The Colne Valley Viaduct is a bridge, under construction as of 2024, which will carry the High Speed 2 railway over the Colne Valley Regional Park and the Grand Union Canal, in Hillingdon, west London. When completed, its length of 3.4 kilometres (2.1 mi) and a weight of 116,000 tonnes will make it the largest railway bridge in the UK. It is one of the largest single civil engineering works of HS2 Phase 1.[2]

Colne Valley Viaduct
Artist's depiction of the completed viaduct
Coordinates51°35′09″N 0°29′24″W / 51.5859°N 0.4900°W / 51.5859; -0.4900
CarriesHigh Speed 2
CrossesColne Valley Regional Park
LocaleHarefield
OwnerAlign MWCC
Characteristics
Total length2.1 miles (3.4 km)[1]
Height10 metres (33 ft)[1]
Rail characteristics
No. of tracks2
Track gauge1,435 mm (4 ft 8+12 in)
Electrified25 kV 50 Hz AC
History
ArchitectAlign MWCC
Construction startMarch 2021
Construction endUnder construction
Statistics
Daily trafficHigh speed passenger trains
Location
Map

A contract for the section of the railway pertaining to the viaduct was awarded during 2017 and the design concept was released to the public on 19 January 2018. Preparatory work commenced shortly thereafter, including a compulsory land purchase and the establishment of temporary facilities, including a factory, onsite. Construction of the viaduct commenced during March 2021 with the main deck completed in September 2024 with full completion expected for May 2025.[3][4] Protestors have occasionally occupied the site, and allegations over the viaduct's aesthetic and environmental impact upon the area have been made.

History

edit

Various means for High Speed 2 to traverse the valley of the River Colne were considered. One option which was studied as an alternative to using a viaduct was the extension of the nearby Northolt tunnel, which was also being built for the new line, however this option was dismissed in a report released in February 2015 due to the increased costs and construction time that would be involved.[5] During 2017, Contract C1 (Central 1), which covers the 21.6 km section of the line that the viaduct falls within, was awarded to the Align JV joint venture, comprising Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick.[1] RC Works were carried out by Kilnbridge Construction Services.

On 19 January 2018, the design concept for the Colne Valley Viaduct, which was created by Knight Architects and Atkins, was unveiled by the British Government.[6][7] This concept was produced in consultation with the Colne Valley Regional Park Panel.[1] Additional work on the viaduct's design has also been undertaken by Grimshaw Architects.[8]

In April 2019, Buckinghamshire County Council requested that the government pause all preparatory work until the Oakervee Review had been completed and disagreed with HS2 Limited over mitigation works.[9] During March 2021, Hillingdon Council and HS2 Limited came to an agreement in which, in light of written assurances from the latter, the former shall not pursue a judicial review into the scheme.[10] Shortly following this decision, full planning permission for the viaduct was secured.[2]

Design

edit

The Colne Valley Viaduct is intended to be a major civil engineering work of High Speed 2, being amongst the largest and perhaps the most prominent single feature to be constructed during Phase 1.[1] In terms of its basic configuration, it is a gently curved structure along a horizontal radius of 5,280 metres (17,320 ft), supported by 57 spans and weighing roughly 116,000 tonnes in total. The viaduct crosses over both the River Colne and the Grand Union Canal, at which points its spans are spaced at intervals of 80 metres (260 ft); the majority of over-land spans cover shorter lengths of either 45 or 60 metres (148 or 197 ft).[11][1]

Considerable attention has been directed to the viaduct's aesthetic design and to avoid unnecessarily impacting the surrounding landscape and local community.[1] To reduce its impact upon wildlife and the general public alike, four-metre (13 ft) high translucent acoustic barriers are to be installed along the entire length of the viaduct; these will reduce noise emissions while only incurring a minimal impact upon the view of onboard passengers.[11] The design of the overhead electrification equipment was also bespoke to reduce its visual impact. The exterior concrete surfaces are faceted to provide a more attractive visual and tactile design.[1] However, the viaduct has been subject to criticism from Stop HS2 for ignoring the needs of local residents.[12] Rail industry periodical Rail Engineer notes that the site of the viaduct features multiple factors of sensitivity, pertaining to both environmental and public interests, as well as access issues during the construction phase.[1]

