Vermont Yankee Nuclear Power Plant

Vermont Yankee was an electricity generating nuclear power plant, located in the town of Vernon, Vermont, in the northeastern United States. It generated 620 megawatts (MWe) of electricity at full power. The plant was a boiling water reactor (BWR), designed by General Electric. It operated from 1972 until December 29, 2014, when its owner Entergy shut down the plant. In 2008, the plant provided 71.8% of all electricity generated within Vermont, amounting to 35% of Vermont's electricity consumption. The plant is on the Connecticut River, upstream of the Vernon, Vermont Hydroelectric Dam and used the reservoir pool for its cooling water.

Vermont Yankee Nuclear Power Plant
Map
Country
  • United States
LocationVernon, VT
Coordinates42°46′44″N 72°30′47″W / 42.77889°N 72.51306°W / 42.77889; -72.51306
StatusNo longer operating as of December 29, 2014
Commission dateNovember 30, 1972
Decommission date
  • 29 December 2014
OperatorEntergy
Nuclear power station
Reactor typeBWR-4/Mark I containment
Reactor supplierGeneral Electric
Cooling sourceConnecticut River
Power generation
Nameplate capacity620 MW
Annual net output5,060 GWh (2014)
External links
Websitewww.safecleanreliable.com
CommonsRelated media on Commons

In March 2012, the plant's initial 40-year operating license was scheduled to expire; in March 2011, the Nuclear Regulatory Commission (NRC) extended its license for another 20 years. Vermont Yankee's continued operations were complicated by the Vermont state legislature's enactment of a law providing the state legislature authority to determine the continued operation of the plant, in addition to the federal government. Entergy requested a new state certificate of public good (CPG),[1] but the Vermont legislature voted in February 2010 against renewed permission to operate. In January 2012, Entergy won a court case, invalidating the state's veto power on continued operations. In August 2013, Entergy announced that due to economic factors Vermont Yankee would cease operations in the fourth quarter of 2014. The plant was shut down at 12:12 pm EST on December 29, 2014.

Since the 1970s, there have been many anti-nuclear protests about Vermont Yankee, including large protests after the Fukushima nuclear disaster in March 2011, and on the date of the original operating license expiry in March 2012. The plant's initial operating license from the Nuclear Regulatory Commission was the subject of a lawsuit that produced the U.S. Supreme Court's 1978 decision Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., in which the Supreme Court set forth a significant doctrine in American administrative law.

Design and function

edit
 
Electricity generation sources for Vermont

Vermont Yankee was a BWR-4 Boiling water reactor that used a Mark I containment structure. It provided 71.8% of all electricity generated in Vermont in 2008[2] and met 35% of the overall electricity requirements of the state.[3]

It was originally designed and constructed for 500 MW electrical output. In 2006, it was upgraded to 620 MW electrical output. The reactor produces 1912 MW of heat which is converted to electricity at 32% efficiency.[4] In comparison, the average residential power demand for all of Vermont in 2012 was 239 MW.[5] The nearby Northfield Mountain hydroelectricity facility was built to balance the supply from Yankee.[6]

The reactor core held up to 368 fuel assemblies and 89 control rods.[7] The spent fuel pool is licensed to contain up to 3353 spent fuel assemblies.[7]

Ownership and operational license

edit

In 1978, the Vermont Yankee reactor was the subject of Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., an important United States Supreme Court administrative law case which ruled that courts cannot impose procedures upon the NRC as this exceeds their power of judicial review.

