The Tartan oil field is a significant crude oil producing field in the UK sector of the North Sea, 187 km north-east of Aberdeen. Production of oil started in 1981 and ceased in 2020, the Tartan Alpha installation is currently (2021) undergoing decommissioning.
Tartan oil field | |
---|---|
Country | United Kingdom |
Region | North Sea |
Location/blocks | 15/16a and 14/20a |
Offshore/onshore | Offshore |
Coordinates | 58°22′11″N 00°04′25″E / 58.36972°N 0.07361°E |
Operators | Repsol Resources UK |
Owner | Repsol Resources UK |
Field history | |
Discovery | February 1975 |
Start of production | January 1981 |
Abandonment | 2020 |
Production | |
Estimated oil in place | 14.1 million tonnes (~ 12.8×10 6 m3 or 80.5 million bbl) |
Recoverable oil | 62 million barrels (~1.1×10 7 t) |
Producing formations | Upper Jurassic sandstone |
The field
editThe Tartan oil field is located in Blocks 15/16a and 14/20a of the UK North Sea continental shelf. Its name continues the Scottish theme of oil fields in the area (eg Claymore, Piper, Scott).[1] The Tartan field was discovered in February 1975 and the oil reservoir comprises an Upper Jurassic sandstone at a depth of 9,800 to 12,000 feet (2,9873 to 3,658 metres).[2] The reservoir and its fluids had the following characteristics:[2]
Parameter | Value |
---|---|
Porosity | 8–18 % |
Permeability | 70–500 md % |
API gravity | 37–40°API |
Gas Oil Ratio | 900 standard cubic feet/barrel |
Sulfur content | 0.7 % |
Pressure/temperature | 4,600–5,700 psi (31,715–39,300 kPa) at 220–240 °F |
Recoverable reserves | 62 million barrels, 14.1 million tonnes |
Owners and operators
editThe initial owner of the field was Texaco North Sea Limited which also operated the field. Talisman assumed ownership in 2000. The company became Talisman Sinopec Energy, then Repsol Sinopec.[3]
Development
editThe field was developed by a single integrated drilling, production and accommodation platform: Tartan Alpha (Tartan A). The principal design data of the Tartan A platform is given in the following table.[2]
Installation | Tartan A |
Coordinates | 58°22’11”N 00°04’25”E |
Water depth, metres | 142 |
Fabrication substructure | McDermott-Hudson, Cherbourg and Methil |
Jacket weight, tonnes | 14,400 |
Topsides design | Lawrence Allison |
Topsides weight, tonnes | 14,100 |
Function | Drilling, production, accommodation |
Accommodation (crew) | 200 |
Type | Steel jacket |
Legs | 4 |
Piles | 28 |
Well slots | 30 |
Throughput oil, barrels per day (bpd) | 75,000 + 14,400 Natural Gas Liquids |
Water injection, bpd | 105,000 |
Platform installed | June 1979 |
Production started | January 1981 |
Oil production to | Claymore |
Gas production to | Frigg pipeline |
Tartan Alpha was originally connected to the Piper Alpha platform through a 19 km 18-inch diameter gas pipeline. The failure of the riser of this pipeline at about 22:20 6 July 1988 during the Piper Alpha disaster led to a second major explosion followed by a widespread fire.[4]
Production from Tartan's faulted reservoir was 'disappointing'. Texaco therefore halted production well drilling on Tartan and focussed on the Highlander field, about 13 km north-west of Tartan, to enable the field to produce through Tartan.[2]
Tartan satellites
editIn addition to its own production several other smaller fields were tied back to Tartan. The design data is summarized below.[5]
Name of field | Highlander | Petronella | Galley | Duart | Tartan North Terrace |
Year installed | 1985 | 1986 | 1998 | 2007 | 2004 |
Distance from Tartan, km | 13 | 11 | 14 | 3.4 | |
Production pipeline, inches | 12 | 8 | 10 | 8 | 6 |
Gas lift pipeline, inches | 8 | 12 | – | – | 3 |
Water injection pipeline, inches | 4 | – | 8 | – | – |
No. of Wells | 1 | 1 | 1 |
Production from the Galley field was originally through the Northern Producer a floating production facility.[6]
Processing
editOil from the wellheads and subsea tie-ins was routed to one of five 1st stage 3-phase (oil, gas, water) separators. Oil flowed from the 1st stage separators to the single 2nd stage separator and from there was pumped through metering streams to the 27 km 24-inch diameter oil export pipeline to Claymore.[5]
Produced water from the separators was treated in a degassing vessel and hydrocyclones to an oil-in-water concentration of less than 30 mg/litre prior to discharge overboard.[5]
Gas from the separators was compressed in the single 5 stage compression train. Gas was treated to remove hydrogen sulfide. Some gas was used to provide lift gas for the wells and the remainder was exported via a 72 km 18-inch pipeline to the Frigg MCP01 bypass line, and thence to St. Fergus.[5]
By 2017 there were 5 Tartan production wells and 1 subsea injection well.[5]
The fluid handling capability of the Tartan facilities in its latter years of operation was as follows:[5]
Treatment facility | Capacity |
---|---|
Crude oil | 30,000 bbls/day |
Gas compression | 40-66 MMSCFD (million standard cubic feet per day) |
Dehydration | 70 MMSCFD |
Gas sweetening | 70 MMSCFD |
Decommissioning
editRepsol Sinopec were granted a Cessation of Production authorisation by the UK Oil and Gas Authority in August 2020.[7] Repsol Sinopec have submitted decommissioning plans to the Oil and Gas Authority, and are undertaking decommissioning of the Tartan installation and its associated infrastructure.[8]
References
edit- ^ Department of Trade and Industry (1994). The Energy Report. London: HMSO. pp. 88 and map 8. ISBN 0115153802.
- ^ a b c d Oilfield Publications Limited (1985). The North Sea Platform Guide. Ledbury: Oilfield Publications Limited. pp. 641–46.
- ^ "Tartan Oil Field". abarrelfull. Retrieved 18 October 2021.
- ^ "Safety of offshore oil and gas operations: Lessons from past accident analysis" (PDF). publications.jrc.ec.eur. 2012. Retrieved 18 October 2021.
- ^ a b c d e f Repsol Sinopec. "Tartan A: Infrastructure Code of Practice" (PDF). repsolsinopecuk.com. Retrieved 18 October 2021.
- ^ "Galley oil field". abarrelfull. Retrieved 18 October 2020.
- ^ "Repsol Sinopec calls time on Tartan Alpha after 40 years". Energy Voice. 2020. Retrieved 18 October 2021.
- ^ Oil and Gas Authority. "Decommissioning Project summary". Retrieved 18 October 2021.