The main deck of the viaduct is to be manufactured at a nearby temporary factory, the assembly of which is to commence from the northern end.[1][13] In total, 908 deck units and 92 pier head units will be produced; weighing between 60 and 140 tonnes, each one unique to its intended place in the overall structure. Assembly will use a match-casting technique with relatively tight tolerance, supported by an adjustable steel formwork and prefabricated steel reinforcement where relevant.[1] While two deck units are to be typically cast each day, the more complex pier head units will each require three days to complete. To appropriately handle rail braking loads,of up to 9,000 tonnes a total of four shock absorber units are to be integrated into the deck structure of the viaduct.[1] The structure will also feature four expansion joints. The foundations will consist of driven piles upon which the faceted framework is installed; water-based piers are considerably more complex in shape and design.[1]

Construction

edit
 
Construction as of April 2024
 
Colne Valley Viaduct under construction in January 2023 showing the bridge deck cross section.
 
Colne Valley Viaduct bridge piers under construction in January 2023.

As early as 2018, protestors had taken up positions in the Colne Valley to voice their objections to the project.[14] In April 2019, 12 Extinction Rebellion protesters began treesitting in order to prevent HS2 Limited chopping down trees as part of preparatory works at Harvil Road, near to the proposed site of the viaduct.[15] There had been a protest camp next to the road since October 2017, which HS2 began evicting in January 2020.[16]

In order to clear the viaduct's intended path, a farmhouse was compulsory purchased while a watersports centre was required to relocate. Both properties are to be demolished.[17][18] Various preparatory works were also undertaken during the 2010s, including the diversion of water mains, the realignment of 275 kVa overhead power line, and a reinforcement of a gas mains, along with other measures.[1] Towards the northern end of the viaduct, a temporary construction compound has been assembled, which accommodates offices, plant, employee welfare facilities, and the pre-cast factories for the project. Sufficient space for the storage and treatment of up to 3,000,000 cubic metres (110,000,000 cubic feet) of chalk slurry has also been provisioned for the construction of the Chiltern tunnel to the north of the viaduct.[1][19]

Progress

edit

During March 2021, construction of the viaduct's foundations commenced, although test piling had occurred before this.[20] Between spring and summer 2021, an internal access road was built, while the onsite factory building the viaduct segments were commissioned during the autumn. During May 2022, deck construction commenced from the northern embankment.[21]

In December 2021, the first six-metre-tall (20 ft) pier for the viaduct was cast.[22][23] Construction of four jetties across the lake was also completed to support work on the piers that will be built in the water.[23] In June 2022, the bridge building machine was launched.[24] By December 2022, 125 of the 1,000 bridge segments had been placed in their final position.[25]

Construction reached the half-way point (1.7km) in November 2023.[26]

In February 2024, construction was halted for "urgent remedial works" in the week before the launching girder was due to begin crossing the Grand Union Canal. This involved repeating cable tensioning in the most recently completed span, which includes drilling out the concrete join.[27]

The final pre-cast deck segment was installed on 5 September 2024.[28]

