Josh (24 November 2019). "NEWest Alliance appointed to deliver Yanchep rail extension and Thornlie–Cockburn link". The West Australian. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  190. ^ "NEWest Alliance chosen for Yanchep Rail Extension". Railway Technology. 26 November 2019. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  191. ^ Gameng, Monica (24 November 2019). "CPB-Downer JV selected as preferred contractor for METRONET projects". Felix Vendor Marketplace. Retrieved 24 March 2024.
  192. ^ Gubana, Benjamin (17 December 2019). "Metronet Thornlie–Cockburn link between Armadale and Mandurah train lines delayed to 2023 after $200m blowout". ABC News. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  193. ^ Smith, Ben (18 December 2019). "Major Metronet project over budget and delayed". PerthNow. Cockburn Gazette. Archived from the original on 19 July 2023. Retrieved 19 July 2023.
  194. ^ "WA Government signs contracts with NEWest Alliance". Railway Technology. 17 December 2019. Archived from the original on 14 May 2023. Retrieved 19 July 2023.
  195. ^ a b McGowan, Mark; Saffioti, Rita (24 November 2019). "Joint media statement – Work starts on METRONET Yanchep Rail Extension unlocking thousands of local jobs" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  196. ^ "Eight months of milestones for Yanchep Rail Extension". Metronet. 17 December 2020. Retrieved 24 March 2024.
  197. ^ "Yanchep Rail Extension taking shape". Metronet. 21 May 2021. Retrieved 24 March 2024.
  198. ^ Jarvis, Lucy (17 June 2021). "Stalled: Yanchep Rail Extension work veering off track". PerthNow. Wanneroo Times. Retrieved 24 March 2024.
  199. ^ Jarvis, Lucy (22 July 2021). "Yanchep rail timetable shift flagged amid skills shortage". PerthNow. Wanneroo Times. Retrieved 24 March 2024.
  200. ^ McGowan, Mark (9 September 2021). "Projects adjusted to deliver a strong economy for the long term" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  201. ^ de Kruijff, Peter (9 September 2021). "State projects delayed to ease pressure on 'hot' WA construction market". WAtoday. Retrieved 24 March 2024.
  202. ^ Clarke, Jenna (9 September 2021). "Metronet projects, including Thornlie–Cockburn link and Yanchep train line, will be DELAYED by 12-months". PerthNow. Retrieved 24 March 2024.
  203. ^ Brown, Tyler (10 September 2021). "Plans for principal shared path from Butler to Yanchep as part of rail extension scrapped to save money". PerthNow. Retrieved 24 March 2024.
  204. ^ Brown, Tyler (25 November 2021). "Wanneroo Council calls for cycle path to return as part of new Alkimos train station". PerthNow. Retrieved 24 March 2024.
  205. ^ "Concerns about Yanchep rail cost cutting as cycle path deleted". Yanchep News Online. 8 September 2021. Retrieved 24 March 2024.
  206. ^ Brown, Tyler (16 December 2021). "Metronet: Yanchep rail extension hits milestone with work underway at Alkimos, Eglinton and Yanchep stations". PerthNow. Retrieved 24 March 2024.
  207. ^ "All stations go for Perth's northern corridor". Metronet. 16 December 2021. Retrieved 24 March 2024.
  208. ^ Gameng, Monica (3 April 2022). "2022–23 Federal Budget: $2.1bn funding for WA infrastructure projects". Felix Vendor Marketplace. Retrieved 24 March 2024.
  209. ^ "CEO Newsletter – Federal Budget Update 2022". Infrastructure Australia. 31 March 2022. Retrieved 24 March 2024.
  210. ^ de Kruijff, Peter (12 May 2022). "Record $33.9b for infrastructure projects as Premier plays down construction costs". WAtoday. Retrieved 24 March 2024.
