Jabban Hydropower Plant

Jabban (Malakand-I) Hydropower Plant (MHPP-I) is a small, low-head, run-of-the-river hydroelectric power generation station having 22 megawatt generation capacity (four units of 5.5 MW each) located at the Jabban area of the Malakand District in the Khyber Pakhtunkhwa province of Pakistan. It is situated on the Swat River. It is about 210 km from Pakistan's capital Islamabad, 45 km from the city of Mardan and 7 km upstream of 20 MW Dargai Hydropower Plant (Malakand-II). It is a small hydel power generating plant constructed and put in commercial operation in July, 1938, generating an average annual yield of 122 million units (GWh) of least expensive electricity.[1][2]

Jabban Hydropower Plant (Malakand-I)
Jabban Hydropower Plant is located in Pakistan
Jabban Hydropower Plant
Location of Jabban Hydropower Plant (Malakand-I) in Pakistan
Official nameJabban Hydropower Plant (Malakand-I)
LocationMalakand District, KPK, Pakistan
Coordinates34°33′26.80″N 71°55′54.14″E / 34.5574444°N 71.9317056°E / 34.5574444; 71.9317056
StatusOperational
Opening dateJuly 1938
Owner(s)Water and Power Development Authority (WAPDA)
Dam and spillways
Type of damrun-of-the-river
ImpoundsSwat River
Jabban Hydropower Plant (Malakand-I)
Operator(s)WAPDA
Commission dateJuly 1938
Turbines4 × 5.5 MW
Installed capacity22 MW
Annual generation122 million units (GWh)

Old Jabban Power Station

edit

Since its commissioning in 1937 with an initial installed capacity of 9.6 MW (3 units of 3.2 MW each), and addition of 10 MW (2 units of 5.0 MW each), Jabban Hydro Electric Power Station generated 5783.314 Gwh of cheap electricity till the last day of its operation on 12 November 2011.

Fire incident

edit

The 70-year-old power house was badly damaged due to a fire incident on 11 December 2006. The extent of damage was such that it was not possible to restore operation of the existing units. Moreover, the plant equipment had already outlived its life. The situation necessitated to carry out rehabilitation of Jabban Hydroelectric Power Station on "fast track basis" by installing new machines of higher efficiency at the same site.

The rehabilitation of the hydropower station was completed in 2013 with a total cost of Rs3.8 billion by the contractor HRL-CCPG JV (Habib Rafique Ltd. (Pakistan) & Central China Power Group China).[2]

Salient technical features

edit
  • Installed capacity: 22 MW (4 Units of 5.5 MW each)
  • Annual net electrical output: 122 GWh
  • Design discharge: 34 m3/s (8.5 m3/s per unit)
  • Rated net: head 76.8 m
  • Generation voltage: 11 kV
  • Transmission voltage: 132 kV

See also

edit

References

edit
  1. ^ Development Portfolio Archived 2014-07-21 at the Wayback Machine. wapda.gov.pk
  2. ^ a b Ongoing Projects Archived 2014-07-22 at the Wayback Machine. WAPDA. Retrieved on 2015-06-20.