Kárahnjúkar Hydropower Plant

(Redirected from Kárahnjúkastífla Dam)

Kárahnjúkar Hydropower Plant (Icelandic: Kárahnjúkavirkjun [ˈkʰauːraˌn̥juːkaˌvɪr̥cʏn]), officially called Fljótsdalur Power Station[1] (Icelandic: Fljótsdalsstöð [ˈfljoutsˌtalsˌstœːθ])[2] is a hydroelectric power plant in Fljótsdalshérað municipality in eastern Iceland, designed to produce 4,600 gigawatt-hours (17,000 TJ) annually for Alcoa's Fjarðaál aluminum smelter 75 kilometres (47 mi) to the east in Reyðarfjörður. With the installed capacity of 690 megawatts (930,000 hp), the plant is the largest power plant in Iceland. The project, named after the nearby Kárahnjúkar mountains, involves damming the rivers Jökulsá á Dal and Jökulsá í Fljótsdal with five dams, creating three reservoirs. Water from the reservoirs is diverted through 73 kilometres (45 mi) of underground water tunnels and down a 420-metre (1,380 ft) vertical penstock towards a single underground power station. The smelter became fully operational in 2008 and the hydropower project was completed in 2009.[3]

Fljótsdalur Power Station
Kárahnjúkar Dam
Kárahnjúkar Dam, looking south.
Kárahnjúkar Hydropower Plant is located in Iceland
Kárahnjúkar Hydropower Plant
Location of Fljótsdalur Power Station
Kárahnjúkar Dam in Iceland
CountryIceland
Coordinates64°56′N 15°48′W / 64.933°N 15.800°W / 64.933; -15.800
StatusOperational
Opening date2009
Dam and spillways
Type of damEmbankment, concrete-face rock-fill dams
ImpoundsJökulsá á Dal
Jökulsá í Fljótsdal
Height193 m (633 ft)
Length730 m (2,400 ft)
Dam volume8.5×10^6 m3 (300×10^6 cu ft)
Spillways1
Spillway typeTunnel
Reservoir
CreatesHálslón Reservoir
Total capacity2.1 km3 (1,700,000 acre⋅ft)
Maximum length25 km (16 mi)
Operator(s)Landsvirkjun
Turbines6 x 115 MW (154,000 hp) Francis-type
Installed capacity690 MW
Annual generation4,600 GWh

The Kárahnjúkar Dam[1] (Icelandic: Kárahnjúkastífla [ˈkʰauːraˌn̥juːkaˌstipla])[2] is the centrepiece of the five dams and the largest of its type in Europe, standing 193 metres (633 ft) tall with a length of 730 metres (2,400 ft) and comprising 8.5 million cubic metres (300×10^6 cu ft) of material.

The project has been heavily criticised for its environmental impact and its use of foreign workers.

Description

edit

The hydroelectricity project harnesses the rivers Jökulsá á Dal and Jökulsá í Fljótsdal by creating three reservoirs with five concrete-face rock-filled embankment dams; three on the Jökulsá á Dal and two on the Jökulsá í Fljótsdal. After being used in the Fljótsdalur Power Station, all water used in electricity production is discharged into the river Jökulsá í Fljótsdal.

 
Kárahnjúkar Dam

Three dams on the Jökulsá á Dal; the Kárahnjúkar Dam (Icelandic: Kárahnjúkastífla), the Desjará Dam[1] (Icelandic: Desjarárstífla)[2] and the Sauðárdalur Dam[1] (Icelandic: Sauðárdalsstífla)[2] create the Hálslón Reservoir. At 193 metres (633 ft) tall and 730 metres (2,400 ft) long, the Kárahnjúkar Dam is the largest dam in the project and the largest of its type in Europe as well. The 60-metre (200 ft) tall and 1,000-metre (3,300 ft) long Desjará Dam and the 25-metre (82 ft) tall and 1,100-metre (3,600 ft) long Sauðárdalur Dam are saddle or auxiliary dams that maintain the desired height of the Hálslón Reservoir. Water from the 25-kilometre (16 mi) long, 2.1-cubic-kilometre (1,700,000 acre⋅ft) capacity Hálslón Reservoir (about the size of Manhattan island in New York) is diverted down a 39.7-kilometre (24.7 mi) long, 7.2–7.6-metre (24–25 ft) diameter headrace tunnel towards the Fljótsdalur Power Station.[4][5]

