Line 4 (Chongqing Rail Transit)

Line 4 of Chongqing Rail Transit is a rapid transit line in Chongqing, China.[1]

Line 4
A train of Chongqing Rail Transit Line 4
Overview
Native name重庆轨道交通4号线
StatusOperational
Line number4
LocaleChongqing, China
Termini
Stations24
Service
TypeRapid transit
SystemChongqing Rail Transit
Operator(s)Chongqing Rail Line 4 Construction Operation Co., Ltd.
History
Opened28 December 2018; 5 years ago (2018-12-28)
Technical
Line length48.5 km (30.1 miles)
Number of tracks2
Track gauge1,435 mm (4 ft 8+12 in)
Electrification1500 V DC overhead line
Route map

Panguilu
Hongfan depot
Shima Interchange
Yudaishan
     Loop line
Panxi
Dashiba
     Line 5
Daqingcun
Huahuiyuan
     Line 6
Longxi
Jiazhoulu
     Line 3
Min'an Ave.
     Loop line
Chongqing N. Station
N. Square
Chongqing North railway station      Line 10
Toutang
     Line 9
Baoshuigang
     Line 9
Cuntan
Heishizi
Gangcheng
Taipingchong
Tangjiatuo depot
Tangjiatuo
Tieshanping
Luqi
Guoyuan Logistics Hub
Yuzui
Yanping
Shiheqing
Fusheng
Fusheng railway station
Sanbanxi
Longyi Ave.
Longxing
Gaoshita
Pufu
Tongzilin
Shichuan
Huangling
Shichuan depot

Since June 2020, some Express trains through operate from Line 4 into the Loop line.[2]

Interior of a Line 4 train

Opening timeline

edit
Segment Commencement Length Station(s) Name
Chongqing North Station North Square – Tangjiatuo 28 December 2018 15.7 km (9.8 mi)[3] 7 Phase 1
Min'an Ave. – Chongqing North Station North Square 11 January 2019 1
Tangjiatuo – Huangling 18 June 2022[4] 32.8 km (20.4 mi) 15 Phase 2
Gangcheng 7 October 2023 infill station 1

Stations

edit

Phases 1 and 2

edit

Phase 1 (Min'an Ave. – Tangjiatuo) is 15.754 km (9.789 mi) in length (underground section is 11.075 km (6.882 mi), elevated section is 4.679 km (2.907 mi)).[3] In June 2018, debugging of the first segment of Phase I commenced.[5] Phase 1 of Line 4 began operating on December 28, 2018.

Phase 2 (Tangjiatuo – Huangling) is 32.8 km (20.4 mi) in length (21.25 km (13.20 mi) underground and 11.55 km (7.18 mi) elevated[6]) with 15 stations (10 underground stations and 5 elevated stations).[7] In 2022, debugging of this segment commenced.[8] The segment opened on June 18, 2022.[9]

Service
routes
Station
No.
Station name[8] Connections Distance
km
Location
E L English Chinese
Through-service to/from Tiaodeng via Loop line
 
  
Min'an Ave. 民安大道      Loop line - 0.00 Yubei
 
  
Chongqing North Station North Square[a] 重庆北站北广场      Line 10 2.27 2.27
 
  
Toutang 头塘      Line 9 2.36 4.63 Jiangbei
 
  
Baoshuigang 保税港      Line 9 1.36 5.99
 
  
Cuntan 寸滩 2.59 8.58
 
  
Heishizi 黑石子 1.53 10.11
 
  
Gangcheng 港城 1.29 11.4
 
  
Taipingchong 太平冲 2.13 13.53
 
  
Tangjiatuo 唐家沱 1.82 15.35
 
  
Tieshanping 铁山坪 1.38 16.73
 
  
Luqi 鹿栖 5.30 22.03
 
  
Guoyuan Logistics Hub 果园物流枢纽 2.60 24.63
 
  
Yuzui 鱼嘴 2.73 27.36
 
  
Yanping 雁坪 1.45 28.81
 
  
Shiheqing 石河清 2.69 31.50
 
  
Fusheng 复盛   Fusheng 2.16 33.66
 
  
Sanbanxi 三板溪 1.32 34.98
 
  
Longyi Ave. 龙驿大道 2.52 37.50 Yubei
 
  
Longxing 龙兴 1.56 39.06
 
  
Gaoshita 高石塔 1.13 40.19
 
  
Pufu 普福 1.96 42.15
 
  
Tongzilin 桐梓林 1.91 44.06
 
  
Shichuan 石船 2.64 46.70
 
  
Huangling 黄岭 1.57 48.27
  1. ^ The former translation is North Square of Chongqingbei Railway Station, which has been replaced since the opening of Line 10's station

Western Extension

edit
  • Under construction

The Western extension of Line 4 started construction in March 2021. It will add 9 more stations west of Min'an Ave. station. The extension is 11 km (6.8 mi) in length.[10]

Station
No.
Station name Connections Distance
km
Location
English Chinese
Panguilu 盘桂路 Jiangbei
Shima Flyover 石马立交
Yudaishan 玉带山      Loop line
Panxi 盘溪
Dashiba 大石坝      Line 5
Daqingcun 大庆村 Yubei
Huahuiyuan 花卉园      Line 6
Longxi 龙溪
Jiazhoulu 嘉州路      Line 3

References

edit
  1. ^ "轨道交通4号线、5号线、10号线和环线 明年部分线路有望建成通车". May 17, 2016.
  2. ^ "轨道交通将跨线运行 唐家沱到重图不到40分钟-新华网". m.xinhuanet.com. Retrieved August 27, 2020.
  3. ^ a b "重庆轨道交通四号线一期工程".
  4. ^ "重庆轨道交通4号线二期今日将开通运营". cq.cqnews.net.
  5. ^ "轨道4号线不载客试运行,有望年内投用". June 21, 2018.
  6. ^ "重庆轨道交通4号线二期、18号线、5号线跳蹬至江津段、市域快线璧山至铜梁线PPP项目". Archived from the original on June 9, 2022. 线路全长约32.8km(地下段长约21.25km,高架段长约11.55km)
  7. ^ "重庆轨道交通4号线进入全面主体结构施工阶段".
  8. ^ a b "轨道4号线二期通过验收 28日进行不载客试运行". January 26, 2022.
  9. ^ "重庆轨道交通4号线二期今日中午12时开通运营". Archived from the original on June 18, 2022.
  10. ^ "重庆新开工4条轨道线路 看看这些站有没有经过你家". March 2, 2021.