Umsinde Emoyeni Wind Power Station

The Umsinde Emoyeni Wind Power Station (UEWPS), is a 140 MW wind power plant under construction in South Africa. The power station is under development by a consortium comprising (i) African Clean Energy Developments (ACED) and (ii) Energy Infrastructure Management Services (EIMS Africa). Both entities are subsidiaries of African Infrastructure Investment Managers (AIIM), an asset manager entity headquartered in Cape Town, South Africa.[1][2]

Umsinde Emoyeni Wind Power Station
Map
CountrySouth Africa
LocationMurraysburg, Beaufort West
Central Karoo District
Western Cape Province
Coordinates31°50′56″S 23°49′32″E / 31.84889°S 23.82556°E / -31.84889; 23.82556
StatusUnder construction
Construction beganJune 2024
Commission dateQ4 2026 Expected
OwnerAfrican Infrastructure Investment Managers (AIIM)
Operator"Umsinde Emoyeni Power Consortium"
Wind farm
TypeOnshore
Power generation
Nameplate capacity140 MW

The power generated here is intended for sale to Sibanye-Stillwater, the South African mining conglomerate, to support its gold, platinum-group elements and related metals mining operations in South Africa. The power will be transmitted from the wind farm to the off-taker by Eskom, the national electricity utility company under a 20-year power purchase agreement (PPA) and a long-term "wheeling agreement".[1][2]

Location

edit

The power station is located near the town of Murraysburg, in Beaufort West, in Central Karoo District in extreme northeastern Western Cape Province, close to its border with the Northern Cape Province of South Africa.[1] Murraysburg is located approximately 619 kilometres (385 mi), by road, northeast of Cape Town, the provincial capital.[3]

Overview

edit

The design calls for a wind farm with generation capacity of 140 megawatts.[1][2]

Developers

edit

The table below illustrates the ownership of this power station. The owner(s) are expected to form a special purpose vehicle (SPV) company to own, design, fund, build, operate and maintain the wind farm. For descriptive purposes, we will refer to the SPV company as Umsinde Emoyeni Power Consortium.[1][2][4]

Shareholding In Umsinde Emoyeni Power Consortium
Rank Shareholder Domicile Percentage Notes
1 African Clean Energy Developments (ACED) South Africa [1][2][4]
2 Energy Infrastructure Management Services (EIMS Africa) South Africa [1][2][4]
3 Reatile Renewables Pty Limited South Africa [4]
Total 100.00

Funding and time table

edit

African Infrastructure Investment Managers (AIIM) are funding the renewable energy project. AIIM is the parent entity of the two main shareholders, ACED and EIMS Africa. The project received financial support from Old Mutual Alternative Investments (OMAI)’s IDEAS Fund and from a syndicated loan arranged by Rand Merchant Bank.[4] Construction is expected to start in June 2024 with commercial commissioning planned in the fourth quarter of 2026.[1][2][4]

Other considerations

edit

With the attainment of financial closure for Umsinde Emoyeni Wind Farm, Sibanye-Stillwater has attained 407 MW of green renewable energy for its exclusive use, in its decarbonization and greening efforts. The 407 MW mitigates 24 percent of the miner's carbon footprint, equivalent to approximately 1,450,000 tonnes of CO2 annually, beginning in January 2027. Sibanye-Stillwater still plans to increase this portfolio of renewable green power sources to 600 MW, as it progresses towards total carbon neutrality by 2040.[5]

See also

edit

References

edit
  1. ^ a b c d e f g h Jean Marie Takouleu (6 June 2024). "South Africa: Mining Company Sibanye Signs For 140 MW of Wind Energy". Afrik21.africa. Paris, France. Retrieved 6 June 2024.
  2. ^ a b c d e f g MRA (31 May 2024). "Sibanye-Stillwater secures fourth renewable energy deal with 140MW wind project". Mining Review Africa (MRA). Rondebosch, Cape Town, South Africa. Retrieved 6 June 2024.
  3. ^ "Road Distance Between Murraysburg, South Africa And Cape Town, South Africa" (Map). Google Maps. Retrieved 6 June 2024.
  4. ^ a b c d e f "SA Mining Firm Sibanye Concludes PPA For 140MW Wind Farm". RenewAfrica.Biz. Cape Town, South Africa. 3 June 2024. Retrieved 6 June 2024.
  5. ^ "Sibanye-Stillwater Secures 140MW Wind Energy Project". BizCommunity.com. Cape Town, South Africa. 30 May 2024. Retrieved 6 June 2024.
edit