On the river Jökulsá í Fljótsdal, the 26-metre (85 ft) tall and 1,650-metre (5,410 ft) long Kelduá Dam forms the 60-million-cubic-metre (2.1×10^9 cu ft) capacity Kelduárlón Reservoir. Downstream from the Kelduá Dam is the 37-metre (121 ft) tall, 620-metre (2,030 ft) long Ufsarstífla dam which forms the Ufsarlón, a much smaller reservoir. Water from the Ufsarlón Reservoir is diverted down a 13.3-kilometre (8.3 mi) long, 6-metre (20 ft) diameter headrace tunnel where it joins the Hálslón Reservoir headrace tunnel.[4][5]

Before each of the headrace tunnels from the Hálslón Reservoir or Ufsarlón Reservoir reach the underground power station, they both join to form a single combined headrace tunnel. The single headrace tunnel later splits into two 0.8-kilometre (0.50 mi) long, 4-metre (13 ft) diameter steel-lined penstocks (tunnels) and the water makes a rapid descent down a final 420-metre (1,380 ft) vertical penstock into the power station. The underground Fljótsdalur Power Station contains six vertical-axis Francis turbine generators rated at 115 MW each. The power station has a combined capacity of 690 MW and discharge of 144 cubic metres per second (5,100 cu ft/s) (averages 110 cubic metres per second (3,900 cu ft/s)) into the river Jökulsá í Fljótsdal via tailrace tunnels and canals. The power production of 4,600 GWh/year[4] corresponds to a capacity factor of 76%, which is relatively high for a hydroelectric facility. Power produced is then transmitted to Alcoa's Fjarðaál aluminium smelter 75 kilometres (47 mi) to the east in Reyðarfjörður.[4][5]

Fjarðaál aluminium smelter

edit

The Fjarðaál aluminium smelter was completed June 2007 and reached full operation in April 2008. Construction began in 2004 and the facility contains a smelter, cast house, rod production and deep-water port. The smelter employs 450 people and produces 940 tons of aluminium a day, with capacity of 346,000 metric tons of aluminium per year. Fjarðaál means "Fjords Aluminium" in Icelandic.[5][6]

History

edit

Using the rivers Jökulsá á Dal and Jökulsá í Fljótsdal along with other resources in eastern Iceland has been on the drawing board since the 1970s. From 1975 to 2002, several international companies had planned or attempted to build a metal plant at Reyðarfjörður that would be powered by a hydroelectricity project similar to the Kárahnjúkar. All failed because of opposition to the project until Alcoa along with the Government of Iceland and Landsvirkjun, Iceland's national power company committed to the massive project in 2002.[7]

Construction

edit
 
Construction of Kárahnjúkar Dam, concrete-face backside
 
The end of the tunnel at Skriðuklaustur leading water from Kárahnjúkar Dam to the power plant.

The project is funded by Landsvirkjun, which operates the dams and Fljótsdalur Power Station. The Italian company Impregilo is the largest contractor working on the dams.[8] The total cost of the hydropower project is 1.3 billion USD. The penstock was built in place by the German company DSD-NOELL (Würzburg) whereas ATB Riva Calzoni of Italy provided intake structures, wheels gates and sliding gates. In total, more than 4,000 tons of steel were used for the steel liner.

Preparatory work on the project began in August 2002 and construction on the Kárahnjúkar Dam and headrace tunnels for the Hálslón Reservoir began in April 2003. In September of the same year, construction began on the underground power station. Construction on both the Desjará Dam and the Sauðárdalur Dam began in April 2004. In June 2006, construction of the Kelduá Dam and Ufsarstífla Dam began and in September, the Hálslón Reservoir began to fill. In mid-2008, the Kelduá and Ufsarstífla Dams were complete and the Ufsarlón Reservoir headrace tunnel was ready.[5][9]

Construction on the headrace tunnels was done by three full-face tunnel boring machines, while remaining areas were drilled and blasted.[5] This was the first time that tunnel boring machines were used in Iceland.[10]

There were several workplace fatalities during the construction process including: Arni Thor Bjarnason, Eilifur Gopi Hammond, Ludvik Alfred Halldorsson and Kresimir Durinic.[11]

