The Svinesund Bridge (Norwegian: Svinesundsbrua, Swedish: Svinesundsbron) is a through arch bridge crossing Iddefjord at Svinesund, and joining Sweden and Norway. Svinesund is a sound separating the Swedish municipality of Strömstad from the Norwegian municipality of Halden, and thus it is the border between Norway and Sweden in this region. The bridge is the westernmost border crossing (and one of the southernmost) between the two countries and carries the European route E6 which is a major traffic route in the area, connecting Oslo and the rest of Norway with Gothenburg, Malmö, Copenhagen and the rest of Europe.
Svinesund Bridge | |
---|---|
Coordinates | 59°05′40″N 11°15′06″E / 59.094497°N 11.251800°E |
Carries | Four lanes on European route E6 |
Crosses | Iddefjord at Svinesund |
Locale | Swedish municipality of Strömstad, Norwegian municipality of Halden |
Characteristics | |
Design | Through arch bridge |
Total length | 704 m (2,310 ft) |
Width | 2 vehicular lanes in each direction |
Longest span | 247 m (810 ft) |
Clearance above | total height 92 m (302 ft) above water |
Clearance below | deck 55 m (180 ft) above water |
History | |
Opened | June 10, 2005 |
Location | |
Description of the bridge
editThe New Svinesund Bridge is a highway bridge across the Iddefjord at Svinesund. The bridge's construction cost was NOK 500 million,[1] while the total cost of the project including approach work, customs (this is an EU border) and toll plazas, and new interchanges for E6 (with the old bridge and old E6 becoming local routes) was SEK 1,400 million. The project is a joint venture of the Swedish and Norwegian road authorities, and all costs are to be financed with tolls (some writings refer to them as "road tax") collected. Both bridges were tolled in both directions. The toll plaza stopped on 15. March 2021.[2]
The total length of the bridge is 704 metres (2,310 feet) and consists of a substructure in ordinary reinforced concrete together with a steel box-girder superstructure. The main span of the bridge between abutments is approximately 247 metres (810 feet) and consists of a single ordinary reinforced concrete arch which carries two steel box-girder bridge decks, one on either side of the arch. The level of the top of the arch and the bridge deck are +91.7 metres (301 feet) and +61 metres (200 feet), respectively. Over the part of the bridge where the arch rises above the level of the bridge decking, the two bridge decks are joined by traverse beams positioned at 25.5 metres (84 feet) centres. The traverse beams are in turn supported by hangers to the concrete arch.
Construction notes
editThe bridge was constructed between 2003 and 2005 and was inaugurated on June 10, 2005, and opened for traffic on June, 13 the same year. Unusually for a two hinge concrete arch bridge, the arch was built using cantilever construction supported by temporary cable stays. The bridge was engineered by Bilfinger Berger, who also acted as general contractors.[3]
The two halves of the arch were cast using similar climbing formwork, with concrete provided via a cable conveyor. The construction system had an hydraulic self climbing casting mould which was anchored to the most recently completed arch segment, and segments were added at a rate of about 1 per week (illustration showing process). Each segment used about 60 cubic meters of k70 class concrete, and there were about 50 segments per side. The arch itself is hollow, and has been provided with heating coils to keep it free from ice and snow build up as well as navigation lights and interior maintenance pathways (info taken from this PDF[permanent dead link ] at the joint bridge info site).
Once the arch was in place, the stays, temporary concrete stay towers and cable conveyors were removed, and the roadway segments added. Some were added in place, but the centre roadway section under the arch was floated in on barges, as a complete section, and raised into place.
Old Svinesund Bridge
editThe former Svinesund Bridge, inaugurated on 15 June 1946,[4] 1-kilometre (0.62 mi) to the east, was renamed the Old Svinesund Bridge but is still in service as a complement to the new bridge. Heavy trucks (gross weight exceeding 3,500 kg / 7,700 lb) are no longer permitted on the old bridge now that the new one is available. A significant part of Norwegian trade in goods was carried by trucks crossing the bridge, which now travels on the new bridge.
It was built during the war period 1939–1946. It was delayed because of the war and the fact that it was partly destroyed when lightning ignited explosives (1942), placed on the bridge as a defence measure.
References
edit- ^ Reference Portfolio - New Svinesund Bridge (PDF), AAS - Jakobson, archived from the original (PDF) on 8 August 2014, retrieved 3 August 2014
- ^ "Avslutter bompenger på Svinesund". Statens vegvesen (in Norwegian Bokmål). Retrieved 2021-03-15.
- ^ Majestic arch over the Idefjord
- ^ "Structurae [en]: Eutersdorf Suspension Bridge".
External links
edit- Swedish Road Administration's project site
- PDF[permanent dead link ] on engineering and construction from the above site
- PDF[permanent dead link ] on topography and project profile from the above site
- Old and New Svinesund Bridge on en.broer.no
- Svinesund Bridge (1946) at Structurae
- Svinesund Bridge (2005) at Structurae
- Map at commercial site multimap.com, showing the old and new bridges (new shown as dotted, under construction) and rerouting of E6