  211. ^ Zimmerman, Josh (23 May 2023). "Budget Estimates: Premier Mark McGowan refuses to rule out more blowouts to Metronet costs". The West Australian. Retrieved 24 March 2024.
  212. ^ Hastie, Hamish (11 May 2023). "McGowan hammers cost-of-living as WA to hit $4.2b budget surplus". WAtoday. Retrieved 24 March 2024.
  213. ^ "2023–24 Budget: Economic and Fiscal Outlook" (PDF). Parliament of Western Australia. May 2023. p. 186. ISSN 1448-2630. Retrieved 4 October 2023.
  214. ^ Zimmerman, Josh (9 May 2024). "WA State Budget 2024: Treasurer Rita Saffioti announces WA's sixth surplus in a row, Metronet blowout". The West Australian. Retrieved 9 May 2024.
  215. ^ "WA Budget live: Unpacking what's in Roger Cook and Rita Saffioti's budget for 2024–25". ABC News. 9 May 2024. Retrieved 9 May 2024.
  216. ^ "2024–25 Budget Statements. Budget Paper No. 2 – Volume 2" (PDF). Our Budget. p. 619. Retrieved 9 May 2024.
  217. ^ a b c d e "Yanchep rail extension officially opened after significant delays and cost blow outs". The West Australian. 14 July 2024. Retrieved 15 July 2024.
  218. ^ a b Burmas, Grace; Png, Kenith (14 July 2024). "WA government hails Yanchep train extension 'spectacular project' despite cost, time blow-outs". ABC News. Retrieved 15 July 2024.
  219. ^ a b Condon, Alex (14 July 2024). "WA Labor, Liberals trade barbs over 'MetroDEBT' as Yanchep extension opens". WAtoday. Retrieved 15 July 2024.
  220. ^ "State Budget delivers continued METRONET investment". Metronet. 11 May 2023. Retrieved 24 March 2024.
  221. ^ McGowan, Mark; Saffioti, Rita (16 May 2023). "Joint media statement – First track laid for METRONET Yanchep Rail Extension" (Press release). Government of Western Australia. Retrieved 24 March 2024.
  222. ^ Tan, Christopher (21 May 2023). "Metronet: Yanchep rail extension project crawls ahead after first 3km of track laid". The West Australian. Retrieved 24 March 2024.
  223. ^ Dietsch, Jake (22 December 2023). "First test run for $1.08b Metronet Yanchep rail extension marks major milestone after years of delays". The West Australian. Retrieved 24 March 2024.
  224. ^ Vieira, Isabel (22 December 2023). "Test train hits tracks on Yanchep extension". Business News. Retrieved 24 March 2024.
  225. ^ a b Cook, Roger; Saffioti, Rita (23 April 2024). "Joint Media Statement – Date Announced For First Train Services On Metronet Yanchep Rail Extension" (Press release). Government of Western Australia. Retrieved 15 July 2024.
  226. ^ Dietsch, Jake (23 April 2024). "Metronet project: July opening date announced from Butler to Yanchep railway extension". The West Australian. Retrieved 23 April 2024.
  227. ^ "Next stop... YANCHEP!". Metronet. 5 June 2024. Retrieved 15 July 2024.
  228. ^ Lopez, Erick; Dietsch, Jake (27 April 2024). "Mayor questions name change on train line from Joondalup to Yanchep as opening date is revealed". PerthNow. Retrieved 15 July 2024.
  229. ^ Moore, Norman; Kierath, Graham (14 November 1996). "WA Australian Sports Centre Trust to take over ownership of the Arena Joondalup" (Press release). Government of Western Australia. Retrieved 6 January 2024.
  230. ^ "Structure Plan For Arena Joondalup Precinct" (PDF). City of Joondalup. p. 12. Retrieved 6 January 2024.
  231. ^ "Perth and Peel@3.5million: The Transport Network" (PDF). Department of Transport. March 2018. pp. 12, 14. Archived (PDF) from the original on 15 March 2023. Retrieved 15 July 2024.
  232. ^ Northern Suburbs Transit System Master Plan 1989b, p. 14.
  233. ^ a b c d e f g h i j "Manual – Rail Access" (PDF). Public Transport Authority. 13 September 2024. p. 10–27. Retrieved 5 October 2024.