Criticism

edit

The dams have been the frequent subject of protests by environmentalists for many reasons.[12] The area is within the second largest (formerly) unspoiled wilderness in Europe and covers about 1,000 square kilometres (390 sq mi) in total and the rivers that supply water to the project are part of Europe's largest glacier, Vatnajökull. About 70% of the workforce was composed of foreign workers.[13] For the construction of Kárahnjúkar Hydropower Plant in East Iceland, five dams in two glacial rivers created three reservoirs, that together flooded over 440,000 acres of unspoilt Highland territory. The megastructure is on a scale like nothing the nation has seen before or since and, as such, has been a constant source of protest and controversy due to the landscapes irretrievably lost.[14] The total affected area according to the environmental impact assessment, outlines that a total of 3,000 km2 or 741,316 acres were affected by the project's construction. That is approximately 3% of Iceland's total land mass.[15]

Representation in film and literature

edit

The project as a whole was criticised heavily in the 2006 book Draumalandið[16] and subsequent 2009 documentary Dreamland.[17] The project was documented in a MegaStructures program of the National Geographic Channel, and the Discovery Channel's Extreme Engineering, along with mention in the 2006 Sigur Rós rockumentary Heima (At Home), where the band played at a protest against the building of the dam.[18] The dam has been read as an inspiration for a mysterious dam in Steinar Bragi's horror novel Hálendið.[19]

See also

edit

References

edit
  1. ^ a b c d "Fljótsdalur Power Station". landsvirkjun.com. Landsvirkjun, National Power Company of Iceland. Archived from the original on 13 July 2018. Retrieved 13 July 2018.
  2. ^ a b c d "Fljótsdalsstöð". landsvirkjun.is. Landsvirkjun, National Power Company of Iceland. Archived from the original on 13 July 2018. Retrieved 13 July 2018.
  3. ^ Kárahnjúkar HEP – Landsvirkjun – September 2009 Archived 11 May 2011 at the Wayback Machine
  4. ^ a b c d Key Figures of the Kárahnjúkar Hydroelectric Project Archived 17 June 2011 at the Wayback Machine
  5. ^ a b c d e f The Kárahnjúkar Hydropower Project Overview Archived 17 June 2011 at the Wayback Machine
  6. ^ "Alcoa – Fjarðaál smelter information". Archived from the original on 10 January 2011. Retrieved 2 January 2010.
  7. ^ Large-scale industry in East Iceland Archived 17 June 2011 at the Wayback Machine
  8. ^ The Icelandic contractor Suðurverk hf was the main contractor working on Desjará Dam and Sauðárdalur Dam Karahnjúkar website – Impregilo Archived 27 October 2004 at the National and University Library of Iceland
  9. ^ Kárahnjúkar Construction Schedule Archived 3 March 2006 at the National and University Library of Iceland
  10. ^ "Looking at tunnel roughness 3 April 2008". Archived from the original on 14 June 2011. Retrieved 2 January 2010.
  11. ^ Veal, Lowana (2007) ICELAND: Dam Proves Fatal for Workers, IPS http://www.ipsnews.net/2007/01/iceland-dam-proves-fatal-for-workers/ Archived 24 August 2018 at the Wayback Machine
  12. ^ "Iceland be Damned", Radio Netherlands Archives, February 8, 2003
  13. ^ "Giant dam and smelter boost economy and raise tensions in Iceland". Archived from the original on 8 November 2007. Retrieved 2 January 2010.
  14. ^ "A Complete Guide to Hydroelectric Power Rivers in Iceland".
  15. ^ "Saving Iceland » Dams".
  16. ^ Andri Snær Magnason, Dreamland: A Self-Help Manual for a Frightened Nation. Translated by Nicholas Jones. London: Citizen Press, 2008. Originally published as Draumalandið: Sjálfshjálparbók handa hræddri þjóð. Reykjavík: Mál og menning, 2006.
  17. ^ Þorfinnur Guðnason and Andri Snær Magnason, dir., Draumalandið [Dreamland], Ground Control Productions, 2009.
  18. ^ Nicola Dibben, 'Music and Environmentalism in Iceland', in: Holt, F. and Kärjä, A-V. (eds.), The Oxford Handbook of Popular Music in the Nordic Countries. Oxford: Oxford University Press, 2017: 163-84 (pp. 167-69); ISBN 9780190603908.
  19. ^ Hall, Alaric (2020). Útrásarvíkingar! The Literature of the Icelandic Financial Crisis (2008–2014). Earth, Milky Way: punctum. pp. 107–9, 305. doi:10.21983/P3.0272.1.00. ISBN 978-1-950192-70-0.
edit