The Whitney Hill Wind Farm is a 24-turbine wind farm near Mount Pulaski in southeastern Logan County in the U.S. state of Illinois. The project was developed by Enel Green Power.[1]
Whitney Hill Wind Farm | |
---|---|
Country | USA |
Location | Mount Pulaski, Illinois |
Coordinates | 39°57′25″N 89°18′40″W / 39.95694°N 89.31111°W |
Status | Active |
Construction began | 2019 |
Owner | Enel Green Power |
Wind farm | |
Type | Onshore |
Power generation | |
Units operational | 21 x 2.8 MW, 3 x 2.3 MW |
Make and model | GE Renewable Energy |
Annual net output | 246GWh |
Detail
editThe Whitney Hill complex's 24 wind turbines were completed in December 2019.[2] The project was designed to generate a maximum of 65.3 megawatts of electricity.[3] The Whitney Hill complex utilizes leasehold rights to 5,000 acres of land.[1]
References
edit- ^ a b Blanchette, David (August 12, 2019). "Wind farm project starting in Mount Pulaski area". State Journal-Register. Springfield, Illinois. Retrieved October 25, 2022.
- ^ "Enel completes 66-MW Whitney Hill wind project in Illinois". windpowerengineering.co. Windpower Engineering & Development. Retrieved October 25, 2022.