On July 31, 2002, Entergy Nuclear Vermont Yankee, LLC (EVY) purchased the plant from Vermont Yankee Nuclear Power Corporation (VYNPC) for $180 million. Entergy received the reactor complex, nuclear fuel, inventories, and related real estate, as well as the liability to decommission the plant and related decommissioning trust funds of approximately $310 million. The acquisition included a 10-year power purchase agreement (PPA) under which three of the former owners committed to purchase a portion of the electricity produced by the reactor at a cost of approximately 4.5 cents per kilowatt hour.[8]

On May 6, 2006, Vermont Yankee achieved its power of 1,912 MWth (120% of its original licensed thermal power of 1,593 MW-thermal) because of an NRC approved Extended Power Uprate. The power increase was carried out in steps to allow collection of data on the reactor's steam dryer at various power levels, in accordance with the NRC imposed power ascension test plan.[citation needed]

As of 2008, Vermont Yankee employed about 600 people including those in the corporate office on Old Ferry Road in Brattleboro, Vermont.[9]

Cooling water

edit

Vermont Yankee used the Connecticut River as its source of cooling water for its two major water systems: the circulating water system and the service water system. The circulating water system removed heat from the power generation process of the plant by cooling the plant's main condenser. The service water system cooled both safety and non-safety related auxiliary components in the nuclear facility and the turbine facility of the plant, and absorbed decay heat from the reactor's cooling systems in emergencies or in times when the reactor was shut down.[citation needed]

Electricity Production

edit
Generation (MWh) of Vermont Yankee Nuclear Power Plant[10]
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual (Total)
2001 391,996 355,360 357,555 328,187 129,478 372,189 379,097 371,824 365,191 384,957 378,276 357,010 4,171,120
2002 392,352 343,305 349,713 338,459 209,953 372,559 372,809 365,720 349,961 93,192 380,204 394,389 3,962,616
2003 394,170 343,479 393,094 380,067 387,278 368,768 370,028 377,983 308,413 353,639 378,082 389,151 4,444,152
2004 392,688 366,832 391,126 36,007 319,916 209,343 287,777 367,658 360,891 376,536 368,682 380,564 3,858,020
2005 365,760 344,961 380,316 327,910 378,106 358,865 326,287 360,452 352,417 265,384 227,835 383,254 4,071,547
2006 383,337 343,081 400,542 420,472 440,374 445,119 455,681 441,760 432,747 462,863 415,434 465,113 5,106,523
2007 463,654 414,710 458,386 412,847 171,302 337,130 449,454 346,130 302,751 432,845 450,832 463,687 4,703,728
2008 466,966 435,128 457,370 421,705 454,881 426,840 353,682 450,462 416,093 254,854 296,627 460,445 4,895,053
2009 449,448 419,364 466,954 452,122 456,763 414,275 453,608 444,490 439,241 463,967 433,515 466,861 5,360,608
2010 456,042 420,181 462,455 340,785 34,419 435,183 444,665 444,971 429,442 464,870 382,329 467,131 4,782,473
2011 466,848 417,284 465,773 449,890 450,521 441,959 438,847 438,452 381,453 94,610 396,824 464,894 4,907,355
2012 443,053 411,053 395,624 378,059 436,234 325,610 424,496 427,807 424,508 438,158 427,969 456,767 4,989,338
2013 448,263 386,804 110,854 355,626 457,416 438,579 445,367 441,562 394,036 455,128 448,496 464,196 4,846,327
2014 455,960 402,047 462,717 436,190 460,551 425,399 445,611 445,824 420,652 412,030 372,080 321,521 5,060,582
2015 -- -- -- -- -- -- -- -- -- -- -- -- 0

Closure/extension planning

edit

Entergy Vermont Yankee applied to the Nuclear Regulatory Commission for a license extension of 20 years on January 27, 2006.[11] In early 2010, the Vermont State Senate voted 26–4 to block the Vermont Public Service Board (PSB) from considering continued operation of Vermont Yankee.[12]

On March 10, 2011, the NRC voted to conclude proceedings regarding renewal of the operating license for the Vermont Yankee Nuclear Power Station near Brattleboro, Vermont, for an additional 20 years.[13] On March 21, 2011, the Nuclear Regulatory Commission issued their renewal of the operating license for the Vermont Yankee plant for an additional 20 years.;[14] the renewed license will expire March 21, 2032.

