Kaiseraugst Nuclear Power Plant

The site for the Kaiseraugst Nuclear Power Plant is located in north-west Switzerland beside the river at Kaiseraugst, a short distance to the east of Basel.

Kaiseraugst Nuclear Power Plant
Map
CountrySwitzerland
LocationKaiseraugst (AG)
Coordinates47°32′24″N 7°44′56″E / 47.54000°N 7.74889°E / 47.54000; 7.74889
StatusProject abandoned
Construction began1974
Commission datenever
OperatorKernkraftwerk Kaiseraugst AG
Power generation
Units planned1 x 1,000 MW

Plans to build and operate the power plant were the subject of increasingly high-profile controversy over many years. The project failed because of bitter and ultimately effective opposition from the local population and because it became a cause célèbre for environmentalist pressure groups in Switzerland and across German speaking central Europe more generally. The matter hit the headlines most powerfully in 1975, with an eleven-week occupation of the site by a large number of people (estimated, initially, at around 15,000 people). The project was finally abandoned in 1988.[1]

History

edit

The local energy generation company, Motor-Columbus, designed the Kaiseraugst Nuclear Power Plant in response to growing electricity consumption in Switzerland. In order to cover the perceived power generation shortfall as quickly as possible, attempts were made to accelerate the planning and authorization phases of the project. For political reasons the intended timetable turned out to be unachievable, however. In the end the planning phase lasted more than twenty years, and by 1988 the project had absorbed 1.3 billion Swiss francs.[1]

 
Protest 1975
 
Demonstration, ca. April 1975
 
Demonstration 1983

Opposition to the Kaiseraugst Nuclear Plant began early in the decade. In May 1970 the first Switzerland-wide organised opposition group to an atomic power plant project, the NAK,[2] was established. It later became better known as the NWA[3][4]

A critical decision of the Federal Court was delivered in July 1973, when it was determined that the municipality of Kaiseraugst and the nearby urban canton of Basel-Stadt could not file a valid complaint against the project with the court. The court held that the constitutional position and the relevant legislation left the federal (i.e. national) state as the sole authorizing body in this case.

The federal authorities examined a range of scenarios, always focused on the need to secure national energy supplies. In the end they endorsed the Kaiseraugst Nuclear Plant, however. After this the project was rejected by many. At that time others saw things differently, however. Nationally the majority in Switzerland supported the use of nuclear power generation.

Outline permission to locate an 850 MW power station at Kaiseraugst was granted on 28 August 1972. There was also provision for repositioning the plant by 600 meters within the site in order to allow for the erection of cooling towers. Concrete project planning began in 1974.[1]

In April 1975 the site for the power plant was occupied by activists. This was the second such occupation, but this time it involved around 15,000 people which was enough to hamper excavation work, which had already started. In the end the start of the construction was delayed this time by eleven weeks as a result of resistance by the demonstrators. Less than four years later, in February 1979, the "Information Pavilion" for the planned nuclear power plant was blown up by militant project opponents. The force of the explosion also lifted into the air an Audi, parked nearby and belonging to Michael Kohn, president of Kernkraftwerke Gösgen AG and initiator of the power plant construction.[5]

On 28 October 1981 the Federal government mandated an upgrade, raising the output of the planned power plant from 900 to 1,000 MW.[1] Between 17 and 25 September 1985, three different reactor types were more closely considered, all three of them variously configured water cooled reactors:[6]

Two years later, in 1987, authorization was given for construction using an air cooled device, although the option of adding cooling towers had to remain open. Finally all the prerequisites were put in place for a comprehensive Emergency Plan, having regard to the Basel region's seismic record. The next stage, which could no longer be deferred, involved selecting a supplier for the reactor. That stage would never be completed, however, because a contract for a reactor was never signed. In 1988 the project was dropped on economic grounds.[1]

According to government figures the total loss to Kernkraftwerk Kaiseraugst AG had reached between 1.1 and 1.3 billion francs.[1]

See also

edit

References

edit
  1. ^ a b c d e f Kernkraftwerk Kaiseraugst. Nichtrealisierung Archived 2016-06-03 at the Wayback Machine. Schweizer Nationalrat, Motion 88.334, eingereicht von Nationalrat Georg Stucky am 3. März 1988 mit Antwort des Bundesrates vom 28. September 1988. Dort Punkt 2.2.6 Die aufgelaufenen Kosten (retrieved 22 July 2008)
  2. ^ Northwest Swiss Action Committee against the Kaiseraugst Nuclkaer Power Plant" ("Nordwestschweizer Aktionskomitee gegen das Atomkraftwerk Kaiseraugst")
  3. ^ Its later name, slightly more succinctly, was the WNorthwest Swiss Action Committee against atomic power plants" ("Nordwestschweizer Aktionskomitee gegen Atomkraftwerke"). The name has subsequently been further simplified to "Nie wieder Atomkraftwerke" [Atomic power plants: never again].
  4. ^ Historisches Lexikon der Schweiz: Antiatombewegung, accessed 30 September 2014.
  5. ^ Beobachter: Der Mythos Kaiseraugst
  6. ^ Archiv zur Geschichte der Kernenergie in der Schweiz (S. 142)