Line 12 (Shanghai Metro)

(Redirected from Line 12, Shanghai Metro)

Line 12 is an east–west line of the Shanghai Metro network. It runs from Jinhai Road in Pudong to Qixin Road in Minhang District. The first section from Tiantong Road to Jinhai Road opened on 29 December 2013,[2] and additional stations up to Qufu Road were in operation by 10 May 2014.[3] The remaining stations opened on 19 December 2015.[4][5] Since the opening of the extension in December 2015, Line 12 has the most interchanges with other metro lines in the Shanghai Metro.[6] The line is colored forest green on system maps.

Line 12
Jinhai Road station line 12 platform
Overview
Other name(s)M2 (planned name);
Minpu line
Native name上海地铁12号线
StatusOperational
OwnerShanghai Rail Transit Line 12 Development Co., Ltd.
LocalePudong; Yangpu, Hongkou, Jing'an, Huangpu, Xuhui, and Minhang districts, Shanghai, China
Termini
Stations32
Service
TypeUrban rail transit in China Rapid transit
SystemShanghai Metro Shanghai Metro
ServicesMainline: Qixin RoadJinhai Road; Partial Mainline: Hongmei Road ↔ Jufeng Road
Operator(s)Shanghai No. 4 Metro Operation Co. Ltd.
Depot(s)Zhongchun Road parking lot;
Jinqiao parking lot
Rolling stock75 Class A 6-car trains
Daily ridership826,000 (2019 Peak)[1]
History
Commenced30 December 2008; 15 years ago (2008-12-30)
Opened29 December 2013; 10 years ago (2013-12-29)
Last extension19 December 2015; 8 years ago (2015-12-19)
Technical
Line length40.4 km (25.10 mi)
Number of tracks2
CharacterUnderground
Track gauge1,435 mm (4 ft 8+12 in)
ElectrificationOverhead lines (1500 volts)
Operating speed80 km/h (50 mph)
Average speed: 28.5 km/h (18 mph)
SignallingALSTOM Urbalis CBTC
Route map
To scale geographic map:

History

edit
Shanghai metro line 12 opening history
Segment Commencement Opened Length Station(s) Name Investment
Tiantong Road — Jinhai Road 30 Dec 2008 29 Dec 2013 17.5 km (10.87 mi) 15 Initial phase (1st section) ¥23.399 billion
Qufu Road — Tiantong Road 30 Dec 2008 10 May 2014 1.1 km (0.68 mi) 1 Initial phase (1st section)
Qixin Road — Qufu Road 30 Dec 2008 19 Dec 2015 21.8 km (13.55 mi) 16 Initial phase (2nd section)
Dongjing — Qixin Road 16 Dec 2022 exp 2027 17.2 km (10.69 mi) 6 Western extension

Construction accident

edit

On 31 December 2012, the ground maintenance warehouse of Jinqiao Parking Lot collapsed during the construction process, resulting in 5 deaths and 18 injuries.[7]

Stations

edit

Service routes

edit
Shanghai metro line 12 service routes
Routes Station name Connections Distance Location Open-
ing
Plat-
form[8]
M P English Chinese km min
Dongjing 洞泾  9  0.00 0.00 Songjiang West extension under construction
Liuwu Highway 刘五公路 1.91 1.91
Husong Highway 沪松公路 1.96 3.87
Hi-tech Park 科技园 5.36 9.23
Changxi Road 场西路 1.44 10.67
Changdong Road 场东路 1.78 12.45
Qixin Road 七莘路 4.73 17.18 0 Minhang 19 Dec
2015[9]
Underground Island
Hongxin Road 虹莘路 1.73 18.91 4
Gudai Road 顾戴路 1.23 20.14 6
Donglan Road 东兰路 1.87 22.01 9
Hongmei Road 虹梅路 0.69 22.70 11
Hongcao Road 虹漕路 1.42 24.12 14 Xuhui
Guilin Park 桂林公园  15  0.83 24.95 16
Caobao Road 漕宝路  1  1.55 26.50 19
Longcao Road 龙漕路  3  0.84 27.34 21
Longhua 龙华  11  1.04 28.38 24
Middle Longhua Road 龙华中路  7  1.35 29.73 26 Underground Side
Damuqiao Road 大木桥路  4  1.57 31.30 29 Underground Island
Jiashan Road 嘉善路  9  1.01 32.31 31
South Shaanxi Road 陕西南路  1   10  1.49 33.80 34 Huangpu
West Nanjing Road 南京西路  2   13 [i] 1.40 35.20 37 Jing'an
Hanzhong Road 汉中路  1   13  1.48 36.68 40
Qufu Road 曲阜路  8  1.24 37.92 43 10 May
2014[10]
Tiantong Road 天潼路  10  1.04 38.96 45 29 Dec
2013[11]
Underground Side
International Cruise Terminal 国际客运中心 1.69 40.65 49 Hongkou
Tilanqiao 提篮桥 0.98 41.63 51 Underground Island
Dalian Road 大连路  4  0.79 42.42 53 Yangpu
Jiangpu Park 江浦公园  18  1.29 43.71 55
Ningguo Road 宁国路 0.91 44.62 58
Longchang Road 隆昌路 1.42 46.04 61 Underground Side
Aiguo Road 爱国路 0.92 46.96 63 Underground Island
Fuxing Island 复兴岛 0.82 47.78 65
Donglu Road 东陆路 1.70 49.48 68 Pudong
Jufeng Road 巨峰路  6  1.09 50.57 71
North Yanggao Road 杨高北路 1.27 51.84 74
Jinjing Road 金京路 1.16 53.00 76
Shenjiang Road 申江路 1.14 54.14 78
Jinhai Road 金海路  9  2.53 56.67 83 Underground Side
  1. ^ Virtual transfer with line 2 or line 13 – passengers who hold the Shanghai Public Transportation Card and transfer within 30 minutes of exiting the station are able to transfer to other lines without exiting the system.