On April 14, 2011, Entergy, the owner of Vermont Yankee, sued the state of Vermont to stay open despite the Senate's blocking vote.[15][16]

On August 14, 2013, the United States Court of Appeals for the Second Circuit ruled, upholding a lower court's decision that allowed the Vermont Yankee plant to keep running despite a seven-year effort by the Vermont Legislature to close it, finding that states are "pre-empted" from regulating safety by the Atomic Energy Act of 1946, which made safety a federal responsibility.[17]

On August 28, 2013, Entergy announced that due to economic factors, notably the lower cost of electricity provided by competing natural gas-fired power plants, it would cease operations and schedule the plant's decommissioning in the fourth quarter of 2014.[18] Vermont Yankee was shut down at 12:12 pm EST on December 29, 2014.[19] All fuel in the reactor was transferred to the spent fuel pool by January 12, 2015. By August 2018, all VY's remaining spent nuclear fuel was relocated from the spent fuel pool into in dry fuel storage casks.[20][21]

In December 2014, Entergy submitted the Post Shutdown Decommissioning Report to the Nuclear Regulatory Commission. This report estimated that the total cost for decommissioning the reactor would be $1.24 billion. The same document reported that only $665 million had been collected in the 42 years of operations of this plant for this purpose. Entergy hopes to raise some of the shortfall funds through "external financing".[22]

On September 28, 2016, Entergy began auctioning off more than 1,000 lots of goods in Brattleboro, Vt.[23]

Two cooling towers were demolished in July 2019.[24]

Controversy and operations

edit

2007

edit

Cooling for the plant's steam condenser was provided by circulating water through it, drawn from the adjacent Connecticut river. This water did not come in contact with the nuclear reactor and was not radioactive. The cooling towers were used to cool water returning from the condenser before it was discharged back into the river at times when it was too warm to comply with the environmental discharge permit. In 2007 the fourth cell of the west cooling tower collapsed, spilling some of the non-radioactive, cooling water.[25] The collapse was an "industrial safety event," which did not threaten the integrity of the reactor or release any radiation into the environment. The NRC stated that the remaining cooling tower had enough capacity to allow the plant to operate at full output, however, until September 16, 2007, the reactor was kept at 50% power.

The cause of the collapse was found to be corrosion in steel bolts and rotting of lumber. Entergy asserted that future inspections would be much more stringent in order to prevent further problems.

2008

edit

The cooling tower collapse caused Vermont's then governor, Jim Douglas, to question the reliability of the power station:[26] In March 2008, a State Senate committee recommended that the Legislature appoint a panel to oversee an independent review of the plant's reliability. The panel gave Vermont Yankee a generally positive review. "What this report suggests to me is there is not a cause or reason to seek the closure of the plant because of operational or safety concerns," said Public Service Commissioner, David O'Brien.[27]

The Nuclear Regulatory Commission performed a tri-annual inspection July–August 2008. It found three "minor faults." An Associated Press report said that it had won "high marks."[28]

2009

edit

In May 2009, the vice-president of operations at Vermont Yankee told the PSB during the reliability review that he did not believe there was any radioactively contaminated underground piping at the plant, but that he would check and respond to the panel.[29] In October 2009, Arnold Gundersen, a member of a special oversight panel convened by the Vermont General Assembly, confirmed that radioactive contamination had been detected in underground pipes. An Entergy spokesperson told Vermont Public Radio (VPR) that the earlier testimony was a "miscommunication."[29] On June 4, 2010, VPR reported that, because they had provided misleading information, Entergy Nuclear would be liable for legal expenses incurred by certain parties.[30]