  234. ^ "High Capacity Signalling Fact Sheet" (PDF). Metronet. p. 2. Archived (PDF) from the original on 30 March 2023. Retrieved 18 July 2023.
  235. ^ "METRONET: High Capacity Signalling". Infrastructure Australia. Archived from the original on 5 July 2023. Retrieved 18 July 2023.
  236. ^ a b "HCS SWTR Book 1 – Scope of Works DRAFT 01-09-21_Redacted". Tenders WA. 30 September 2021. pp. 77, 79. Archived from the original on 20 January 2022. Retrieved 20 January 2022. Click Download Now, then Download for Information Only. Make sure HCS SWTR Book 1 – Scope of Works DRAFT 01-09-21_Redacted.pdf is selected, then click Download Documents.
  237. ^ a b c "Transperth Zone Map" (PDF). Transperth. Retrieved 5 October 2024.
  238. ^ "City Project Plan Map". New MetroRail. August 2002. Archived from the original on 29 August 2007.
  239. ^ Acott, Kent (21 June 2013). "Secrets of high-tech tunnel". The West Australian. Retrieved 5 October 2024.
  240. ^ "Proposed extensions to Lakeside Joondalup Shopping Centre fronting Grand Boulevard and Boas Avenue on part of lot 504 Joondalup Drive – [08431]" (PDF). City of Joondalup. 2005. pp. 2–3. Retrieved 5 October 2024.
  241. ^ Pearce, Yonnene (7 June 2000). "Cinemas had to screen out trains". The West Australian. p. 56.
  242. ^ Yanchep Rail Extension Project Definition Plan 2018, p. 20.
  243. ^ a b c "Yanchep Line Train Timetable" (PDF). Transperth. 15 July 2024. Retrieved 15 July 2024.
  244. ^ "Stations & Maps". Transperth. Retrieved 12 July 2024.
  245. ^ "Transperth". Public Transport Authority. Retrieved 10 November 2024.
  246. ^ Acott, Kent (9 January 2016). "Bus, rail and ferry services to change". The West Australian. Retrieved 12 November 2024.
  247. ^ "Bus, Train and Ferry – Major Timetable Changes". Transperth. 31 January 2016. Archived from the original on 3 February 2016.
  248. ^ "Joondalup Line Train Timetable" (PDF). Transperth. 21 September 2014. Archived from the original (PDF) on 12 January 2015.
  249. ^ "Joondalup Line Timetable" (PDF). Transperth. 17 August 2008. Archived from the original (PDF) on 27 July 2008.
  250. ^ "Joondalup Line Timetable" (PDF). Transperth. 1 March 2009. Archived from the original (PDF) on 12 June 2009.
  251. ^ O'Brien, Simon (4 June 2009). "Timetables change as train capacity boosted" (Press release). Government of Western Australia. Retrieved 12 November 2024.
  252. ^ Kerr, Peter (5 June 2009). "Shuttle train service cuts will save $2m". The West Australian. p. 6.
  253. ^ Thomson, Chris (1 July 2009). "Cockburn to Whitfords trains slashed". WAtoday. Archived from the original on 4 July 2009.
  254. ^ a b "Railcar contract seals railway commitment". Government of Western Australia. 12 May 2002. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  255. ^ a b "WA Railcar Program Project Definition Plan" (PDF). Metronet. December 2018. Archived (PDF) from the original on 18 January 2022. Retrieved 18 January 2022.
  256. ^ a b "Timetables change as train capacity boosted". Government of Western Australia. 4 June 2009. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  257. ^ a b Zimmerman, Josh (19 March 2024). "C-series Metronet train due to enter service next month". The West Australian. Retrieved 19 March 2024.
  258. ^ a b Saffioti, Rita (19 March 2024). "All aboard! First METRONET C-series train ready for passengers" (Press release). Government of Western Australia. Retrieved 19 March 2024.
