Line 5 of the Chengdu Metro (Chinese: 成都地铁5号线; pinyin: Chéngdū Dìtiě Wǔ Hào Xiàn) is a rapid transit line in Chengdu. It starts at Huagui Road and ends at Huilong. The total length is 49.018 km (30.5 mi).
Line 5's color is purple. This line began construction on 14 September 2015,[1] was opened on 27 December 2019, from Huagui Road to Huilong.
Originally, the line was planned to use 6-car Type A rolling stock. However, anticipating high demand as the line will provide relief for the older Line 1 and connect several important business and residential areas, the line was redesigned to allow for expansion to use 8-car Type A rolling stock.[2] This will allow for an ultimate configuration of the line to reach capacities of 64,300 people per hour per direction.[3][4]
Progress
edit- 2015
- July 6, Phase 1 & 2 are officially approved.[5]
- In August, all stations started construction.
- 2016
- August 18, first tunnel boring machine started tunneling between Jiudaoyan and Dujianian.[6]
- November 3, first tunnel section is finished.[7]
- November 4, to accommodate the projected high demand, Line 5 was redesigned from supporting 6-car A-Type trains to 8-car A-Type trains.[8]
- November 12, Dujianian topped out, being the first station on the line to do so.[9]
- 2017
- May 25, Keyuan to Gaoshengqiao is the first to finish all tunnel work.[10]
- December 5, Phase 1 & 2 begins track-laying.[11]
- 2018
- April 17, first trainbody was completed by CRRC Chengdu. It is the first A-type train for Chengdu Metro.[12]
- September 9, tunnel construction is finished.
- November 10, first train for Dafeng Depot arrived.
- November 22, elevated sections finished sound barrier work.
- December 11, Elevated sections finished power-off testing from Huagui Road to Xingfuqiao.
- December 15, Elevated sections and Dafeng Depot finished testing.
- December 28, Phase 1 & 2 finished track-laying.
- 2019
- October 30, 41 stations are fully functional and finished station testing; all stations are now operating by Chengdu Metro Company.
- November 22, all escalators passed government assessment.
- December 9, Phase 1 & 2 passed safety assessment.
- December 25, Chengdu Metro officially announced Line 5's opening date scheduled for December 27 is the opening time.
- December 27, Phase 1 & 2 started public operation.
- 2020
- August 8, Line 5 trains will have different air conditioning settings in each car. Riders can choose between the center four cars which are set to 27 degrees or the two cars on each end which are set to 25 degrees.[13]
- 2022
- On 16 Feb 2020, in order to fix the noise issue of Line 5, Xingfuqiao to Beibu Shopping Mall to Liaojiawan sections now limits operational speed of 60 km/h on average, minimizing the noise to environment and neighbourhoods.[14]
Timeline
editSegment | Commencement | Length | Station(s) | Name |
---|---|---|---|---|
Huagui Road — Huilong | 27 December 2019 | 49.018 km (30.5 mi) | 41 | Phase 1 & 2 |
Stations
editService
routes |
Station
No. |
Station name | Transfer | Distance km |
Location | |||
---|---|---|---|---|---|---|---|---|
English | Chinese | |||||||
● | 05 01 | Huagui Road | 华桂路 | - | 0.000 | Xindu | ||
● | 05 02 | Baishuichang | 柏水场 | 1.139 | 1.139 | |||
● | 05 03 | Liaojiawan | 廖家湾 | 0.856 | 1.995 | |||
● | 05 04 | Beibu Shopping Mall | 北部商贸城 | 1.983 | 3.978 | Jinniu | ||
● | 05 05 | Xingfuqiao | 幸福桥 | 1.582 | 5.560 | |||
● | 05 06 | Jiudaoyan | 九道堰 | 0.932 | 6.492 | |||