2010

edit

In January 2010, the Vermont Department of Health reported that tritium, a radioactive isotope of hydrogen, had been discovered in a sample of ground water taken from a monitoring well the previous November.[31] The level of the isotope was initially below the acceptable limit for drinking water set by the Environmental Protection Agency.[32] By mid-January, however, the level had risen to 20,000 picocuries per liter (pCi/L), the federal limit for drinking water. The head of the Nuclear Regulatory Commission told Vermont's congressional delegation that the agency would devote more resources to addressing concerns about Vermont Yankee, and that he expected the source of the tritium leak would be located within the next several weeks.[33]

On February 4, 2010, Vermont Yankee reported that ground water samples from a newly dug monitoring well at the reactor site were found to contain about 775,000 pCi of tritium per liter (more than 37 times the federal limit). On February 5, 2010, samples from an underground vault were found to contain 2.7 million pCi/L.[34] On February 14, 2010, the source of the leak was found to be a pair of steam pipes inside the Advanced Off-Gas (AOG) pipe tunnel. The pipes were repaired, stopping the leak.[31]

Samples taken from the river and other drinking water sources by the Vermont Department of Health showed no detectable levels of tritium.[35] The New Hampshire Department of Health and Human Services made a similar statement after several tests of the river.[36]

During the search for the source of the tritium leak, other radionuclides were found in the soil at the site. Levels of cesium-137 were found to be three to ten times higher than background levels. Silt in a pipe tunnel contained 2,600 picocuries/kg, but contamination outside the pipe tunnel was limited to a small volume, about 150 cubic feet (4.2 m3) of soil. According to the Vermont State Department of Health, there was no health risk from the cesium, as the quantities were small and it had not migrated.[35]

Since cesium-137 is a fission product, it is an indicator of a nuclear fuel leak, but the consensus was that the cesium-137 probably leaked from defective fuel assemblies during or prior to 2001, when the last leak of that type was reported by Vermont Yankee. (Problems with fuel rods were common in the 1970s and 1980s.)[37]

On May 20, 2010, the NRC released a report on Vermont Yankee:

Based on the results of this inspection, the NRC determined that Entergy-Vermont Yankee (ENVY) appropriately evaluated the contaminated ground water with respect to off-site effluent release limits and the resulting radiological impact to public health and safety; and that ENVY complied with all applicable regulatory requirements and standards pertaining to radiological effluent monitoring, dose assessment, and radiological evaluation. No violations of NRC requirements or findings of significance were identified.[38]

In early November 2010, a water leak[39] caused by a faulty weld caused a "conservative" four-day shutdown while the pipe involved was repaired. A company spokesman said that "if plant managers had known on Sunday night what they knew on Monday, they might have tried to fix the leak while the plant kept running."[40]

In 2010, Vermont Electric Power Company constructed a new substation, designated as the Vernon Substation, on the Vermont Yankee site to serve as the site's new main transmission facility and to connect a new 345 kV transmission line to Central Vermont as part of its Southern Loop project. The aging Entergy-owned Vermont Yankee substation could not handle the additional line or any additional transformers and VELCO desired to have a utility owned and controlled substation for what is probably the state's most important interconnection point. Additionally, the local 115 kV system was relying exclusively on Entergy's single 345 kV to 115 kV transformer. The construction of the Vernon substation included a second 345 kV to 115 kV transformer to supplement the existing Entergy owned transformer. The additional transformer also provided redundancy for Vermont Yankee's source of offsite power. The four transmission lines that formerly connected directly to the Vermont Yankee substation now connect to the Vernon substation, and three tie-lines, one at 115 kV and two at 345 kV, connect the Vermont Yankee substation to the Vernon substation. Each 345 kV tie line is capable of carrying the full power output of the plant.