  259. ^ "WA Railcar Program". Metronet. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  260. ^ "More trains for Perth's transport system". Government of Western Australia. 19 September 2006. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  261. ^ "WA Government secures new railcars". Government of Western Australia. 22 September 2006. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  262. ^ a b Carter, Mark (6 November 2013). "Perth grapples with growth and funding challenges". International Railway Journal. Archived from the original on 28 September 2020. Retrieved 18 January 2022.
  263. ^ "State Budget 2011–12: Supporting our Community; Building the State (Transport) – Massive injection to build WA's road, rail and bus networks". Government of Western Australia. 19 May 2011. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  264. ^ "State Budget 2011–12: Building the State – Funding for new railcars for Perth's growing transport system". Government of Western Australia. 23 May 2011. Archived from the original on 18 January 2022. Retrieved 18 January 2022.
  265. ^ a b "More rail cars for Perth transport system". Government of Western Australia. 4 November 2012. Archived from the original on 19 January 2022. Retrieved 18 January 2022.
  266. ^ "Historic contract signed for WA-made METRONET railcars". Government of Western Australia. 10 December 2019. Archived from the original on 20 January 2022. Retrieved 20 January 2022.
  267. ^ Westrail (1994). Annual Report 1993–1994. p. 13.
  268. ^ "Annual Report 2004–05" (PDF). Public Transport Authority. 2005. p. 10. Retrieved 12 November 2024.
  269. ^ "Annual Report 2007–08" (PDF). Public Transport Authority. 2008. p. 5. Retrieved 12 November 2024.
  270. ^ Paül, Valerià; Biermann, Sharon (June 2014). "PATREC Perspectives: Perth Public Transport Patronage: "Off The Rails" or "Back On Track"?" (PDF). Planning and Transport Research Centre. p. 2. Retrieved 12 November 2024.
  271. ^ a b c d "Transport performance". Public Transport Authority. Retrieved 29 August 2024.
  272. ^ "Annual Report 2013–14" (PDF). Public Transport Authority. 2014. pp. 5, 44. Retrieved 12 November 2024.
  273. ^ "Annual Report 2014–15" (PDF). Public Transport Authority. 2015. p. 48. Retrieved 12 November 2024.
  274. ^ "Annual Report 2015–16" (PDF). Public Transport Authority. 2016. p. 20. Retrieved 12 November 2024.
  275. ^ "Annual Report 2016–17" (PDF). Public Transport Authority. 2017. p. 21. Retrieved 12 November 2024.
  276. ^ "Annual Report 2017–18" (PDF). Public Transport Authority. 2018. p. 10. Retrieved 12 November 2024.
  277. ^ "Annual Report 2018–19" (PDF). Public Transport Authority. 2019. p. 10. Retrieved 12 November 2024.
  278. ^ "Annual Report 2019–20" (PDF). Public Transport Authority. 2020. p. 17. Retrieved 12 November 2024.
  279. ^ Saffioti, Rita (20 December 2022). "Joondalup Line celebrates 30 years of train services" (Press release). Government of Western Australia. Retrieved 5 January 2024.
  280. ^ Yanchep Rail Extension Project Definition Plan 2018, p. 18.
  281. ^ Perpitch, Nicolas (13 March 2018). "Welcome to Seaforth — the loneliest train station on the Perth rail network". ABC News. Retrieved 12 November 2024.

Sources

edit

Further reading

edit
  • Dowling, Neil (21 March 1993). "Joondalup Railway". The Sunday Times. pp. 48–53.
  • Fastrak North (Video). Transperth. 1993 – via State Library of Western Australia.

Conferences

edit

Journal articles

edit
  • Alexander, Ian; Houghton, Stewart (1994). "New Investment in Urban Public Transport: 1: The Northern Suburbs railway in Perth". Australian Planner. 32 (1): 7–11. doi:10.1080/07293682.1994.9657648.
  • Alexander, Ian; Houghton, Stewart (1995). "New Investment in Urban Public Transport II: Evaluation of the Northern Suburbs railway in Perth". Australian Planner. 32 (2): 82–87. doi:10.1080/07293682.1995.9657666.