References

edit
  1. ^ a b c d e f g h i j k l m n o "Colne Valley Viaduct – HS2's largest bridge". railengineer.co.uk. 7 June 2021.
  2. ^ a b Horgan, Rob (1 April 2021). "HS2 secures full planning consent for UK's longest rail bridge after council drops legal challenge". newcivilengineer.com.
  3. ^ "HS2 bridge near Watford now Britain's longest".
  4. ^ Hakimian, Rob (15 July 2022). "HS2 timeline of major events to 2025 revealed". New Civil Engineer. Retrieved 16 July 2022.
  5. ^ "Proposal for Northern Extension of Northolt Tunnel SIFT Report" (PDF). High Speed 2. 27 February 2015. Archived (PDF) from the original on 26 July 2019. Retrieved 3 July 2020.
  6. ^ "HS2 reveals Colne Valley viaduct concepts". GOV.UK. Retrieved 28 July 2020.
  7. ^ Smale, Katherine (19 January 2018). "HS2 reveals controversial Colne Valley viaduct". newcivilengineer.com.
  8. ^ Hopkirk, Elizabeth; Rogers, Dave (15 April 2020). "Huge boost as government tells HS2 to start work". Building Design. Retrieved 28 July 2020.
  9. ^ Smale, Katherine (6 August 2019). "HS2 and council clash over Colne Valley viaduct 'uncertainty'". New Civil Engineer. Retrieved 29 July 2020.
  10. ^ "Hillingdon and HS2 declare peace over plans for Colne Valley Viaduct". hillingdontimes.co.uk. 19 March 2021.
  11. ^ a b "HS2 Colne Valley Viaduct". Grimshaw. Retrieved 28 July 2020.
  12. ^ Wareham, Stephanie (24 January 2018). "Campaigners criticise HS2 plans for 'one of the longest viaducts in UK'". Bucks Free Press. Retrieved 29 July 2020.
  13. ^ Horgan, Rob (14 June 2021). "The reality of working on HS2's biggest construction site". newcivilengineer.com.
  14. ^ Topham, Gwyn (8 December 2020). "Veteran activist Swampy among protesters in HS2 site standoff with police". theguardian.com.
  15. ^ Snaith, Emma (27 April 2019). "Extinction Rebellion activists camp out in trees to protest HS2". The Independent. Retrieved 29 July 2020.
  16. ^ Taylor, Diane (7 January 2020). "HS2 begins evicting activists from protest site after two years". The Guardian. Archived from the original on 13 June 2020. Retrieved 29 July 2020.
  17. ^ Harris, Simon (29 July 2020). "Couple lose battle to save their dream home from HS2 bulldozers". ITV News. Retrieved 30 July 2020.
  18. ^ Taylor, Diane; Barkham, Patrick (13 June 2020). "Rise in injunctions against HS2 protesters". The Guardian. Retrieved 29 December 2022.
  19. ^ Horgan, Rob (27 April 2021). "How HS2 plans to reuse chalk slurry from Chilterns tunnel to 'rewild' the Colne Valley". newcivilengineer.com.
  20. ^ "Work begins to form HS2's Colne Valley Viaduct foundations". Global Railway Review. Retrieved 18 March 2021.
  21. ^ "HS2: Work begins on 'UK's longest railway bridge' in Buckinghamshire". BBC News. 31 May 2022. Retrieved 29 December 2022.
  22. ^ "First pier cast for Colne Valley viaduct [– with video]". www.theconstructionindex.co.uk. Retrieved 20 December 2021.
  23. ^ a b "HS2 creates the first of 56 giant piers for Colne Valley Viaduct". Planning, BIM & Construction Today. 20 December 2021. Retrieved 4 February 2022.
  24. ^ "HS2 celebrates start of construction on UK's longest railway bridge". HS2 News and Information. Retrieved 3 June 2022.
  25. ^ Hakimian, Rob (15 December 2022). "HS2 Construction progresses on record-breaking Colne Valley Viaduct". New Civil Engineer. Retrieved 29 December 2022.
  26. ^ Pearson, Gavin (9 November 2023). "HS2 | Construction of UK's longest rail bridge reaches halfway point". New Civil Engineer. Retrieved 29 February 2024.
  27. ^ Johnson, Thomas (20 February 2024). "HS2 | Colne Valley Viaduct construction halted for 'urgent remedial works'". New Civil Engineer. Retrieved 29 February 2024.
  28. ^ "Britain gets its new longest rail bridge in major HS2 milestone". HS2. 5 September 2024. Retrieved 5 September 2024.
edit