● | 05 07 | Dujianian | 杜家碾 | S11 | 0.766 | 7.258 | ||
● | 05 08 | Dafeng | 大丰 | 0.848 | 8.106 | Xindu | ||
● | ● | 05 09 | Shixi Park | 石犀公园 | 1.711 | 9.817 | ||
● | ● | 05 10 | Huanghuayuan | 皇花园 | 0.816 | 10.633 | ||
● | ● | 05 11 | Lujiaqiao | 陆家桥 | 1.123 | 11.756 | Jinniu | |
● | ● | 05 12 | Quanshui Road | 泉水路 | 1.299 | 13.055 | ||
● | ● | 05 13 | Dongzikou | 洞子口 | 27 | 1.038 | 14.093 | |
● | ● | 05 14 | Funing Road | 福宁路 | 0.769 | 14.862 | ||
● | ● | 05 15 | Wukuaishi | 五块石 | 0.921 | 15.783 | ||
● | ● | 05 16 | Saiyuntai | 赛云台 | 0.765 | 16.548 | ||
● | ● | 05 17 | 2nd Beizhan Road West | 北站西二路 | 7 Chengdu BRT | 0.775 | 17.323 | |
● | ● | 05 18 | Xibeiqiao | 西北桥 | 6 | 1.499 | 18.822 | |
● | ● | 05 19 | Huapaifang | 花牌坊 | 0.906 | 19.728 | ||
● | ● | 05 20 | Fuqin | 抚琴 | 0.998 | 20.726 | ||
● | ● | 05 21 | Chengdu University of TCM & Sichuan Provincial People's Hospital |
中医大·省医院 | 2 4 | 1.293 | 22.019 | Qingyang |
● | ● | 05 22 | Qingyang Taoist Temple | 青羊宫 | 13 | 0.676 | 22.695 | |
● | ● | 05 23 | Provincial Orthopaedics Hospital | 省骨科医院 | 17 | 0.915 | 23.610 | |
● | ● | 05 24 | Gaoshengqiao | 高升桥 | 3 10 | 1.358 | 24.968 | Wuhou |
● | ● | 05 25 | Keyuan | 科园 | 1.400 | 26.368 | High-Tech Zone | |
● | ● | 05 26 | Jiuxing Avenue | 九兴大道 | 8 | 0.959 | 27.327 | |
● | ● | 05 27 | Shenxianshu | 神仙树 | 7 Chengdu BRT | 1.599 | 28.926 | |
● | ● | 05 28 | Shiyang Flyover | 石羊立交 | 1.811 | 30.737 | ||
● | ● | 05 29 | Chengdu First People's Hospital | 市一医院 | 30 | 0.662 | 31.399 | |
● | ● | 05 30 | Jiaozi Avenue | 交子大道 | 0.851 | 32.250 | ||
● | ● | 05 31 | Jincheng Avenue | 锦城大道 | 9 | 0.858 | 33.108 | |
● | ● | 05 32 | Jincheng Lake | 锦城湖 | 1.334 | 34.442 | ||
● | ● | 05 33 | Dayuan | 大源 | 1.503 | 35.945 | ||
● | ● | 05 34 | Minle | 民乐 | 1.027 | 36.972 | ||
● | ● | 05 35 | Qilong | 骑龙 | 1.722 | 38.694 | Tianfu New Area | |
● | ● | 05 36 | The Police College | 警官学院 | 1.449 | 40.143 | ||
● | ● | 05 37 | Erjiang Temple | 二江寺 | 1.479 | 41.622 | ||
● | 05 38 | Nanhu Flyover | 南湖立交 | 1.292 | 42.914 | |||
● | 05 39 | Yixin Lake | 怡心湖 | 19 | 2.034 | 44.948 | ||
● | 05 40 | Longma Road | 龙马路 | 1.649 | 46.597 | |||
● | 05 41 | Huilong | 回龙 | 6 | 1.605 | 48.202 | ||
See also
editReferences
edit- ^ 成都地铁5号线设41个站 2019年开通运营 [Chengdu Metro Line 5 str 41 stations To be opens in 2019] (in Chinese). Sichuan News. 21 May 2015. Retrieved 2015-07-04.
- ^ 成都地铁5号线将采用“8A”车辆编组 每列车定员2144人_网易新闻. 163.com news. Archived from the original on 2016-11-13. Retrieved 2018-07-04.
- ^ 成都地铁5号线将进行扩容 运能提高约70% ——凤凰房产成都. cd.house.ifeng.com. Retrieved 2016-11-20.
- ^ "Sina Visitor System" 1号线太挤?“大肚子”5号线救急. 2018-04-18.
- ^ "成都地铁5号线一、二期工程获批 工期四年半" (in Chinese). 四川新闻网. 2015-07-06. Retrieved 2015-07-06.
- ^ "成都最长在建地铁线路5号线 首台盾构下井(图)" (in Chinese). 凤凰网. 2016-08-19. Retrieved 2016-08-19.
- ^ "成都地铁5号线一、二期工程首段盾构区间贯通" (in Chinese). 网易. 2016-11-03. Archived from the original on 2018-04-27. Retrieved 2016-11-03.
- ^ "成都地铁5号线将采用"8A"车辆编组 每列车定员2144人" (in Chinese). 网易. 2016-11-04. Archived from the original on 2016-11-13. Retrieved 2016-11-04.
- ^ "成都地铁5号线一、二期工程首个车站主体结构顺利封顶" (in Chinese). 四川在线. 2016-11-13. Retrieved 2016-11-13.
- ^ "成都地铁5号线科园站-高升桥站间双线贯通 已17站封顶" (in Chinese). 四川新闻网. 2017-05-26. Retrieved 2017-05-26.
- ^ "成都地铁5号线一二期工程正式开始铺轨(图)" (in Chinese). 凤凰网. 2017-12-05. Retrieved 2017-12-05.
- ^ "首列"成都造"地铁5号线A型铝合金车体下线" (in Chinese). 搜狐. 2018-04-18. Retrieved 2018-04-18.
- ^ "怕冷的中间走,怕热的两头去!成都地铁5号线"分区控温"来了" (in Chinese). 四川在线. 2020-08-08. Retrieved 2020-08-08.
- ^ "关于成都地铁5号线幸福桥至廖家湾地铁噪音问题,已降低列车运行". 2020-08-07.