Important Stations

edit

Future expansion

edit

West extension

edit

In June 2021 Songjiang's Party secretary announced that a five station 17.3 km (10.7 mi) west extension to Dongjing on line 9 will start construction within the year.[12] Construction began on 16 December 2022 with six stations planned on the extension, all in Shanghai's Songjiang District.[13]

Station name change

edit

Headways

edit
Shanghai metro line 12 headway[14]
Time Qixin Road -
Hongmei Road
Hongmei Road -
Jufeng Road
Jufeng Road -
Jinhai Road
Monday - Friday (Working Days)
AM peak 7:30–9:30 About 5 min About 2 min and 30 sec About 5 min
Off-peak 9:30–16:30 About 6 min
PM peak 16:30–20:00 About 7 min and 30 sec About 3 min and 45 sec About 7 min and 30 sec
Other
hours
Before 7:30
After 20:00
About 6 - 8 min
Saturday and Sunday (Weekends)
Peak 8:00–19:00 6 min
Other
hours
Before 8:00
After 19:00
8 - 10 min

Technology

edit

Rolling Stock

edit

The trains of Line 12 are composed of 6-carriage of Class A cars, with a design speed of 80 km/h (50 mph), VVVF AC drive, and a design life of 30 years.

Shanghai metro Line 12 Rolling stock
Fleet numbers Manufacturer Time of
manufac-
turing
Class No
of
car
Assembly[i] Rolling stock Number Notes
246 Bombardier Movia 456 2011-2013 A[ii] 6 Tc+Mp+M+M+Mp+Tc 12A01 1201-1241
(120011-122461)
Original name: AC09B.
Same as 07A01 and 09A02 (but different painting).
90 Bombardier Movia 456 2017-2018 A[ii] 6 Tc+Mp+M+M+Mp+Tc 12A02 1242-1256
(122471-123361)
114 CNR Changchun Railway Vehicles Co., Ltd. 2018-2020 A[ii] 6 Tc+Mp+M+M+Mp+Tc 12A03 12057-12075
(123371-124501)
USB charging ports (concealed design).
  1. ^ Tc: Trailer with cab; Mp: EMU with pantograph; M: EMU without pantograph.
  2. ^ a b c Class A carriage: 21-24m in length, 3.0m in width and 3.8m in height; Capacity: about 310 people.

Future Rolling Stock

edit
Shanghai Metro Line 12 future rolling stock
Fleet numbers Manufacturer Time of
manufac-
turing
Class No
of
car
Assembly[i] Rolling stock Number Notes
108 TBA 2026-2027 A[ii] 6 Tc+Mp+M+M+Mp+Tc 12A04 12076-12093
(124511-125581)
  1. ^ Tc: Trailer with cab; Mp: EMU with pantograph; M: EMU without pantograph.
  2. ^ Class A carriage: 21-24m in length, 3.0m in width and 3.8m in height; Capacity: about 310 people.

References

edit
  1. ^ "Metro breaks records" (in Chinese). Shanghai Metro. 9 March 2019. Retrieved 9 March 2019.
  2. ^ "Eye-catching stations highlight of Metro Line 12". Eastday. 18 December 2013. Archived from the original on 24 December 2013. Retrieved 22 December 2013.
  3. ^ Xu, Huili (23 May 2014). "Qufu Rd. Station of Metro Line 12 Opens on May 10". Graphics by Zuo Rongliang. Shanghai Shentong Metro Group. Retrieved 12 November 2015.
  4. ^ Chen, Lydia (30 December 2008). "Metro Line 12 to connect Minhang and Pudong". Shanghai Daily. Archived from the original on 13 December 2009. Retrieved 27 December 2009.
  5. ^ Xu, Huili; Qu, Chunliang (2 November 2015). "Metro Lines 12, 13 Adjust Departure Time of First, Last Trains from Oct. 24". Graphics by Ji Zhoujie. Shanghai Shentong Metro Group. Retrieved 12 November 2015.
  6. ^ Zhang, Ningniing (18 December 2015). "Metro network adds 27 stations". Shanghai Daily. Retrieved 11 January 2016.
  7. ^ The collapse of the construction site of Shanghai Metro Line 12 by a tower crane has caused 5 deaths and 18 injuries. 2013-02-09
  8. ^ 乘车指南 > Station信息. Shanghai Metro Official Site. Retrieved 17 December 2015. Instructions: 点击相应线路,选择Station,点击"站层图"可查看相应Station的站台结构。
  9. ^ 上海地铁运管中心 (17 December 2015). 12月19日起 11、12、13号线新延伸段建成试运营. Shanghai Metro Official Site. Retrieved 17 December 2015.
  10. ^ 12号线曲阜路站5月10日起开站. Shanghai Metro Official Site. 5 May 2014.
  11. ^ 12号线、16号线12月29日起载客试运营. Shanghai Metro Official Site. 27 December 2013.
  12. ^ Songjiang's development full steam ahead
  13. ^ "设6站、全长17.27公里!轨道交通12号线西延伸工程正式开工建设". Information Office of Shanghai Municipality. Retrieved 16 December 2022.
  14. ^ "Schedule" (in Chinese). Shanghai Metro. 7 July 2021. Retrieved 7 July 2021.