2011

edit

During the week of January 17, 2011, tritium was detected at a level of 9,200 picocuries per liter (below the federally required reporting level) in an area 150–200 feet north of the location where it was detected a year earlier. According to the State's radiological health chief at the Vermont Health Department, Bill Irwin, and Vermont Yankee spokesman, Larry Smith, the source of the leak was not yet known. Irwin and Governor Peter Shumlin expressed concern about the discovery.[41]

2012

edit

On January 19, 2012, Judge J. Garvan Murtha of United States District Court in Brattleboro ruled that the state of Vermont could not force Vermont Yankee to close down, as the legislation that attempted to do so was based on radiological safety arguments that are the exclusive concern of the NRC. The judge also held that the state cannot force the plant's owner, Entergy, to sell electricity from the reactor to in-state utilities at reduced rates as a condition of continued operation.[42]

2013

edit

On June 7, 2013, Vermont's Public Service Board issued Entergy a Certificate of Public Good to install an outdoor diesel generator to replace a tie line from the nearby hydroelectric station as its station blackout power source. The outdoor generator would only operate if the plant's main emergency diesel generators located inside the turbine building were to fail. The outdoor generator is a self-contained unit that does not require cooling water from the plant's cooling water systems. The new generator would power instrumentation in the control room and would be capable of providing emergency AC power to one train of each of the plant's emergency cooling systems.[43] On August 27, 2013, Entergy announced in a press release that it would close Vermont Yankee by the end of 2014. Among the reasons cited for the closure were ongoing low energy prices resulting from increased shale gas production, and the high operating costs of the plant.[44]

Protests and politics

edit

In 1971, Esther Poneck led the New England Coalition on Nuclear Pollution in opposing construction of Vermont Yankee. In the 1970s and 1980s there were many anti-nuclear protests at Vermont Yankee which attempted to block access to the plant.[45] More recent protests include:

  • January 2006: 100 anti-nuclear supporters demonstrated at the front door of Entergy Nuclear, and eleven people were arrested for trespassing.[46]
  • April 2009: About 150 activists marched from Montpelier's City Hall to the State House to urge lawmakers to back development of renewable energy sources such as wind power and solar power; the marchers had gathered 12,000 signatures in support of closing Vermont Yankee.[47]
  • January 2010: A coalition of anti-nuclear activists participated in a 126-mile walk from Brattleboro to Montpelier in an effort to block the re-licensing of Vermont Yankee. About 175 people took part in the March, some joining for the day and some for longer stretches.[48]

In February 2010, the Vermont Senate voted 26 to 4 against allowing the PSB to consider re-certifying the Vermont Yankee Nuclear Plant after 2012, citing radioactive tritium leaks, misstatements in testimony by plant officials, a cooling tower collapse in 2007, and other problems.[49] Some businesses in Vermont were concerned there was an absence of a clear plan to replace the electricity generated by the plant. A spokesman for IBM, the largest private employer in the state, and the state's largest consumer of electricity, said "we have to be smarter than this".[50] Larry Reilly, president of Central Vermont Public Service Corp., Vermont's largest utility, stated in 2011 that he was untroubled by the prospect of closure: "There's plenty of power out there"."[51] Analysis by researchers at the University of Vermont estimated that an increase of "slightly more than 3 percent" in the retail price of electricity in Vermont would result from closing Vermont Yankee.[4]

Ex-Governor Peter Shumlin was a prominent opponent of the Vermont Yankee. Two days after Shumlin was elected governor in November 2010, Entergy sought offers to purchase the plant.[52] The company withdrew the plant from consideration for sale in late March 2011.[53]

In March 2011, 600 people gathered for a weekend protest outside the Vermont Yankee plant, in the wake of the Fukushima I nuclear accidents.[54] On March 22, 2011, the day after the NRC issued Vermont Yankee's license extension, Vermont's congressional delegation, Senator Patrick Leahy (D), Senator Bernie Sanders (I), and Representative Peter Welch (D), issued a joint statement decrying the NRC's action and noting the similarity of Vermont Yankee to units then in partial meltdown at the Fukushima Daiichi power station, Japan.[55]

In March 2012, more than 130 protesters were arrested at the corporate headquarters of the Vermont Yankee nuclear power plant, on the first day of the plant's operation after the expiration of its original 40-year license.[56]

