Champlain Hudson Power Express

The Champlain Hudson Power Express (CHPE) is a planned high-voltage direct current (HVDC) underwater and underground power cable project linking the Quebec area to the New York City neighborhood of Astoria, Queens.[1] Following completion of a review by the New York State Public Service Commission, construction began in 2022. The line is permitted and expected to be operational in 2026.[2][3]

Champlain Hudson Power Express
Location
CountryCanada
United States
FromQuebec
ToNew York City
Ownership information
PartnersTransmission Developers Inc.
Blackstone Group
OperatorTransÉnergie
Construction information
Expected2026
Technical information
Total length339 mi (546 km)
Power rating1,200 MW[1]

The venture, being developed by Transmission Developers Inc. (TDI), a Blackstone Group, L.P. (Blackstone) portfolio company, would carry clean energy—hydropower and wind power from eastern Canada—and feed it directly in the New York City electricity market. Construction costs for this project are estimated at US$2.2 billion for the section located in the State of New York.[4] The estimated total cost is US$4.5 billion.[3]

The Quebec section of the line would be built and operated by TransÉnergie, the transmission arm of Hydro-Québec.[5]

Background

edit

Power rates in the New York metro area and Long Island have long been among the highest in the U.S.[6] and according to the U.S. Department of Energy, New York City is the "epicenter" of grid congestion in the eastern United States. The congestion problem in the New York City area and on Long Island is compounded by the fact that the area uses two-thirds of the state's electricity while most generation and import capacity is located upstate and near the Great Lakes.[7]

Over the years, a number of proposals to increase transmission capacity to the New York City and Long Island markets have encountered hostile reactions and determined opposition from environmental groups and communities along the planned paths.[citation needed] For instance, construction of the Cross Sound Cable, a 328-MW submarine DC cable linking Connecticut to Long Island via the Long Island Sound, was authorized in 2002, but its commissioning was delayed for a year because of a dispute involving the promoter and the state of Connecticut.[8] Another project, the Neptune Regional Transmission System has been operational since 2007. The 65 miles (105 km) 500 kV cable connects New Jersey and Long Island. It runs buried in the Atlantic Ocean and has a capacity of 660 megawatts.[9] A proposed HVDC line, West Point Partners, that would have interconnected the grid from a substation in Athens, New York to a substation near the Indian Point Energy Center was tabled when the landowner where the southern converter station would be located, Con Edison, sold the land to the Village of Buchanan. The Village of Buchanan then sold the rights to use the land to the natural gas company Spectra for their new proposed natural gas pipeline.[10]

However, a 400 kilovolts DC line 306 kilometres (190 mi) between the Rock Tavern substation, 60 miles north of New York, and the Marcy hub in central New York, has been marred by controversy. Launched in 2006,[11] the proposed New York Regional Interconnect (NYRI) had a 1,200 megawatts capacity. It was shelved by its developers in early 2009 after two years of staunch opposition from several groups concerned by the impact of pylons along the proposed route.[12]

Project

edit

TDI, whose board is chaired by Brian Kubeck, is backed by Blackstone and was announced on February 23, 2010.[13] Since then, the CHPE Project has made significant progress in terms of securing the governmental approvals. The Federal Energy Regulatory Commission authorized the Project developers to sell transmission rights at negotiated rates in July 2010.[14] Less than a year later, the New York State Department of State issued its Coastal Zone Consistency determination for the project.[citation needed]

Settlement

edit

On February 24, 2012, the parties participating in the detailed review of the project being conducted before the New York State Public Service Commission (PSC) announced that they had reached a settlement of all of the issues in the proceeding.[15] On April 18, 2013, the New York State Public Service Commission granted the CHPE project a Certificate of Environmental Compatibility and Public Need.[citation needed]

The CHPE project tries to avoid difficulties encountered by other proposals by presenting itself as an "environmentally benign" solution. By avoiding overhead wires and 10 story high towers, the promoter hopes to avoid the fate of previous projects, such as NYRI. The initial project involved two 1,000 MW lines, the first one to New York, and the second going all the way to Connecticut, via the Long Island Sound. The construction cost for the two lines and converter stations in the U.S. was estimated at $3.8 billion.[16] The line to Connecticut was cancelled in July 2010.[17]

According to the company's president and CEO, Donald Jessome, choosing an underwater route avoids " disrupt[ing] communities with overhead transmission". The developer says that the cable also provides economic and environmental benefits to the state, bringing low-cost and clean power to critical load centers.[16]

Opposition to project

edit

The Atlantic chapter of the Sierra Club has asked its members to oppose this project. New York wind energy producers currently cannot get their electricity carried to New York City. It is the Sierra club's contention that CHPE will stop any chance of New York City getting locally produced wind power and in general dampen the market for local alternative energy production.[18]

