Hoima–Kinyara–Kafu High Voltage Power Line

The Hoima–Kinyara–Kafu High Voltage Power Line is a planned high voltage electricity power line, connecting the high voltage substation at Kabaale, Buseruka sub-county, Hoima District, in the Western Region of Uganda to another high voltage substation at Kafu, Nakasongola District, in the Central Region of Uganda. On the way, the power line passes through Kinyara Sugar Works, in Masindi District.[1]

Hoima–Kinyara–Kafu High Voltage Power Line
Location
CountryUganda
Coordinates01°25′14″N 31°22′22″E / 1.42056°N 31.37278°E / 1.42056; 31.37278
General directionWest to East
FromHoima, Uganda
ToKafu, Uganda
Ownership information
OwnerGovernment of Uganda
PartnersThe World Bank Group
OperatorUganda Electricity Transmission Company Limited
Construction information
Expected2023
Technical information
Type of currentAC
Total length92 km (57 mi)
AC voltage220kV
No. of circuits2

Location

edit

The power line starts in the village of Kabaale, Buseruka sub-county, Hoima District, in the Western Region of Uganda, at a 220kV substation there. The power line would travel in a general north-easterly direction to the Kinyara Sugar Works, in Masindi District, through another 220kV substation there, and continue on to terminate at Kafu, in Nakasongola District, at a 220kV substation that is connected to the Karuma–Kawanda High Voltage Power Line,[1] a total distance of 92 kilometres (57 mi).[2]

Overview

edit

This power line is intended to increase and strengthen the supply of grid electricity to the Western Region of Uganda. The four main objectives are as follows:

The first objective is to connect the region to the 600 megawatts Karuma Hydroelectric Power Station through the connection at Kafu.[1]

The second objective is to pick up co-generation at Kinyara Sugar Works, where energy production is expected to be stepped up from 14 megawatts to 45 megawatts.[1]

The third objective is to pick up any power from the Hoima oil fields, including the proposed 100 megawatts natural gas-fired Nzizi Thermal Power Station.[1]

The fourth objective is to bring power to the Hoima Metropolis including the Uganda Oil Refinery, the Kabaale International Airport, the city of Hoima and the Ugandan end of the East African Crude Oil Pipeline. At its southern end, in Hoima District, this transmission line will connect to the existing 226 kilometres (140 mi), 220kV Nkenda–Fort Portal–Hoima High Voltage Power Line, which was completed in 2018.[3]

Construction

edit

As of 2018, this power line was marked as "Under Procurement". Funding is expected through a loan from the International Development Association, a member of the World Bank Group.[4]

See also

edit

References

edit
  1. ^ a b c d e NEK Consults Limited (June 2017). "Hoima–Kinyara 220kV Transmission Line And Substations: Hoima–Kinyara Updated ESIA Report" (PDF). Kampala: The World Bank. Retrieved 17 April 2019.
  2. ^ UETCL (2018). "Project Status Brief For PR". Kampala: Uganda Electricity Transmission Company Limited (UETCL). Retrieved 18 April 2019.
  3. ^ UETCL (14 August 2018). "Happening today, commissioning of the Nkenda–Fort Portal–Hoima 220kV transmission line, at the Nkenda Substation in Kasese". Kampala: Uganda Electricity Transmission Company Limited (UETCL) via Twitter.com. Retrieved 18 April 2019.
  4. ^ Uganda Electricity Transmission Company Limited (March 2018). "The Status of the Power Transmission Projects" (PDF). Powerutilityleadership.com. Retrieved 18 April 2019.
edit