The Krafla geothermal power plant (Icelandic: Kröflustöð [ˈkʰrœplʏˌstœːθ]) is a geothermal power generating facility located in Iceland, close to the Krafla Volcano and the lake Mývatn. With 33 boreholes, it is able to produce 500 GWh of electricity annually, with an installed capacity of 60 megawatts.

Krafla Power Station
Krafla Power Station
Map
CountryIceland
LocationKrafla
Coordinates65°42′13.9″N 16°46′23″W / 65.703861°N 16.77306°W / 65.703861; -16.77306
StatusOperational
Construction began1974
Commission date1977
OwnerLandsvirkjun
Geothermal power station
Wells33
Max. well depth2,222 m (7,290 ft)
Power generation
Units operational2 x 30 MW
Make and modelMitsubishi Heavy Industries
Nameplate capacity60 MW
External links
Websitelandsvirkjun.com
CommonsRelated media on Commons

The construction work started in 1974, but due to volcanic activities in the area, building was slowed. The Krafla power station was officially launched in the early 1977, but was only able to produce at its full 60-megawatt capacity after a second steam turbine was installed in 1996.[1]

Originally the power plant was owned by the government, but was purchased in 1985 and has since been operated by Landsvirkjun (National Power Company).[2] About 15 employees work there full-time.

Geothermal power station details

edit

The Krafla geothermal power plant consists of two 30-megawatt units, with double pressure inlet and dual-flow turbines with 5 steps on each side. It takes its energy from 17 high-pressure production wells with 110 kg/second of 7.7 bar and, due to new technologies, 5 low-pressure production wells with 36 kg/s of 2.2 bar.[1]

The other seven wells are not in use. The turbines consume 52.5 and 17.8 kg/s of high- and low-pressure steam each. If the inlet pressure and the mass flow were raised, the output of each turbine could be increased to 35 megawatts.[3]

One of the additional wells (IDDP-1), which was drilled in the Krafla geothermal reservoir in 1999, is known for being the world's hottest geothermal well, since its borehole reaches magma at its lowest point, with a temperature of 430 °C. The right to use the well is owned by Mannvit.[1]

Project development

edit

The construction work of the Krafla geothermal power plant started in 1974, with trial boreholes,[4] after a contract over two planned units was signed.

After the drilling started, seismic and volcanic activities in the area threatened the building of the power station, like the major volcanic eruptions less than 2 km from the power station away, introducing the possibility that it would never start operating at all. Nevertheless, it was finished in early 1977 and was launched in 1978, though the power plant did not work to its full potential until the seismic and volcanic activities strongly declined in 1984 and further boreholes were drilled. In 1996 even more boreholes were drilled and a second turbine was installed, but Krafla was only able to operate at 60 megawatts in 1999, after the renovations were finished, which mainly consisted of renewing the steam gathering system in order to meet the standards for the double pressure inlet to the turbines and the control and safety system in general.

The two companies which were in charge of the engineering of the Krafla geothermal power station since very early in its developing process were Mannvit and Verkís.[1]

edit

See also

edit

References

edit
  1. ^ a b c d "Krafla Geothermal Power Plant Design & Engineering". Mannvit. Archived from the original on 2023-03-27.
  2. ^ "Krafla Geothermal Station". Landsvirkjun.
  3. ^ Nielsen, Gunnlaugur; Maack, Runólfur; Gudmundsson, Ásgrímur; Gunnarsson, Gunnar Ingi (2000). "Completion of Krafla Geothermal Power Plant" (PDF). Proceedings World Geothermal Congress 2000.
  4. ^ "Krafla Power Station - Landsvirkjun.en". Landsvirkjun. Archived from the original on 2015-09-11. Retrieved 2016-06-29.
edit

  Media related to Krafla power plant at Wikimedia Commons