Route

edit

The proposed cable would have a length of approximately 339 miles (546 km)[3] between the Canada-U.S. border and its southern terminal, in New York City. The two 5-inch (127 mm) cables would be buried at varying depths of 7 feet (213 cm) under Lake Champlain and the Hudson River, Harlem, and East Rivers.[citation needed]

The cables would cross the border under Lake Champlain and would run southward to the Town of Dresden north of the Village of Whitehall. On its way to the Hudson, the cables would be routed briefly along State Route 22 and then parallel the Delaware & Hudson Railroad right-of-way to Rotterdam, at which point it accesses the right-of-way of a CSX Transportation rail line, continuing southwards until it enters the Hudson River in the Town of Catskill.[citation needed]

Once the cables are in the Hudson River, they continue south to the Town of Stony Point, where the CSX railroad right-of-way is again relied on until the cables re-enter the Hudson in the Town of Clarkstown. The cables next make landfall in the Harlem River Intermodal Yard in the Bronx, traverses the East River to reach Queens, and terminates at a converter station on the large energy campus in the Astoria neighborhood in the New York City borough of Queens.[citation needed]

Economics, emission levels, and reliability

edit

In an economic analysis filed on behalf of the promoter to the New York Public Service Commission in July 2010, London Economics International estimates that the projected line would save New York customers $8.1 billion (2010) on their electricity bills over the first 10 years of operations, between 2015 and 2024.[19] In addition, the proposed cable would have positive impacts on the electricity grid, since power carried by the cables could force the retirement of older, uneconomic power plants in New York.[19]

The planned line, which would carry 7.64 terawatt-hours of renewable electricity per year, would lower SO
2
emissions by 6,800 tonnes, NO
x
emissions by 10,800 tonnes and CO
2
emissions by nearly 37 million tonnes during the first decade of operation.[19]

The CHPE is expected to create 1,400 jobs directly and thousands of indirect and induced jobs.[20] The Project will also reinforce the reliability of New York's bulk power delivery system.[citation needed]

The proposed CHPE project has been granted permits by the New York State Public Service Commission, and the final Environmental Impact Statement (EIS) was issued by the U.S. Department of Energy for the project as of 2014.[21][22]

Hydro-Québec's position

edit

According to the promoter, the Quebec section of the line would start at a DC conversion station to connect with Hydro-Québec TransÉnergie's Hertel substation (735-315 kV) near La Prairie, and would reach the junction point at the international border in Lake Champlain.[5]

The initial reaction of Hydro-Québec (HQ) and the Quebec government to the CHPE project was mixed, considering the 400 to 500 million Canadian dollars price tag for the Quebec section of the line. In addition, the CHPE could be seen as competing with a proposed 1,200 MW HVDC line to be built by the company in association with NSTAR and Northeast Utilities, which was expected to increase exports of Quebec hydropower to the neighboring New England states.[23][24] Reflecting on the project in April 2010, Hydro-Quebec's CEO, Thierry Vandal, stated that it was technically "very complex" and "very costly".[25]

Despite its initial reaction, the Quebec utility intervened in support of the proposal before the FERC in May 2010,[26] and the PSC in March 2012.[27][18] In the March 2012 letter,[28] HQ cited the CHPE project's potential to bring large quantities of renewable energy to downstate New York at no cost to New York ratepayers and the CHPE project's progress before the PSC as the reasons for entering into "active discussions" with TDI.[citation needed]

Late in January 2013, Hydro-Québec formally filed a project notice to build the Quebec part of the line to the Quebec Minister of Sustainable Development, Environment, Wildlife and Parks, Yves-François Blanchet. The ±320 kV power line would start at the Hertel transmission station, near La Prairie, to reach the US border on the shore of Lake Champlain. The project includes the deployment of a DC terminal at Hertel TS, but in contrast to the US part of the line, Hydro-Québec excludes running the line in the Richelieu riverbed.[29]

After a period of public consultation, HQ came back with a new 58-kilometer path running alongside a 735 kV power line, Autoroute 15, Quebec Routes 202, 221 and rural roads to reach the international border west of the Saint-Bernard-de-Lacolle / Rouses Point border crossing.[30]