In March 2013, more than 500 people, carrying banners and chanting "shut it down", marched through downtown Brattleboro in protest against Vermont Yankee.[57]

Seismic risk

edit

The Nuclear Regulatory Commission's estimate of the risk each year of an earthquake intense enough to cause core damage to the reactor at Vermont Yankee was 8.1×10−06 per year, or a chance of one incident occurring on average every 123,000 years, according to an NRC study published in August 2010, based upon a 2008 USGS survey.[58][59]

Surrounding population

edit

The Nuclear Regulatory Commission defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16 km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80 km), concerned primarily with ingestion of food and liquid contaminated by radioactivity.[60]

The 2010 U.S. population within 10 miles (16 km) of Vermont Yankee was 35,284, an increase of 1.4 percent in a decade, according to an analysis of U.S. Census data. The 2010 U.S. population within 50 miles (80 km) was 1,533,472, an increase of 2.9 percent since 2000. Cities within 50 miles include Brattleboro (6 miles to city center); Keene, N.H., (16 miles to city center); Fitchburg, Mass., (38 miles to city center), Greenfield, Mass., and Northampton, Mass.[61]

From April 2016, due to the continuing decommissioning process, the emergency planning zone was reduced to the site boundaries.[62]

See also

edit

References

edit
  1. ^ "Entergy: No need to plan for VY closing". Burlingtonfreepress.com. December 4, 2012.[permanent dead link]
  2. ^ Vermont Nuclear Profile Energy Information Administration, September 2010.
  3. ^ "US Nuclear Plants; Vermont Yankee". Energy Information Administration. March 18, 2005. Archived from the original on February 8, 2001. Retrieved March 15, 2007.
  4. ^ a b Richard Watts, Paul Hines, Jonathan Dowds, "The Debate over Re-Licensing the Vermont Yankee Nuclear Power Plant", The Electricity Journal, Volume 23, Issue 4, May 2010, Pages 59–67, ISSN 1040-6190, doi:10.1016/j.tej.2010.04.005.
  5. ^ U.S. Energy Information Administration. "2012 Average Monthly Bill- Residential". Retrieved October 6, 2014. From EIA: 309019 customers * 565 kWh / month*customer. To find average: * 12 months/1 year * 1 year/366 days (2012 was leap year) * 1 day / 24 hours =~ 238518 kW
  6. ^ Gellerman, Bruce (December 2, 2016). "New England's Largest Battery Is Hidden Inside A Mass. Mountain". www.wbur.org. WBUR-FM. Retrieved December 13, 2017. When this facility was built, it was actually the largest pumped storage facility in the world. Vermont Yankee being a nuclear power plant generates power 24/7, or what they call base load," Bakas says. "So as a result of that at night they had all this excess power on the grid. So somebody needed to take it. So this plant was conceived and built to take that off-peak power and utilize it through pumping water during off-peak periods.
  7. ^ a b Facility Operating License – Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station), Docket No. 50-271, License No. DPR-28 Amendment No. 5, 208, US Nuclear Regulatory Commission, July 31, 2002
  8. ^ Smith, Robert (September 1, 2002). "Vermont Yankee finally sold to Entergy". Vermont Business Magazine. Archived from the original on April 9, 2005. Retrieved March 26, 2009.
  9. ^ Cosgrove, Brian, a spokesman for Entergy (July 1, 2008). "Entergy is vital to future of state". The Burlington Free Press.{{cite news}}: CS1 maint: multiple names: authors list (link)
