Lianjiang Nuclear Power Plant

The Lianjiang Nuclear Power Plant (Chinese: 廉江核电站) is a nuclear reactor under construction in Cheban town,[1] Lianjiang, Guangdong province of eastern China. It is planned to house six CAP1000 pressurized water reactors (PWRs),[2] at a projected cost of 130 billion yuan (US$18.1 billion). It will be the first Chinese nuclear plant with cooling towers, to reduce the amount of heat released into the local water.[3]

Lianjiang Nuclear Power Plant
Map
CountryChina
LocationLianjiang, Guangdong
Coordinates21°33′15″N 109°48′25″E / 21.55417°N 109.80694°E / 21.55417; 109.80694
StatusUnder construction
Construction beganSeptember 2022
Construction costCNY130bn (US$18bn)
OwnerState Nuclear Power Technology CORP LTD
OperatorState Nuclear Zhanjiang Nuclear Power CO LTD
Nuclear power station
Reactor typePWR
Power generation
Units planned4 × 1160 MW
Units under const.2 × 1160 MW

Construction

edit

The construction of the first two reactors at the Lianjiang site was approved by China's State Council in September 2022. Excavation work began in the same month.[2] Construction of the first unit began on 29 September 2023. It is planned to begin operation in 2028.[4] Construction of the second unit began on 26 April 2024.[5]

Reactor data

edit
Unit Type Net Capacity Gross Capacity Construction start Operation start
(planned)
Notes
Phase I
Lianjiang 1 CAP1000 1161 MW 1250 MW 27 September 2023 2028 [6]
Lianjiang 2 CAP1000 1161 MW 1250 MW 29 April 2024 [7]
Phase II
Lianjiang 3 CAP1000 1160 MW
Lianjiang 4 CAP1000 1160 MW
Lianjiang 5 CAP1000 1160 MW
Lianjiang 6 CAP1000 1160 MW

See also

edit

References

edit
  1. ^ "Lianjiang nuclear power plant". Global Energy Monitor. August 2023. Retrieved 9 October 2023.
  2. ^ a b "Nuclear power in China". Information Papers: Country Briefings. World Nuclear Association (WNA). August 2023. Retrieved 9 October 2023.
  3. ^ "SPIC begins construction of the Lianjiang nuclear plant in Guangdong (China)". Enerdata. 10 October 2023. Retrieved 2023-10-09.
  4. ^ "Construction of first unit at Lianjiang under way". World Nuclear News. 9 October 2023. Retrieved 2023-10-09.
  5. ^ "Construction starts of second Lianjiang unit". World Nuclear News. 29 April 2024. Retrieved 2024-04-30.
  6. ^ "Lianjiang 1". Power Reactor Information System (PRIS). International Atomic Energy Agency (IAEA). 2024-04-28. Retrieved 26 April 2024.
  7. ^ "Lianjiang 2". Power Reactor Information System (PRIS). International Atomic Energy Agency (IAEA). 2024-04-29. Retrieved 29 April 2024.