Bugoye Hydroelectric Power Station

(Redirected from Mubuku II Power Station)

Bugoye Power Station is a 13 MW (17,000 hp) mini hydroelectric power station in Uganda. In the literature, Bugoye Power Station is sometimes referred to as Mubuku II Power Station.

Bugoye Power Station
Bugoye Hydroelectric Power Station is located in Uganda
Bugoye Hydroelectric Power Station
Map of Uganda showing the location of Bugoye Station.
CountryUganda
LocationBugoye, Kasese District
Coordinates00°18′20″N 30°05′53″E / 0.30556°N 30.09806°E / 0.30556; 30.09806
PurposePower
StatusOperational
Dam and spillways
ImpoundsMubuku River
Bugoye Power Station
Operator(s)TronderEnergi
Commission date7 October 2009
TypeRun-of-the-river
Hydraulic head159 m (522 ft)
Turbines2 Francis turbines
Installed capacity13 MW
Annual generation82 Gwh

Location

edit

The power station is located across the Mubuku River, in Bugoye, Kasese District, in Western Uganda. This location lies in the foothills of the Rwenzori Mountains, close to the border with the Democratic Republic of the Congo. Bugoye lies approximately 19 kilometres (12 mi), by road, north of Kasese, the location of the district headquarters, and the nearest large city.[1]

Overview

edit

The Bugoye Hydropower Project, is a run of the river mini-hydropower installation, with installed capacity of 13 MW. The energy generated is fed into the national electric grid at Nkenda Substation, located 6 kilometres (3.7 mi) from Bugoye, via a 33kV transmission line.

The power station is owned and operated by TronderEnergi, a Norwegian power company. Construction began in March 2008 and the plant was commissioned 19 months later in October 2009.[2] Bugoye Power Station is the third mini-hydropower station on River Mubuku. The other two are Mubuku I Power Station, owned by Kilembe Mines Limited (KML), with installed capacity of 5 MW and Mubuku III Power Station, owned by Kasese Cobalt Company Limited (KCCL), with installed capacity of 10 MW.[3]

Construction costs

edit

The estimated costs for the dam and power plant is approximately US$35 million. The funding was facilitated by a loan from the Emerging Africa Infrastructure Fund, (EAIF). This does not include the construction of a 33kV transmission power line linking the power station to the substation where the power is integrated into the national grid. The power line was funded by a grant from the Government of Norway to the Government of Uganda. By mutual consent between the two governments, Tronder Power Limited, assumed the responsibility of developing, constructing, maintaining and servicing the power line.[4] Tronder Power Limited is a Ugandan company co-owned by TronderEnergi and Norfund.[5]

See also

edit

References

edit
  1. ^ "Map Showing Kasese And Bugoye With Distance Marker". Globefeed.com. Retrieved 4 May 2014.
  2. ^ "Bugoye Plant Operating In Uganda". Water Power Magazine. 11 February 2010. Retrieved 4 May 2014.
  3. ^ B, Masereka. "River Nyamwamba Spills Wrath". New Vision. Archived from the original on 5 May 2014. Retrieved 4 May 2014.
  4. ^ "SEAMS And Bugoye Projects". Emerging Africa Fund. Retrieved 4 May 2014.
  5. ^ "About Tronder Power Limited". Tronder Power Limited. Archived from the original on 8 February 2014. Retrieved 4 May 2014.
edit