  10. ^ "Electricity Data Browser". www.eia.gov. Retrieved January 8, 2023.
  11. ^ "Vermont Yankee Nuclear Power Station – License Renewal Application". Nuclear Regulatory Commission. February 27, 2007. Retrieved March 15, 2007.
  12. ^ "Senate votes to close Vermont Yankee nuclear plant in 2012". Burlington Free Press. February 24, 2010. Archived from the original on January 19, 2013. Retrieved June 2, 2011.
  13. ^ "NRC Will Renew Vermont Yankee Operating License for an Additional 20 Years" (PDF). NRC. March 10, 2011. Retrieved March 21, 2011.
  14. ^ NRC license renewal letter March 22, 2011
  15. ^ "Vermont Yankee Nuclear Plant Owner Entergy Sues State To Stay Open". Huffington Post. April 18, 2011. Retrieved May 16, 2011.
  16. ^ Democracy Now news April 19, 2011
  17. ^ Wald, Matthew L. (August 14, 2013). "Appeals Court Blocks Attempt by Vermont to Close a Nuclear Plant". The New York Times.
  18. ^ "Entergy to Close, Decommission Vermont Yankee" (Press release). PR Newswire.
  19. ^ StarTribune.com, Wilson Ring Vermont Yankee nuclear power plant ends operations after 42 years of producing electricity Archived December 29, 2014, at the Wayback Machine, December 29, 2014
  20. ^ Power Magazine, Aaron Larson Vermont Yankee Nuclear Power Plant Shuts Down for the Last Time, December 29, 2014
  21. ^ Dillon, John (August 3, 2018). "Vermont Yankee Moves Last Of Its Spent Nuclear Fuel Into On-Site Storage Casks". Vermont Public. Retrieved April 4, 2024.
  22. ^ Brattleboro Reformer Newspaper, Robert Audette [1] Archived June 7, 2015, at the Wayback Machine, December 19, 2014
  23. ^ "$20M worth of items from Vermont Yankee up for auction". Retrieved September 28, 2016.
  24. ^ VTDigger: "Cooling towers coming down, marking the ‘end of an era’" 11 July 2019
  25. ^ Dale E. Klein (October 31, 2007). "Letter to Senator Kennedy" (PDF). Nuclear Regulatory Commission. Retrieved March 10, 2012.
  26. ^ Governor Urges NRC to Approve Independent Safety Assessment Archived November 10, 2010, at the Wayback Machine
  27. ^ Slota, Bianca (March 17, 2009). "Oversight Panel Gives Yankee Go-Ahead". WCAX News. Archived from the original on November 24, 2011. Retrieved March 18, 2009.
  28. ^ Gram, Dave (September 27, 2008). "Vt. Yankee passes review". The Burlington Free Press.
  29. ^ a b Barlow, Daniel (February 2, 2010). "Backtracking and in trouble: A detailed timeline on who said what on Vt. Yankee". Barre-Montpelier Times-Argus. Archived from the original on April 25, 2015. Retrieved April 7, 2010.
  30. ^ "Groups That Challenged Vermont Yankee To Be Reimbursed". Vermont Public Radio. June 7, 2010. Retrieved March 16, 2011.
  31. ^ a b "Investigation into Tritium Contamination at Vermont Yankee Nuclear Power Station". Healthvermont.gov. July 18, 2016.
  32. ^ Gram, Dave (January 7, 2010). "Vt. Yankee Well Tests Shows Radioactive Isotope". Montpelier, Vermont. Associated Press. Retrieved January 11, 2010.
  33. ^ "Delegation ask NRC for assurances on Vermont Yankee". The Burlington Free Press. January 27, 2010. Retrieved January 27, 2010. [dead link]
  34. ^ "Vermont Yankee zeroes in on possible source of leak". Burlington Free Press, February 6, 2010 [dead link]
  35. ^ a b laboratory_testing. Healthvermont.gov. Retrieved on April 12, 2014.
  36. ^ "Final 6-4-10.pub" (PDF).