See also

edit

References

edit
  1. ^ a b Anderson, Jared. "Opponents of 1,250-MW power line into New York City cite winter deliverability". S&P Global Commodity Insights. S&P Global Commodity Insights. Retrieved 14 March 2022.
  2. ^ "Transmissions Developers Inc". Transmission Developers Inc. 2021. Retrieved 1 June 2021.
  3. ^ a b c Ryan Dezember (18 February 2022). "Can Quebec's Dams Power New York City? Blackstone Is Betting $4.5 Billion on It". The Wall Street Journal. Retrieved 14 March 2022.
  4. ^ Transmission Developers Inc. (2010), "Project Details: Background", Champlain Hudson Power Express, retrieved 2010-08-02
  5. ^ a b Transmission Developers Inc. (2010-05-03), Application for Authority to Sell Transmission Rights at Negotiated Rates and Request for Expedited Action, Federal Energy Regulatory Commission, p. 7, retrieved 2010-08-02
  6. ^ Sanderson, Bill (2010-01-29), "Con Ed electric prices highest of any major utility, federal numbers show", New York Post, New York, retrieved 2010-08-02
  7. ^ United States Department of Energy (December 2009), 2009 National Electric Transmission Congestion Study (PDF), Washington, pp. 45–48, archived from the original (PDF) on 2010-05-27{{citation}}: CS1 maint: location missing publisher (link)
  8. ^ State of New York (2004-06-25), "Governor Pataki hails agreement on Cross Sound Cable and gives order to energize cable and make it operational", Long Island Power Authority, archived from the original on 2011-07-18, retrieved 2009-11-29
  9. ^ Neptune Regional Tramsmission System (July 2007), Neptune: Project Overview (PDF), retrieved 2010-08-02[permanent dead link]
  10. ^ Wilson, David McKay (February 26, 2016). "Cortlandt gets $2.8M from pipeline project". www.lohud.com. Retrieved January 28, 2020.
  11. ^ NYRI (2010-04-08), An Introduction to New York Regional Interconnection (PDF), archived from the original (PDF) on 2011-02-25, retrieved 2010-08-02
  12. ^ Cooper, Elizabeth (2009-04-04), "NYRI quits; Power line project dead", Utica Observer-Dispatch, Utica, NY, archived from the original on 2013-02-05, retrieved 2010-08-02
  13. ^ "Meet the Transmission Developers Inc. Team". Chpexpress.com. Champlain Hudson Power Express. Retrieved 14 March 2022.
  14. ^ "Press Release: TDI ANNOUNCES IMPORTANT MILESTONE IN THE DEVELOPMENT OF THE CHAMPLAIN HUDSON POWER EXPRESS". Champlain Hudson Power Express.
  15. ^ "Application of Champlain Hudson Power Express, Inc. for a Certificate of Environmental Compatibility and Public Need Pursuant to Article VII". NYS Department of Public Service.
  16. ^ a b Bosch, Adam (2010-02-26), "Canadians plan under-water power line", Times-Herald Record, Albany, NY, retrieved 2010-03-02
  17. ^ Turmelle, Luther (2010-07-09), "Canadian electric cable won't reach Connecticut", The Middletown Press, Middletown, CT, archived from the original on 2012-03-05, retrieved 2010-08-02
  18. ^ "Stop CHPE: No need to import Canadian energy from 1,200 miles away" in the Sierra Atlantic Volume 41 Spring 2015
  19. ^ a b c London Economics International LLC (2010-07-16), Projected Energy Market, Capacity Market and Emissions Impact Analysis of the Champlain-Hudson Power Express Transmission Project for New York (PDF), Boston, pp. 8–11{{citation}}: CS1 maint: location missing publisher (link)
  20. ^ Riley, Shantal (4 November 2021). "Canadian Renewable Hydropower Is Heading To New York City". Gothamist. WNYC. Retrieved 14 March 2022.
  21. ^ "Permits". Chpexpress.com. Champlain Hudson Power Express. Retrieved 14 March 2022.
  22. ^ "Final Environmental Impact Statement Issued by the U.S. Department of Energy for the Champlain Hudson Power Express". TDI CHPExpress. Retrieved 15 March 2022.
  23. ^ Presse canadienne (2010-03-02), "Une ligne de 2000 MW entre le Québec et New York?", La Presse (in French), Montreal, archived from the original on 2010-03-04, retrieved 2010-03-02
  24. ^ Rulison, Larry (2010-03-16), "Quebec puts its power on the line", Albany Times-Union, Albany, NY, p. 1, retrieved 2010-03-19
  25. ^ Baril, Hélène (2010-04-09), "Hydro-Québec: "on va livrer ce qui a été demandé"", La Presse (in French), Montreal, archived from the original on 2010-04-10, retrieved 2010-04-09
  26. ^ H.Q. Energy Services (U.S.) (May 24, 2010), "Motion to Intervene of H.Q. Energy Services (U.S.) Inc. and Comments in Support of Application under ER10-1175", Federal Energy Regulatory Commission, Washington
  27. ^ Larocque, Sylvain (2010-07-09), "Hydro-Quebec gets behind proposed transmission line to US", Canadian Business, Canadian Press, retrieved 2010-07-10[permanent dead link]
  28. ^ "Article VII Public Documents". NYS DPS.
  29. ^ St-Pierre, Annie (January 29, 2013). "Projet d'exportation d'Hydro-Québec vers New York". Argent (in French). Archived from the original on February 19, 2013. Retrieved January 29, 2013.{{cite news}}: CS1 maint: unfit URL (link)
  30. ^ Hydro-Québec (September 2013). "Interconnexion Hertel-New York. information sur la solution retenue • Septembre 2013" (PDF) (in French). Retrieved September 24, 2021.
edit