Midi E 3301 was a prototype electric locomotive of Class E 3300 designed for the Chemins de fer du Midi, France. Because of poor performance, it was refused by the Compagnie du Midi and was re-deployed to Swiss railways. On 1 May 1919, it was classified Fb 2/5 11001 and, in 1920, it became experimental locomotive Be 2/5 11001 of the Swiss Federal Railways (SBB).

Midi E 3300
SBB CFF FFS Be 2/5
Electric locomotive Chemins de Fer du Midi E 3301 on the Bern-Lötschberg-Simplon line, later SBB Be 2/5 11001
Type and origin
Power typeElectric
BuilderSLM and Brown-Boveri
Build date1910-1911
Total produced1
Specifications
Configuration:
 • AAR1-C-1
 • UIC1′C1′
Gauge1,435 mm (4 ft 8+12 in)
Wheel diameter1610 mm
Trailing dia.950 mm
Adhesive weight33 tonnes
Loco weight75 tonnes
Power supplyOverhead line
Electric system/sSingle phase AC,
12/15 kV, 16⅔ Hz.
Current pickup(s)2 pantographs
Traction motorsTwo Deri repulsion motors
Performance figures
Maximum speed75 km/h
Power output660 kW (continuous)
736 kW (one hour)
Career
NicknamesViktor

Overview

edit

Many lines of the Midi network being mountain lines, the company began an electrification programme in 1909. The system chosen was single phase alternating current at 12 kV and 16⅔ Hz.

 
Prototype locomotive E.3101

Six prototype locomotives were ordered for the Perpignan - Villefranche-de-Conflent line. They were:[1]

The E 3301 locomotive was expected to perform the following tasks:

  • Haul a 400-ton train on a 2.2% gradient
  • Haul a 300-ton train at 40 km/h on a 2.2% gradient
  • Haul a 100-ton train at 60 km/h on a 2.2% gradient
  • Be equipped with an electric brake for descents

Technical details

edit
 
E 3301 in 1910
 
Brown-Boveri-Déri repulsion motor with 10 poles. Two of these motors were used in the French electric locomotive Midi E3301

The companies SLM Winterthur and Brown-Boveri built the E3301 locomotive in 1910-1911. Power was provided by two large Déri repulsion motors that filled almost the entire engine room. The speed and direction of the motors were controlled by brush-shifting, allowing the train to start without jolting. The motors were powered at 1,250 V by two traction transformers connected in parallel. The power of the motors was transmitted to the central axle by two inclined rods, without gears, then to the other drive axles by coupling rods.

Trials

edit

The E 3301, equipped with auxiliary transformer windings for 15 kV operation, was tested on the Spiez - Frutigen line. During these tests, some design faults became apparent. On 18 February 1912, the locomotive was transferred to Perpignan and trials continued until 16 August 1912. The locomotive was unable to deliver the required performance, as was the case for two other machines. Another gave partial satisfaction, but only E 3201 was fully satisfactory. The Midi also ordered railcars E ABD 1 to 30, which became Class Z 4900 of the SNCF.

Modifications and axle drive testing

edit
 
As modified, showing the different axle drives

Otto Tschanz [de], the SBB's senior mechanical engineer, suggested converting the surplus locomotive into a test vehicle for the new technique of individual axle drives that were replacing coupling rods. It was returned to Brown-Boveri and the original rod drives, traction motors and electrical equipment removed. The first driving axle was unpowered and converted to a carrying axle. As it was still balanced for the rod drive and these cast-in balances could not be removed, a new balance weight had to be fitted to the crankpin position. The centre axle was fitted with a Buchli drive and the third with Tschanz's own design of Tschanz drive.[i] This Tschanz drive transmitted torque via a spur reduction gear and a cardan shaft running inside a hollow axle. As the Buchli drive was as yet untried, a drive was fitted on each side of the axle. This became the French practice, as on the SNCF 2D2 5500 and 9100, but in Switzerland a single-sided drive woud be considered adequate. Overall this now gave a wheel arrangement changed from 1′C1′ to 1′1Bo1′.

The two transformers were replaced by a single one behind the first driver's cab, balancing the traction motors, and with a tap changer for power control.

Service in Switzerland

edit

The modified locomotive was first tested on the Lötschberg railway line. On 1 August 1918, it was officially handed over to the Bern–Lötschberg–Simplon railway (BLS) under number 2B1 10001 for the start of the tests.

Until 1919, the machine was used to haul passenger trains on the ThunSpiez line. On 1 May 1919 it entered permanently the service of the SBB under the number Fb 2/5 10001. From the energizing of the line BernSpiez on 7 July 1919, it began to haul passenger trains. By the end of 1919, it had travelled 24,500 kilometres. In 1920, when it became Be 2/5 11001, it travelled a further 5,500 kilometres and, by 1921, the total was 35,300 kilometres. Around this time, the locomotive was nicknamed Viktor.

SBB were receiving new and better locomotives, so they looked for a new assignment for Viktor. On 1 June 1922, it was assigned to the Erstfeld depot to haul trains on the Erstfeld–ArthGoldau and Erstfeld–Lucerne lines and covered an average daily distance of 224 km. Between 1923 and 1924, it also pulled passenger trains on the Gotthard line between Lucerne and Bellinzona. In 1924 it travelled only 2,000 kilometres, apparently because of accident damage.

In 1925, Viktor was transferred to the Lucerne depot and hauled trains to Rotkreuz (in the Canton of Zug), Zürich and Arth-Goldau and still travelled 202 kilometres daily average. Also in 1925, the train-heating boiler was replaced by a 1,000 volt electric train supply. From 1 October 1926, its use declined and it was used only occasionally on short freight trains. In May 1927, traffic to Rotkreuz and Arth-Goldau increased and Viktor was put back into service and travelled 135 km every day.

On 15 May 1928, the locomotive Be 3/5 12201 resumed its services and Viktor was relegated to shunting duties at Zürich depot. It covered only about 7,000 kilometres in 1928. In 1929, the mileage dropped to 592 km.

Final years

edit

In 1929, Viktor was converted into a self-propelled welding wagon Xe 1/5 n° 99999 which later became XTe 1/5 n° 99999. It was withdrawn on 17 September 1937 and scrapped in December 1937.

References

edit
  1. ^ Similar tests with a mixed arrangement of axle drives were also tried later on the SBB-CFF-FFS Ae 4/8.
  1. ^ Ransome-Wallis, P. (2001). Illustrated Encyclopedia of World Railway Locomotives. Courier Corporation. p. 149. ISBN 9780486412474.
  • Davies, John. Chemins de fer du Midi and Chemins de fer de Paris à Orleans Locomotive List 1840–1938. Woodbridge, Queensland: Dr. John Davies. p. 56. ISBN 0-9585541-0-2.

Further reading

edit
  • Yves Machefert-Tassin, Fernand Nouvion, Jean Woimant, Histoire de la traction électrique. tome I : des origines à 1940, Éditions La Vie du Rail, 1980, 561p. (ISBN 2902808224)
  • Lucien-Maurice Vilain, Évolution du matériel moteur et roulant de la Cie du Midi : 19855 à 1934 (fusion P.O. Midi), Édition Picador, 1979, 286p. (ISBN 2902653034)