  37. ^ ""Plant tests pointing to failed fuel rods," Rutland Herald, April 5, 2010". Rutlandherald.com. Archived from the original on April 8, 2010. Retrieved April 4, 2010.
  38. ^ "Vermont Yankee Nuclear Power Station - Ground Water Monitoring Inspection Report 05000271/2010006". Retrieved May 28, 2010.[permanent dead link]
  39. ^ Josh Stilts (October 8, 2010). "VY closed to fix leak". Brattleboro Reformer. Retrieved October 8, 2010.
  40. ^ Wald, Matthew L., "Vermont Yankee Reactor Restarts" The New York Times Green blog, November 11, 2010. Retrieved November 11, 2010.
  41. ^ "Radioactive Tritium Found In New Well At Vermont Yankee". Vermont Public Radio. January 21, 2011. Retrieved March 16, 2011.
  42. ^ Wald, Matthew L. (January 19, 2012). "Judge Rules Vermont Can't Shut Nuclear Plant". New York Times. Retrieved January 24, 2013.
  43. ^ "PSB approves generator at Vermont Yankee". Brattleboro Reformer. June 7, 2013. Retrieved July 1, 2013.
  44. ^ "Entergy to Close, Decommission Vermont Yankee" (Press release). August 27, 2013. Archived from the original on September 28, 2013. Retrieved August 27, 2013.
  45. ^ David C. Brody, James R. Acker, Wayne A. Logan (2001). Criminal law Jones & Bartlett Publishers, p. 276.
  46. ^ "Eleven arrested in latest protest over Vermont Yankee". Timesargus.com. January 17, 2006. Archived from the original on March 3, 2016.
  47. ^ Barlow, Daniel (April 30, 2009). "Activists stage anti-nuclear rally". Vermonttoday.com. Archived from the original on February 23, 2012.
  48. ^ Anti-nuclear protesters reach capitol[dead link] Rutland Herald, January 14, 2010.
  49. ^ Wald, Matthew L., Vermont Senate Votes to Close Nuclear Plant The New York Times, February 24, 2010.
  50. ^ Entergy Makes Last Ditch Effort To Save Vermont Yankee Archived July 19, 2011, at the Wayback Machine WPTZ.com, February 22, 2010.
  51. ^ M. D. Drysdale, "New Leadership for Vt.'s Biggest Utility: CVPS's Reilly Not Worried About Vermont Yankee," The Herald of Randolph, April 21, 2011.
  52. ^ Wald, Matthew L., Vermont Nuclear Plant Up for Sale The New York Times, November 4, 2010.
  53. ^ "Entergy: No sale of Vermont Yankee". Burlington Free Press. March 30, 2011. Archived from the original on January 18, 2013.
  54. ^ "Vermont Yankee: Countdown to closure". WCAX. March 21, 2011. Archived from the original on March 9, 2012. Retrieved March 3, 2012.
  55. ^ NRC: Vermont Yankee Nuclear Power Plant ‘Good to Go’ for 20 More Years Forbes.com, March 22, 2011.
  56. ^ Wilson Ring (March 22, 2012). "130 arrested in Vermont Yankee protest". BusinessWeek. Archived from the original on October 19, 2015.
  57. ^ Wilson Ring (March 31, 2013). "Hundreds march in protest of Vermont Yankee plant". Boston.com. Associated Press.
  58. ^ Bill Dedman, "What are the odds? US nuke plants ranked by quake risk", NBC News News, March 17, 2011 Retrieved April 19, 2011.
  59. ^ Sheron, B. W. (September 2, 2010). "Safety assessment results...." Archived May 25, 2017, at the Wayback Machine MSNBC. p. D-6, Table D-1, "weakest link model" column.
  60. ^ "NRC: Backgrounder on Emergency Preparedness at Nuclear Power Plants". Nrc.gov. Archived from the original on October 2, 2006.
  61. ^ Bill Dedman, "Nuclear neighbors: Population rises near US reactors", NBC News, April 14, 2011 Accessed May 1, 2011.
  62. ^ "Vermont Yankee's 10-Mile Emergency Planning Zone Set To Expire". VPR News. April 18, 2016. Retrieved October 10, 2017.

See also

edit
edit